Shenzhen Metro

The Shenzhen Metro (simplified Chinese: 深圳地铁; traditional Chinese: 深圳地鐵; pinyin: Shēnzhèn Dìtiě) is the rapid transit system for the city of Shenzhen in Guangdong province, China. The system opened on 28 December 2004. The network underwent major expansion prior to the 2011 Summer Universiade and with three new lines in 2016. The extension opened on 8 December 2019 put the network at 303.4 kilometres (188.5 miles) of trackage operating on 8 lines with 215 stations.[4] That made the Shenzhen Metro 7th longest in China and 12th longest in the world's List of metro systems on that date. By 2030 the network is planned to be 8 express and 24 non-express lines totalling 1142 kilometres of trackage.

Shenzhen Metro
Overview
LocaleShenzhen
Transit typeRapid transit
Number of linesEight: 123457911
Number of stations215[1]
Daily ridership5.5 million (2017)
6.63 million (2019 Peak)[2]
Annual ridership1.8775 billion (2018)[3]
WebsiteSZMC (Shenzhen Metro Group)
MTR Corporation (Shenzhen) (Chinese only)
Operation
Began operation28 December 2004 (2004-12-28)
Operator(s)
Technical
System length303.4 km (188.5 mi)[4]
Track gauge1,435 mm (4 ft 8 12 in) (Standard Gauge)
Top speed80 km/h (50 mph) (Line 1, 2, 4, 5, 7, 9)
85 km/h (53 mph) (Line 3)
120 km/h (75 mph) (Line 11)
System map

Shenzhen Metro
Simplified Chinese深圳地铁
Traditional Chinese深圳地鐵

History

Evolution of the Shenzhen metro

Early planning

In late 1983, Party Secretary of Shenzhen Mayor Liang Xiang led a team to Singapore to study its mass transit system. Upon returning it was decided that 30 meters on each side of Shennan Avenue should be protected as a green belt, and to set aside a 16-meter wide median reserved for a light rail or light metro line.[5] In 1984, the "Shenzhen Special Economic Zone Master Plan (1985–2000)" pointed out that, with the growing population and traffic in Shenzhen, a light metro system would not have sufficient capacity to meet future demand. Instead the report proposed a heavy rail subway line to be built along Shennan Avenue.[6] The project was finally approved by the Central Planning Department in 1992.[7]

In August 1992, during and re-feasibility and rail network planning, The Shenzhen Municipal Government decided to move from building a light metro line to a heavy rail subway line. The rapid growth of Shenzhen City made a lower capacity light metro line impractical.[8] In 1994, Shenzhen organized the preparation of the "Shenzhen urban rail network master plan" to be incorporated into the "Shenzhen City Master Plan (1996–2010)".[9] The city's vision for an urban rail network would consists of nine lines. Of the nine transit lines, three of them would be commuter rail lines upgraded from existing national mainline railways. The total length of the proposed network would be about 270 km. The three upgraded commuter rail lines would overlap the Guangzhou–Shenzhen railway, Pinghu–Nanshan railway and Pingyan railway.[9] This plan established the basic framework for the Shenzhen Metro network.[10]

Construction suspended and restarted

In December 1995, the State Council issued the "moratorium on approval of urban rapid transit projects" to suspend approval of rail transit projects in all Chinese cities except Beijing, Shanghai, and Guangzhou. The Shenzhen Metro project was postponed.[11] In 1996, prior to the handover of Hong Kong, authorities attempted to restart construction by renaming the project "The Luohu, Huanggang / Lok Ma Chau border crossing passenger rail connection project", stressing that the project is designed to meet the potential growing demand for cross-border passenger traffic after the handover.[9]

In 1997, Shenzhen reapplied its Subway plans to the State Planning Commission, and received approval in May 1998.[8] The project was renamed the "Shenzhen Metro first phase".[12] In July 1998, SZMC (Shenzhen Metro Group). was formally established.[12] By April 1999, the subway project feasibility study report has been approved by the state.

Phase I (1998-2004)

Construction of the first sections of Line 1 and Line 4 began in 1999. The grand opening of the Shenzhen Metro system occurred at 5:00pm on Tuesday, December 28, 2004. This made Shenzhen the seventh city in mainland China to have a subway after Beijing, Tianjin, Shanghai, Guangzhou, Dalian and Wuhan.

Initially the trains operated at 15-minute frequencies and consisted of Line 1 services between Luohu and Shijie Zhi Chuang (now Window of the World) and the Line 4 services between Fumin and Shaonian Gong (now Children's Palace). Initially the English names of the stations were rendered in Hanyu Pinyin, but some of the names were changed to English translation with American spelling in mid-2011.

The Futian Checkpoint station opened on 28 June 2007 using the name Huanggang.[13]

Name changes

On April 23, 2008, Shenzhen Municipal Planning Bureau announced that it would change the nomenclature of Shenzhen's subway lines according to the "2007 Urban Rail Transit Plan Scheme". Instead of using numbers as the lines official designation, as typically used in other mainland Chinese metro systems, lines would be given Chinese names more akin to the Hong Kong MTR.[14] In 2010, the Scheme was reviewed and adjusted with new routes and names in addition to newly proposed lines. On 23 October 2013, the SZMC (Shenzhen Metro Group) decided that current operational lines will have their number and names combined, while future lines will only be numbered.[15] Due to the change in the construction order of several lines, some numerical names have been reviewed in order to prevent big jump between numbers. By 2016, only numerical names are used.

Lines currently in operation:

Original No. 2007 Scheme 2010 Scheme Current name
Line 1Luobao LineLuobao Line (Line 1) Line 1
Line 2Shekou LineShekou Line (Line 2) Line 2
Line 3Longgang LineLonggang Line (Line 3) Line 3
Line 4Longhua LineLonghua Line (Line 4) Line 4
Line 5Huanzhong LineHuanzhong Line (Line 5) Line 5
Line 7Xili LineXili Line (Line 7) Line 7
Line 9Neihuan LineMeilin Line (Line 9) Line 9
Line 11Airport LineAirport Line (Line 11) Line 11

Lines under construction:

Original No. 2007 Scheme 2010 Scheme Current Name
Line 8Yantian LineYantian Line (Line 8) Line 2 Extension (Line 8 Phase 1)
Line 16Pinghu LineBantian Line (Line 16/Line 10) Line 10
Line 10Bao'an LineNanbao Line (Line 10/Line 12) Line 12
Line 15Shiyan LineShiyan Line (Line 15/Line 13) Line 13
Line 14Eastern ExpressEastern Express (Line 14) Line 14
Line 12Pingshan LineLongping Line (Line 12/Line 16) Line 16
--Fuyong Line (Line 20) Line 20 (International Expo Conveyance Project)

Phase II (2007-2011)

From 2004 to 2007, there was a lack of official government interest and attention to expanding the subway after completion of Phase 1 with little or no active projects.[16] Subway construction speed was ridiculed as "earthworm speed".[17] On 17 January 2007 Shenzhen won the right to host the 2011 Universiade. In the bid Shenzhen committed to complete 155 km of subway lines before the games.[16] The mayor of Shenzhen at the time, Xu Zongheng, sharply criticized the speed and efficiency of Shenzhen's subway construction procedures and calls for reform.[18] Subsequently, the Shenzhen municipal government and various departments signed a liability form, requiring Phase II subway expansion to be completed in time for the Universiade.[19] Shenzhen Metro increased to over a hundred operating metro stations in June 2011, just before the Shenzhen Universiade games. In the span of two weeks, the network expanded from 64 km to 177 km. This expansion increased rail transit's share of total public transit trips from 6% to 29% in 2014.[20][21][22][23]

Date Opened
Line
Termini
Length
in km
Stations
28 September 2009
  Line 1
- section 2 (trial)
Window of the World Shenzhen University 3.39 3
28 December 2010
  Line 2
- phase 1
Chiwan Window of the World 15.1 12
  Line 3
- phase 1
Shuanglong Caopu 25.6 16
15 June 2011
  Line 1
- section 2
Shenzhen University Airport East 23.6 12
16 June 2011
  Line 4
- phase 2 (first north extension)
Children's Palace Qinghu 15.9 10
22 June 2011
  Line 5
Qianhaiwan Huangbeiling 40.0 27
28 June 2011
  Line 2
- phase 2 (first east extension)
Window of the World Xinxiu 20.65 17
  Line 3
- phase 2 (first south extension)
Caopu Yitian 16.52 14

Phase III (2012-2020)

In 2010, the Shenzhen Urban Planning and Land Resources Committee proposed a building program (Phase III) between 2011 and 2020. In 2011 this plan was approved by the NDRC. Phase III formally commenced in May 2011 with an expected cost of 125.6 billion yuan. It will cover Lines 6, 7, 8, 9, and 11 and will extend the length of the Shenzhen Metro to 348 kilometres and 10 lines.[24][25] In June 2011, the Shenzhen Urban Planning and Land Resources Commission started gather public input on Phase III station names.[26] On June 30, 2016 Line 11 opened being the first subway line in Shenzhen with 8 car trains and 120 km/h maximum service speed and the first in China with a First Class service. Lines 7 and 9 followed on October 28, 2016 bringing the length of the Shenzhen Metro to 285 km and the third longest in China.

Date Opened
Line
Termini
Length
in km
Stations
28 June 2016 Futian Bitou 51.936 18
28 October 2016
  Line 7
Tai'an Xili Lake 30.173 28
  Line 9
- phase 1
Wenjin Hongshuwan South 25.38 22

Phase III revised expansion

Date Opened
Line
Termini
Length
in km
Stations
28 September 2019
  Line 5
- phase 2
Qianhaiwan Chiwan 7.65[27] 7
8 December 2019
  Line 9
- phase 2
Hongshuwan South Qianwan 10.79[28] 10

Current system

The extension opened on 8 December 2019 put the network at 303.4 kilometres (188.5 miles)[4] of trackage operating on 8 lines with 215 stations. That made the Shenzhen Metro 7th longest in China and 12th longest in the world's List of metro systems on that date. Shenzhen metro provides a relatively quick and economical way of travelling in Shenzhen compared to buses and taxis. Line 1 and Line 4 run to the border crossings between the Shenzhen Special Economic Zone and the Hong Kong Special Administrative Region at Luohu/Lo Wu and Futian Checkpoint/Lok Ma Chau, where riders can transfer to Hong Kong's MTR East Rail line for travel onward to Hong Kong.

Line Terminals
(District)
Service patterns Commencement Latest
extension
Length
km
Stations Operator
011 Luohu
(Luohu)
Airport East
(Bao'an)
LuohuAirport East
Rush Hour: LuohuXixiang
Partial:LuohuZhuzilin
2004 2011 41.04 30
Shenzhen Metro Group
022 Chiwan
(Nanshan)
Xinxiu
(Luohu)
ChiwanXinxiu
AM Rush Hour: WanxiaXinxiu
Partial:HouhaiXinxiu
2010 2011 35.78 29
033 Yitian
(Futian)
Shuanglong
(Longgang)
YitianShuanglong
Rush Hour: HuaxinTangkeng
Partial:YitianTangkeng
2010 2011 41.66 30
044 Futian Checkpoint
(Futian)
Qinghu
(Longhua)
Futian CheckpointQinghu
AM Rush Hour: Futian CheckpointHongshan
2004 2011 19.96 15
MTR Corporation (Shenzhen)
055 Chiwan
(Nanshan)
Huangbeiling
(Luohu)
ChiwanHuangbeiling
Partial:ChanglingpiChiwan
ChanglingpiHuangbeiling
2011 2019 47.393[29] 34
Shenzhen Metro Group
07

7

Xili Lake
(Nanshan)
Tai'an
(Luohu)
Xili LakeTai'an
Partial:Antuo HillTai'an/XiliTai'an
2016 30.173[30] 27
09

9

Qianwan
(Nanshan)
Wenjin
(Luohu)
QianwanWenjin
Partial:Shenzhen Bay ParkWenjin
2016 2019 36.18 32
11

11

Futian
(Futian)
Bitou
(Bao'an)
FutianBitou
Partial:FutianSonggang
AM Rush Hour: FutianAirport North
2016 51.94 18
Total 303.4[4] 215

Line 1

Line 1 formerly known as the Luobao line runs westward from Luohu to Airport East. Trains operate every 2 minutes during peak hours and every 4 minutes at other times. The line is operated by SZMC (Shenzhen Metro Group).

Line 2

Line 2 formerly known as the Shekou line runs from Chiwan to Xinxiu. It connects with Line 1 at Window of the World, with Line 4 at Civic Center, with Line 3 at Futian and with Line 1 again at Grand Theater. The line is operated by SZMC (Shenzhen Metro Group).

Line 3

Line 3 formerly known as the Longgang line runs from Yitian to Shuanlong in Longgang, in the north-east part of the city. Construction began on 26 December 2005.[33] The line is operated by Shenzhen Metro Line 3 Operations, which has been a subsidiary of SZMC (Shenzhen Metro Group) since 11 April 2011 when an 80% stake was transferred to SZMC.

Line 4

Line 4 formerly known as the Longhua line runs northward from Futian Checkpoint to Qinghu. Trains operate every 2.5 minutes at peak hours and every 6 minutes during off-peak hours. Stations from Futian Checkpoint to Shangmeilin Station are underground. The line has been operated by MTR Corporation (Shenzhen), a subsidiary of MTR Corporation, since 1 July 2010.

Line 5

Line 5 formerly known as the Huanzhong line runs from Chiwan in the west to Huangbeiling in the east. Construction began in May 2009 and the line opened on 22 June 2011.[35] Line 5 required a total investment of 20.6 billion RMB. The line is operated by SZMC (Shenzhen Metro Group).

Line 7

Line 7 formerly known as the Xili line of the Shenzhen Metro opened on 28 October 2016, with a length of 30.173 km[30] and a total of 27 stations. It connects the Xili Lake to Tai'an. The line travels East–West across Shenzhen in a "V" shape. The line is operated by SZMC (Shenzhen Metro Group).

Line 9

Line 9 formerly known as the Meilin line or Neihuan line of the Shenzhen Metro opened on 28 October 2016. The line runs eastward from Qianwan to Wenjin. It has 10 transfer stations. The line is 36.18 km long, running through the districts of Nanshan, Futian and Luohu. The line is operated by SZMC (Shenzhen Metro Group).

Line 11

Line 11, also known as the Airport Express, runs from Bitou in the north-east to Futian in the city centre via Shenzhen Bao'an International Airport. Construction began in April 2012 and the line opened on 28 June 2016. Line 11 runs at a higher speed of 120 km/h. The line is operated by SZMC (Shenzhen Metro Group).

Future expansion

Phase III revised expansion

Anticipated development and growth in Longgang has prompted officials to fast-track the planning and construction of Line 10 (formerly Line 16), from Futian Free Trade Zone to Pinghu via Meilin, to start in 2015 instead of after 2020.[36][37][38] Although Line 10 is not part of the original three projects (Lines 7, 9 and 11) approved by the National Development and Reform Commission, the project was fast tracked in order to ease the pressure on Line 4 and accommodate further growth of the Longgang area.[39][40] According to the original plan, the northern section of Line 10 runs through Fenggang town of the neighboring Dongguan City. Due to legal and government coordination problems, Line 10 will temporarily terminate in Pinghu, with capability to extend further north into Dongguan.[41] In addition, extension projects of Line 2, 3, 4, 5, 6 and 9, a total of 83.9 km of new subway, were added to the revised plan.[42]

Expected Opening
Line
Expected Terminals
Expected Length
in km
Expected Stations
Current Status
August 2020[43]
  Line 6
- phase 1 & 2
Science Museum Songgang 49.4[44] 27[44] Under construction[45][46][47][48]
Futian Checkpoint Shuangyong Street 29.3[49] 24 Under construction[46][50][51]
October 2020[43]
  Line 3
- phase 3 (second south extension)
Yitian Fubao 1.5 1 Under construction[52][53]
  Line 4
- phase 3 (second north extension)
Qinghu Niuhu 10.791[54] 8 Under construction[52][55][56]
  Line 8
- phase 1
Liantang Yantian Road 12.367[57] 7 Under construction[58][59]
  Line 2
- phase 3 (second east extension)
Xinxiu Liantang 3.82 3 Under construction[60][52][55]
A map with Third phase lines.

Phase IV & Phase IV revised expansion

With the shortening of the Phase III implementation period,[61] a number of lines (Lines 16 and 12) planned in 2007's Phase III moved into the next phase which could possibly be completed by 2020.[62] By 2016, it was determined that Phase 4 will have an implementation period between 2017 and 2022 and consist of 274 km of new subway.[63] Lines 13 and 14 which originally had a long term 2030 completion deadline were moved to Phase IV expansion. In addition, a branch line of Line 6 will connect with the neighboring Dongguan Rail Transit system.[64] Lines 12, 13, 14, and 16 and branch of Line 6 started construction in January 2018.[23] The first phase of Line 20 was fast tracked from Phase IV to provide a shuttle between Line 11 and a new International Convention Center. The construction started in September 2016, but as for early 2019, the construction is paused because the Development and Reform Commission did not approve the project.

A map with fourth phase lines.


Phase IV expansion

Line 12, 13, 14, 16, and the branch of Line 6 was approved by the NDRC in July 2017.[65]

Expected opening
Line
Expected terminals
Expected length
in km
Expected stations
Current status
2022 Zuopaotai Haishangtianyuan East 40.54 33 Under construction[23][66][67]
Shenzhen Bay Checkpoint Shangwu 22.45 16 Under construction[23][64][68][69][70]
Gangxia North Shatian 50.3[23] 17[23] Under construction[23]
  Line 6
Branch
Cuihu Sun Yat-sen University 6.4 3 Under construction[23][64]
2023 Universiade Tianxin 29.2 24 Under construction[23][71][72]
2024
  Line 8
Phase 2
Yantian Road Xiaomeisha 8.025 4 Under Construction[73]
2025
  Line 5
West Extension (Phase 1 remaining section)
Huangbeiling Grand Theater 2.87 3 Under Construction[74]

Phase IV revised expansion

The Phase IV revised plan approved by the NDRC on March 26, 2020.[75]

Expected opening
Line
Expected terminals
Expected length
in km
Expected stations
Current status
References
TBA
  Line 3
- phase 4 (east extension)
Shuanglong Pingdi Liulian 9.35 7 Planned [75]
  Line 6
Branch south extension
Guangmingcheng Cuihu 4.9 3 Planned
  Line 7
- East extension
Xili Lake Xuefu Hospital 2.45 2 Planned
  Line 8
- Phase 3
Xiaomeisha Xichong 4.26 1 Planned
East Extension Futian Hongling South 5.58 3 Planned
- North extension Haishangtianyuan East Songgang 8.16 5 Planned
- North extension Shangwu North Gongming North 18.8 11 Planned
- South extension Shenzhen Bay Checkpoint Dongjiaotou 4.47 3 Planned
- South extension Universiade Xikeng 9.53 9 Planned
- North section Airport North International Conference Center 8.43 5 Construction paused

    Long-term plan

    In the Shenzhen Metro 2007 masterplan proposed four more lines (Lines 13, 14, 15 and 16) which have a planned completion target of 2030.[76] In 2016, all aforementioned lines but Line 15 were designated as part of the Phase IV expansion, moving the completion date forward from 2030 to 2022. In 2012, four further lines Qiannan (Line 17), Pinghu (Line 18), Pingshan (Line 19) and Fuyong (Line 20) where unveiled, making the total planned length of the Shenzhen Metro to 720 km spread out over 20 lines. The first phase of Line 20 was fast-tracked and included in the Phase III revised expansion with a completion date of 2018. This leaves Line 15, 17-19 and the rest of Line 20 available for the next phase (Phase V) of subway expansion. Aside from the set masterplan, at the 12th Guangdong Provincial People's Congress in January 2014,[77] it was proposed to extend Line 4 beyond the planned Phase III terminus at the Songyuan Bus Terminal in Guanlan. The proposal wanted to further extend this line to reach the future planned Dongguan Metro Line 4 at Tangxia station. This proposal aims to shorten the distance between the two cities in residents' minds, boost tourism industries in both cities and expand housing options. It would also allow for direct connection between Hong Kong and Dongguan. As the area in the proposed area is less developed, the cost in building the line is expected to be lower, with a feasibility study yet to be conducted. In addition to metro lines, 5 Pearl River Delta Rapid Transit lines connecting neighboring urban centers in the Pearl River Delta such as Dongguan, Huizhou, Foshan and Guangzhou, totaling 146 km, have also been revealed.[78] In 2016, an even more ambitious masterplan, expanding the previously planned 20 lines to 32, was unveiled. The new plan envisions a 1142 km subway network to be completed by 2030. This will allow for travel between the central and suburban districts to be shortened to 45 minutes and for public transit to make up more than 70% of all motorized trips in Shenzhen.[79]

    Expected opening
    Line
    Expected terminals
    Expected length
    in km
    Expected stations
    Current status
    TBA Bao'an-Longgang line Shiyan Buji East TBC TBC Planned
    107 line Hongshuwan South Xitou TBC TBC Planned
      Line 15
    Dachan Bay Mawan TBC TBC Planned
    Luohu Pinghu 28.7 24 Planned[80]
      Line 21
    TBC TBC TBC TBC Planned
      Line 22
    Shangsha Guanlan North TBC TBC Planned
      Line 24
    Laojie Mawan TBC TBC Planned

    Ridership

    Annual Ridership
    Yearmillion riders±% p.a.
    2005[81] 58    
    2006[82] 90+55.17%
    2007[83] 118+31.11%
    2008[84] 136+15.25%
    2009[85] 138+1.47%
    2010[86] 163+18.12%
    2011[87] 460+182.21%
    2012[88] 781+69.78%
    2013[89] 914+17.03%
    2014[20]1,037+13.46%
    2015[90] 1,122+8.20%
    2016[91]1,297+15.60%
    2017[92] 1,654+27.53%
    2018[93] 1,878+13.54%

    Since the opening of the first phase in 2004, there has been a steady growth in passenger traffic. In 2009 and 2010, passenger traffic soared with major openings of new phase 2 lines, with a three-fold increase in passenger traffic in 2010.[94] On 12 July 2019 it set a new record for its peak ridership at 6.63 million.[2]

    July is the busiest month of the year for the Shenzhen Metro, accounting for 9.3% of annual passenger traffic, while January is the least busy month, accounting for only 6.7%. This is caused by Shenzhen's large migrant worker population.[95]

    Fares and tickets

    Metro rides are priced according to distance travelled, and fares vary from 2 RMB to 14 RMB.[96] Since December 2010 fares are based on a usage fee (2 RMB) + a distance fee. The distance fee is 1 RMB for each 4 km from 4 km to 12 km; after that 1 RMB for each 6 km from 12 km to 24 km and finally 1 RMB for every 8 km over 24 km distance.[97] For passengers who wish to ride on business coach in line 11, they have to pay 3 times the amount of price that calculated by the regulations above.

    Distance (km)Fares (RMB) [98]
    0~121+1/per 4 km
    12~245+1/per 6 km
    over 247+1/per 8 km

    Children under the height of 120 cm or aged below 6 may ride for free when accompanied by an adult.[99] The metro also offers free rides to senior citizens over the age of 65, the physically disabled and military personnel. Tickets for children between 120 cm and 150 cm, or aged between 6 and 14 years, or middle school students, are half priced.

    Metro fares can be paid for with single-ride tokens, multiple-ride Shenzhen Tong cards or 1- day passes.[100]

    Tokens

    Shenzhen Metro RFID Token

    When using cash, a RFID token (NXP Mifare Classic) is purchased and used for a single, non-returnable journey. There are two different types of tokens, with green tokens for Standard Class, and yellow tokens used for Business Class which is only available on Line 11. All ticket vending machines offer both English and Chinese interface. The purchaser touches a station name to calculate the fare. After payment, a green token is dispensed, which must be scanned at the entrance station and deposited at the exit station. A penalty applies should a token be lost. Purchasers of green tokens cannot ride Business Class on Line 11 directly. Instead, they must get off at any transfer stations with Line 11 and purchase a separate yellow token.

    Note that as of 2015, many machines accept only 5 or 10 RMB notes. The token(s) are only valid at the station where issued. Passengers are unable to buy an extra token for return journey prior to departure. Baggage X-Ray machines are located at each station, and may be manned during peak hours.

    Shenzhen Tong cards

    Shenzhen Tong is a pre-paid currency card similar to Oyster Card system in London and the Octopus card system used in Hong Kong. The multiple fare card stores credit purchased at stations. The card can be used by waving it in front of the card reader located at all entrances and exits to the subway system. Riders who pay for metro fare with a card receive a 5% discount. Since March 1, 2008, riders who pay for a bus fare with a card and then a subway fare within 90 minutes receive an additional 0.4 RMB discount on the subway fare. Card users pay a distance based fare.

    Since June 30, 2011, cards containing both a Shenzhen Tong and Hong Kong Octopus chip have been available in both Shenzhen and Hong Kong. There are plans to further integrate the two systems, and for a new card which will be accepted all over Guangdong province and China's two SARs.[101][102]

    Unlike Hong Kong Octopus Cards, Shenzhen Tong cards cannot be sold back to the stations or have faults dealt with by SZMC. Instead, the customer must go to the offices of Shenzhen Tong. Students studying in Shenzhen can use the Shenzhen Tong to receive a 50% discount.

    Note that all sorts of discounts will not applicable for people who wish to ride business coach in line 11.

    Metro cards can also be used on Shenzhen's public bus system.

    Metro 1-day passes

    Metro 1-day pass is a smart card that allowed the card holder have unlimited access of the metro system in 24 continuous hours. Passengers can purchase a 1-day pass for RMB 25 in the service center in any metro station. The pass will be activated and the passenger will have 24 continuous hour for unlimited access after the first entrance. When the pass expired, the pass is no longer available for entering a station but able to exiting a station and finish a journey in 27.5 hours. The 1-day passes are not applicable for business coach in line 11.

    Station facilities, amenities and services

    Some stations have toilets (free of charge), and public telephones. SZMC also operates luggage storage facilities in the concourse above Luohu Station. Mobile phone service is available throughout the system provided by China Mobile, China Telecom, and China Unicom.[103]

    Like the Hong Kong MTR, Guangzhou, and Foshan metros, station announcements are in Mandarin, Cantonese and English. Some announcements, such as train arrival, are in Mandarin and English only. Cantonese, an important local language, is chosen for the local Cantonese population as well as Cantonese speakers in Guangdong, Hong Kong and Macau.

    Equipment

    Bombardier rolling stock on Line 1
    CRRC Nanjing Puzhen rolling stock on Line 4
    CRRC Zhuzhou rolling stock on Line 11 (Business Class)

    Rolling stock

    Line 1

    • 22 Bombardier Transportation Movia 456 6-car sets (101–122)
    • 4 Changchun Railway Vehicles Type A 6-car sets, traction units by Bombardier Transportation (123–126)
    • 26 Zhuzhou Electric Locomotive Works Type A 6-car sets, traction units by Siemens (127–152)
    • 33 Zhuzhou Electric Locomotive Works Type A 6-car sets, traction units by CSR Times Electric. (153-185)

    Line 2

    • 35 Changchun Railway Vehicles Type A 6-car sets, traction units by Bombardier Transportation (201–235)
    • 17 Changchun Railway Vehicles Type A 6-car sets, traction units by Bombardier Transportation (236-252)

    Line 3

    • 43 Changchun Railway Vehicles Type B 6-car sets, traction units by Hyundai Rotem (301-343)
    • 33 Nanjing Puzhen Rolling Stock Works Type B 6-car sets, traction units by Hyundai Rotem (344-376)

    Line 4

    • 28 Nanjing Puzhen Rolling Stock Works Type A 6-car sets (401-428)

    Line 5

    • 22 Zhuzhou Electric Locomotive Works Type A 6-car sets, traction units by Siemens (501–522)
    • 8 Zhuzhou Electric Locomotive Works Type A 6-car sets, traction units by CSR Times Electric (523–530)
    • 21 Changchun Railway Vehicles Type A 6-car sets (531-551)

    Line 7

    • 41 Changchun Railway Vehicles Type A 6-car sets, traction units by Bombardier Transportation (701-741)

    Line 9

    • 29 Changchun Railway Vehicles Type A 6-car sets (901-929)

    Line 11

    • 33 Zhuzhou Electric Locomotive Works Type A 8-car sets (1101-1133)

    Signalling system

    On Line 1 and Line 4, Siemens Transportation Systems supplied 7 (Phase 1) and 6 (Phase 2) LZB 700 M continuous automatic control systems; 7 (Phase 1) and 6 (Phase 2) electronic Sicas ESTT interlockings; the Vicos OC 501 operations control system with 2 operations control centers, fall-back level with Vicos OC 101 and RTU (FEP), 230 (Phase 1) and 240 (Phase 2) FTG S track vacancy detection units.[104]

    Line 2 and Line 5 use Casco CBTC system with 2.4 GHz frequencies, and so the system has suffered frequent problems with interference from consumer Wi-Fi equipment.[105] By the end of November 2012, CASCO solved the problem on Lines 2 and 5 by switching to their standard solution with frequency diversity on 2 different channels.

    Accidents and incidents

    • 4 April 2011 — One worker was killed and four others injured on April 4 when a manually controlled chain hoist broke loose in a Line 5 tunnel in Longgang district. A preliminary investigation by district safety authorities found mechanical failure was to blame.[106]
    • 5 September 2012 — Service was suspended on Line 4 for several hours due to power outage.[107]
    • 9 September 2013 – Three passengers abandoned in Line 1 tunnel after train door opens.[108]
    • 17 February 2014 – Passenger passes out at Shuiwan station on Line 2 and dies after no help or CPR is provided for 50 minutes.[109]
    • 25 June 2015 – Worker killed during tunnel collapse in Line 7 construction.[110]
    • 19 April 2017 — Scaffolding for a metro station collapsed during the construction of the Line 8 on Yantian Rd, killing a worker and injuring three.[111]
    • 11 May 2017 — During the construction of the extension of Line 3 heavy rains caused a partial cave in at an excavation pit for a station on the southern extension of Line 3, killing 2 workers and injuring another.[112]
    • 30 October 2017 — A section of Line 9 tunnel near Shenzhen Bay Park station was damaged by unauthorized community drilling works above ground. While the damage was soon repaired, the line continued to operate at a lowered safety speed of 45 km/h for a week.[113]
    • 6 December 2017 — Unauthorized drilling works for an adjacent bouldering site damaged the tunnel between Houhai and Hongshuwan South station of Line 11, causing sections of tunnel to make contact with a train and the driver to sustain minor injuries. The service of the line was disrupted for 12 hours while the line operated on modified routes, until the damage was fully repaired.[114]
    • 23 December 2017 — A Line 11 train killed a suicidal man lying on the rails between Bihaiwan and Airport, disrupting the service for 80 minutes.[115]
    • 5-7 July 2018 — Over a span of three days, at least seven incidents occurred, where power cables were accidentally cut at various construction sites of Shenzhen Metro, causing blackouts in large areas.[116]
    • 10 July 2018 — During the construction of Line 10, workers accidentally dug up the pipes of Shenzhen Buji Water Supply Co., Ltd., disrupting water distribution system. The Shenzhen Economic and Information Commission warned and penalized the contractor responsible.[117]
    • Since 9 February 2020 – Service between Futian and Xinxiu on Line 2 was suspended due to geographic movement caused by the construction of Line 14.[118]

    See also

    References

    1. "Shenzhen Metro". exploremetro. Retrieved May 27, 2014.
    2. "Shenzhen to Open 3 New Metro Lines by 2020". thatsmags.com. August 2, 2019.
    3. "创历史新高!21日深圳地铁总客流量达646.9万人次". stnn.cc. July 21, 2018.
    4. "两条地铁线纵横交会 前海轨道交通网加密". 地铁9号线二期开通后,深圳地铁线网总里程将达到303.4公里
    5. 彭森 (August 21, 2005). "从7米到140米——深南大道的宽度之谜" (in Chinese). 深圳晚报.
    6. 深圳经济特区总体规划简介[J]. 城市规划,1986,06:9–14.
    7. 深圳市地铁有限公司 (2007). 深圳地铁一期工程建设与管理实践.上册 (in Chinese). 北京: 人民交通出版社. ISBN 978-7-114-06262-9.
    8. "深圳地铁十年始获"出生证"" (in Chinese). 深圳新闻网. June 22, 2011.
    9. 张家识 (1999). "深圳地铁一期工程建设前期工作回顾". In 陈锡贤 (ed.). 地下铁道文集:中国土木工程学会隧道及地下工程分会地下铁道专业委员会第十三届学术交流会论文选 (in Chinese). 深圳: 海天出版社. ISBN 7-80615-959-2.
    10. "深圳地铁网络框架15年前基本敲定" (in Chinese). 深圳特区报. June 25, 2011. Archived from the original on September 14, 2014.
    11. "深圳地铁"十年怀胎"终圆梦". 深圳特区报. April 10, 2010. Archived from the original on January 6, 2016.
    12. "深圳地鐵一期工程主要里程碑時間" (in Chinese). 深圳新闻网. Archived from the original on December 2, 2012.
    13. "深圳地铁皇岗站正式开通" (in Chinese). Archived from the original on September 30, 2007. Retrieved July 1, 2007.
    14. "關於我市近期建設地鐵線路及站點命名的通告" (in Chinese). Archived from the original on December 2, 2012. Retrieved November 22, 2012.
    15. "New Line Naming Scheme". Shenzhen Metro Group Official Weibo. Shenzhen Metro Group. Retrieved October 23, 2013.
    16. "地铁不如期完工,我主动请求处分". 南方日报. February 1, 2007.
    17. "网友声讨"进度慢",市长强调"拖不起",地铁建设"蚯蚓速度"". 南方日报. January 19, 2007.
    18. ""地铁不如期完工,我主动请求处分"_新闻中心_新浪网". news.sina.com.cn. Retrieved October 30, 2016.
    19. "2011年5地铁贯通深圳-搜狐新闻". news.sohu.com. Retrieved October 30, 2016.
    20. "2014年度全市交通运输运营主要概况及分析" (in Chinese). Retrieved January 16, 2015.
    21. ""【深圳】2011年地铁达177公里 长过香港地铁" 星岛网讯" (in Chinese). Archived from the original on September 23, 2013.
    22. SZMC, Curstomer Service Center. "Shenzhen metro - Update - August 2017". www.szmc.net. SZMC. Retrieved August 29, 2017.
    23. L_104026. "深圳5条地铁线路同时开工 2022年底建成通车--深圳频道--人民网". sz.people.com.cn. Retrieved February 8, 2018.
    24. "City to spend 48b yuan on 3 Metro lines". Shenzhen Daily. Retrieved July 28, 2012.
    25. "The Shenzhen urban rail transportation recent construction plan approval (2011–2016)". National Development and Reform Commission. Retrieved August 27, 2012.
    26. "Public notice (draft)". Shenzhen Urban Planning and Land Resources Committee. Archived from the original on September 19, 2012. Retrieved August 27, 2012.
    27. "历经四年多的建设 地铁5号线二期工程今年9月底正式开通!". June 17, 2019.
    28. "深圳地铁5号线南延线和9号线西延线具备通车条件啦!". November 21, 2018.
    29. "约起!深圳地铁5号线二期9月28日开通". 5号线运营总里程将延长至47.393公里
    30. "深圳地铁7、9号线试运营 轨道网络规模居国内第三". October 28, 2016.
    31. Shenzhen Metro Line 1, from Luohu to Airport East was put into a trial operation
    32. photo of ongoing construction in Shekou Archived September 25, 2013, at the Wayback Machine
    33. (Chinese) Wang, Xiaoqing (王晓晴) and Qiu, Gang (邱刚), "深圳地铁3号线动工 2009年建成通车" southcn.com December 27, 2005
    34. (Chinese) 深圳地铁3号线规划线路图 August 21, 2008
    35. (Chinese) Wang, Xiaoqing (王晓晴) "深圳地铁5号线全面开工" Xinhua September 19, 2008
    36. "龙岗加快地铁16号线建设准备". 深圳商报. Archived from the original on August 29, 2011. Retrieved August 27, 2012.
    37. "地铁16号线 2014年初开工". 深圳商报. Archived from the original on March 19, 2012. Retrieved August 27, 2012.
    38. SZ to advance Metro Line 16 work-szdaily多媒体数字报刊平台
    39. "深圳交委称早7点以前或实行地铁票价优惠". 南方网. December 5, 2012. Archived from the original on December 4, 2014.
    40. "我市召开轨道交通建设指挥部会议,地铁16号线有望提前开工". 深圳市交通运输委员会. January 7, 2013. Archived from the original on January 4, 2015.
    41. "市地铁集团首席规划师刘卡丁:16号线力争提前建设,暂时不到龙岗中心城". 南方日报. December 5, 2012.
    42. "地铁10号线 终点在平湖---深圳都市报". dtzbd.sznews.com. Archived from the original on February 25, 2014. Retrieved January 4, 2017.
    43. "深圳2020年轨道建设清单来了 你关心的这几条线都安排上了". January 2, 2020.
    44. "地铁6号线全线贯通 明年年中光明通地铁". August 30, 2019.
    45. "深圳地铁6号线拟年底开建 11号线预计后年通车". 搜房网. June 10, 2014.
    46. 地铁6号线10号线预计2019年通车-深圳晚报
    47. "地铁6号线10号线预计2019年通车".
    48. 刘世雄,陈福贵 (2013). "深圳地铁6号线运营成本测算研究". 现代城市轨道交通. 1.
    49. "地铁6号、10号线传喜讯,计划明年年中迎客". December 3, 2019.
    50. 地铁10号线预计本月开工|10号线|地铁|轨道_新浪新闻
    51. 深圳地铁10号线拟年底开工 2019年12月开通
    52. "深圳地铁7,9,11号线明年开通 今年将增加铁路始发列车". 本地宝. March 31, 2015. Retrieved April 7, 2015.
    53. http://jt.sz.bendibao.com/news/2016617/772214_2.htm
    54. "地铁4号线北延线明年年底通车 清湖至松元厦区间隧道提前贯通". June 22, 2019.
    55. "8号线用磁悬浮相对经济 现有线路除1号线外都要延长". 深圳晚报. February 19, 2014. Retrieved February 19, 2014.
    56. "深圳地铁4号线北延线正式施工 各大站点示意图曝光 - 深圳本地宝". jt.sz.bendibao.com. Retrieved September 18, 2016.
    57. "深圳地铁8号线开始铺设轨道,盐田2020年进入地铁时代". August 1, 2019.
    58. http://www.newsgd.com/news/2017-11/15/content_178854309.htm
    59. 深圳地铁6条延长线线路图!看看哪些经过你家 - 深圳本地宝
    60. http://jt.sz.bendibao.com/news/2016617/772214.htm
    61. "未来五年深圳再建五条地铁". 南方都市报. Archived from the original on December 3, 2012. Retrieved August 27, 2012.
    62. "轨道交通近期建设规划方案". Shenzhen Urban Planning and Land Resources Committee. Archived from the original on November 29, 2012. Retrieved August 27, 2012.
    63. http://www.sutpc.com/ad.asp
    64. "深圳地铁四期规划来了!新增5条线,与东莞地铁对接方案出炉 - 市场 -深圳乐居网". sz.house.sina.com.cn. Retrieved January 4, 2017.
    65. "国家发展改革委关于深圳市城市轨道交通第四期建设规划(2017-2022年)的批复". July 7, 2017.
    66. "深圳地铁12号线最快明年开工建设 工期5年 - 深圳本地宝". jt.sz.bendibao.com. Retrieved October 28, 2016.
    67. "深圳地铁12号线新消息!站点公布,预计2022年竣工_广深新闻_新闻_星岛环球网". news.stnn.cc (in Chinese). Retrieved August 6, 2018.
    68. "深圳湾口岸直通地铁!快来看13号线最新进展!_广深新闻_新闻_星岛环球网". news.stnn.cc (in Chinese). Retrieved August 6, 2018.
    69. "深圳地铁13号线9个站点完成驻地建设,计划2021年开通_启动". www.sohu.com. Retrieved December 8, 2018.
    70. "深圳地铁12号线预计2022年建成通车-新华网". www.gd.xinhuanet.com. Retrieved September 28, 2019.
    71. "深圳地铁16号线最新进展!将于2023年投入运营_广深新闻_新闻_星岛环球网". news.stnn.cc (in Chinese). Retrieved August 6, 2018.
    72. "深圳地铁16号线进入主体施工阶段 2023年建成通车_证券时报网". kuaixun.stcn.com. Retrieved December 8, 2018.
    73. "深圳地铁两新线同日开建 _大公网". www.takungpao.com. Retrieved August 13, 2019.
    74. "深圳地铁5号线西延线工程开工-新华网". www.xinhuanet.com. Retrieved August 13, 2019.
    75. "国家发展改革委关于调整深圳市城市轨道交通第四期建设规划方案的批复". March 26, 2020. Retrieved April 26, 2020.
    76. "轨道线网规划方案". Shenzhen Urban Planning and Land Resources Committee. Archived from the original on November 30, 2012. Retrieved November 21, 2012.
    77. "Dongguan Metro connection called for". Shenzhen Daily. Retrieved January 22, 2014.
    78. "Four more Metro lines planned". Shenzhen Daily. Retrieved November 21, 2012.
    79. "关于地铁2号线东延线、地铁3号线西延线线站位初步方案" (PDF).
    80. "深圳地铁17号线什么时候开工? - 深圳本地宝". jt.sz.bendibao.com. Retrieved September 18, 2016.
    81. 深圳市统计局. "2005年度12月份深圳统计月报:运输邮电:地铁客流量1-12月累计" (in Chinese). Archived from the original on January 25, 2013.
    82. 深圳市统计局 (December 2, 2008). "深圳市2006年国民经济和社会发展统计公报" (in Chinese).
    83. 深圳市统计局 (December 2, 2008). "深圳市2007年国民经济和社会发展统计公报" (in Chinese).
    84. 深圳市统计局 (March 24, 2009). "深圳市2008年国民经济和社会发展统计公报" (in Chinese).
    85. 深圳市统计局 (April 27, 2010). "深圳市2009年国民经济和社会发展统计公报" (in Chinese).
    86. 深圳市统计局 (April 28, 2011). "深圳市2010年国民经济和社会发展统计公报" (in Chinese).
    87. 深圳市统计局. "2011年度12月份深圳统计月报:运输邮电:地铁客流量1-12月累计" (in Chinese). Archived from the original on December 4, 2012.
    88. "深圳地铁客流量 去年猛增近七成" (in Chinese). 深圳商报. January 10, 2013. Archived from the original on March 4, 2016.
    89. "深圳市2013年国民经济和社会发展统计公报" (in Chinese). 深圳市统计局. April 8, 2014.
    90. 深圳市交通运输委员会 (January 19, 2016). "2015年12月交通运输运营指标统计月报".
    91. "2016年交通运输运营指标统计年报" (in Chinese). 深圳市交通运输委员会. February 6, 2017. Archived from the original on February 11, 2017.
    92. "2017年交通运输运营指标统计年报" (in Chinese). 深圳市交通运输委员会. January 23, 2018.
    93. 2018年12月交通运输运营指标统计月报 (in Chinese). 深圳市交通运输委员会. January 18, 2019.
    94. 杨丽,杨德明 (2012). "深圳市城市轨道交通网络化客流变化研究". 现代城市轨道交通 (in Chinese). 6.
    95. 陈煜 (2011). "深圳地铁运营对轨道交通客流预测的启示". 铁道工程学报 (in Chinese). 8.
    96. (Chinese) fare information
    97. New Metro fares announced
    98. Business coach fears is three times as matching normal coach fears.
    99. (Chinese) SZMC fare policy
    100. types of tickets
    101. One smartcard to rule them all: Guangdong, HK team up to offer unified travel card | The Nanfang
    102. Guangdong and Hong Kong Linked by One Transportation Card _Life of Guangzhou
    103. "features". southcn.com. Retrieved August 27, 2012.
    104. "Metro Lines 1 and 4, Shenzhen, China". Archived from the original on February 4, 2009. Retrieved July 6, 2008.
    105. "Pocket Wi-Fi hotspots paralyse Chinese metro lines."
    106. "Accidents on Metro expansion hurt Shenzhen". South China Morning Post. April 23, 2011. Retrieved February 15, 2018.
    107. Ruixi, Zhao (September 7, 2012). "深圳地铁发生史上最严重事故 龙华线断电6小时". people.com.cn. Retrieved February 15, 2018.
    108. "Passengers abandoned in Shenzhen metro tunnel after train door opens". South China Morning Post. Retrieved May 5, 2018.
    109. "外企女经理地铁口晕倒后死亡 卧地长达50分钟". news.sina.com.cn. Retrieved May 5, 2018.
    110. "Shenzhen Metro Tunnel Collapses... for the 4th Time This Year | The Nanfang". The Nanfang. June 26, 2015. Retrieved May 5, 2018.
    111. "深圳在建地铁倒塌1死3伤 乘坐地铁前这一点你不能不知". JRJ.com. April 20, 2017. Retrieved February 15, 2018.
    112. "深圳地铁工地发生坍塌事故 2人遇难1人被困". Sina.com. May 11, 2017. Retrieved February 15, 2018.
    113. "深圳地铁9号线隧道被打穿 目前已限速". SZNews.com. October 30, 2017. Retrieved February 15, 2018.
    114. "解读 这是什么鬼?深圳地铁隧道竟被凿穿,罪魁祸首竟然是它!". Sohu. December 6, 2017. Retrieved February 15, 2018.
    115. "深圳地铁碾压事件:1人身亡死者翻越护栏俯卧轨道被碾_新闻频道_中华网". china.com. December 24, 2017. Retrieved April 1, 2018.
    116. "施工3天挖断7根电缆 深圳地铁:已对施工单位顶格处罚". CNR. July 12, 2018. Retrieved July 13, 2018.
    117. "深圳地铁施工三天挖断七条电缆 又挖爆供水主管道". Zaobao. July 12, 2018. Retrieved July 13, 2018.
    118. "深圳地铁2号线遇地质突变 部分站点临时停运-中新网". www.chinanews.com. Retrieved April 13, 2020.
    This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.