Deduru Oya Dam

Deduru Oya Dam
Location of Deduru Oya Dam in Sri Lanka
Country Sri Lanka
Location Wariyapola
Coordinates 07°43′06″N 80°16′28″E / 7.71833°N 80.27444°E / 7.71833; 80.27444Coordinates: 07°43′06″N 80°16′28″E / 7.71833°N 80.27444°E / 7.71833; 80.27444
Purpose Irrigation
Status Operational
Construction began 2006
Opening date 2014
Construction cost Rs. 9.5 billion
Dam and spillways
Type of dam Embankment
Impounds Deduru Oya
Height 20 m (66 ft)
Length 2,400 m (7,900 ft)
Spillways 8
Reservoir
Creates Deduru Oya Reservoir
Total capacity 75,000,000 m3 (2.6×109 cu ft)
Deduru Oya Power Station
Operator(s) MOPE
Commission date 2014
Type Conventional
Installed capacity 1.5 MW

The Deduru Oya Dam is an embankment dam built across the Deduru River in Kurunegala District of Sri Lanka. Built in 2014, the primary purpose of the dam is to retain approximately a billion cubic metres of water for irrigation purposes, which would otherwise flow out to sea. Construction of the dam began in 2006 and was ceremonially completed in 2014, with the presence of former President Mahinda Rajapaksa.[1]

The mouth of Deduru Oya, approximately 80km downstream of the dam.

Site studies and design of the dam was done by engineers from the Ministry of Irrigation. The dam, which measures approximately 2,400 m (7,900 ft) wide, creates the Deduru Oya Reservoir, which has a capacity of 75,000,000 m3 (2.6×109 cu ft). Water from the reservoir is used to irrigate approximately 11,000 hectares (27,000 acres) of farmland, while also powering a 1.5 megawatt hydroelectric power station, operated by the Ministry of Power and Energy.[2]

In addition to the eight sluice gates, water from the reservoir is channelled from the reservoir (for irrigation) via three canals, namely the Left Canal, Central Canal, and the South Canal. The South Canal is a trans-basin concrete canal measuring 33 km (21 mi), channelling water from the Deduru Oya Reservoir to the Inginimitiya Reservoir at a flow rate of 300 cu ft/s (8.5 m3/s).[3]

See also

References

  1. "Deduru Oya Reservoir the Large Irrigation Solution for North Western Province". Ministry of Irrigation. Retrieved 4 November 2015.
  2. P. Krishnaswamy (12 January 2014). "Deduru Oya Reservoir Project commissioning, a landmark event". Sunday Observer. Retrieved 4 November 2015.
  3. Rubasinghe, Ariya (1 March 2012). "A massive multi-functional project for Deduru Oya". Daily News. Retrieved 4 November 2015.
  • "Deduru Oya Reservoir Project to be commissioned tomorrow". News.lk. 21 November 2014. Retrieved 4 November 2015.


This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.