History of Bay Area Rapid Transit

Bay Area Rapid Transit, widely known by the acronym BART, is the main rail transportation system for the San Francisco Bay Area. It was envisioned as early as 1946 but the construction of the original system began in the 1960s.

Origins and planning

Envisioned master plan for rapid transit in San Francisco. BART was intended to take over existing rail corridors as well as incorporate new routes into the regional system. This map from 1960 included service through the Caltrain right of way as well as the Twin Peaks Tunnel, currently used for Muni Metro service, in addition to a Geary Subway and the constructed route down Mission Street (truncated to Balboa Park in this plan).

The idea of an underwater electric rail tube was first proposed in the early 1900s by Francis "Borax" Smith – the San Francisco Chronicle ran a front-page editorial in 1900 suggesting an electrified subway.[1] There were also plans for a third-rail powered subway line (Twin Peaks Tunnel) under Market Street in the 1910s.[2] Much of BART's current coverage area was once served by the electrified streetcar and interurban train network called the Key System. This early twentieth century system once had regular transbay traffic across the lower deck of the San Francisco–Oakland Bay Bridge. The final passenger run occurred on April 20, 1958 and the entire system was soon dismantled in favor of automobiles and buses and the explosive growth of highway construction.

Proposals for the modern rapid transit system now in service began in 1946 by Bay Area business leaders concerned with increased post-war migration and growing congestion in the region. An Army-Navy task force concluded that an additional trans-bay crossing would soon be needed and recommended a tunnel; however, actual planning for a rapid transit system did not begin until the 1950s. In 1951, California's legislature created the San Francisco Bay Area Rapid Transit Commission to study the Bay Area's long-term transportation needs. The commission's 1957 final report concluded the most cost-effective solution for the Bay Area's traffic woes would be to form a transit district charged with the construction and operation of a high-speed rapid rail system linking the cities and suburbs. Nine Bay Area counties were included in the initial planning commission.[3]

Logo adopted by the five-county BARTD in 1958.

The San Francisco Bay Area Rapid Transit District was formed by the state legislature in 1957, comprising the counties of Alameda, Contra Costa, Marin, San Francisco, and San Mateo. Because Santa Clara County opted instead to first concentrate on its Expressway System, that county was not included in the original BART District. In 1959 a bill was passed in the state legislature that provided for the entire cost of construction of the tube to be paid for with surplus toll revenues from the San Francisco–Oakland Bay Bridge. This represented a significant portion of the total cost of the system.[4]

By 1961 a plan for the new system was sent to the boards of supervisors of each of the five counties. These plans called for three branches traversing the San Francisco Bay and connecting Concord in the east, Richmond in the northeast, Fremont in the southeast; a crossing of the Golden Gate connecting San Francisco to Novato in the northwest; and a final branch running along the Peninsula from Palo Alto.[5] However, in April 1962 San Mateo County opted out, citing high costs, existing service provided by Southern Pacific commuter trains, and concerns over shoppers leaving their county for stores in San Francisco. This left Daly City (still in San Mateo County, but only a few feet across the county line) as the southwest terminus. Marin County followed soon thereafter in May, being forced out of the BART district due to engineering objections from the board of directors of the Golden Gate Bridge and fear that Marin voters would not approve the bonds, which had to win more than 60% approval.[6] The withdrawal also resulted in the cancellation of the Geary Subway section of the system. In 1962, a final Composite Report was prepared[7] and approved by the voters of the three remaining participating counties that November.

The initial system (1964–76)

Bay Area Rapid Transit
Initial System (1976)
Concord
Parking
Richmond Maintenance Yard
 
Concord
Parking
Richmond
Train Yard
 
Parking
El Cerrito del Norte
Pleasant Hill
Parking
Parking
El Cerrito Plaza
Walnut Creek
Parking
Parking
North Berkeley
Lafayette
Parking
Berkeley
Orinda
Parking
Parking
Ashby
Rockridge
Parking
MacArthur
southbound
Parking
19th Street Oakland
Oakland City Center/12th Street
northbound
Lake Merritt
Parking
Parking
Oakland West
Fruitvale
Parking
Coliseum
Parking
Embarcadero
San Leandro
Parking
Montgomery Street
Bay Fair
Parking
Powell Street
Hayward
Parking
Civic Center
South Hayward
Parking
16th Street Mission
 
Hayward
24th Street Mission
Maintenance Complex
 
Glen Park
Union City
Parking
Fremont
Parking
Balboa Park
Parking
Daly City

BART construction officially began on June 19, 1964 with President Lyndon Johnson presiding over the ground-breaking ceremonies at the 4.4-mile (7.1 km) test track between Concord and Walnut Creek in Contra Costa County.

The enormous tasks to be undertaken were daunting. System wide projects would include the construction of three underground rail stations in Oakland's populated downtown area, three stations through San Francisco’s downtown beneath Market Street (later expanded to four), as well as four other underground stations in other parts of San Francisco, three subterranean stations in Berkeley (which paid more to bury them, in contrast to the stations in neighboring Oakland and El Cerrito), as well as new maintenance facilities throughout the system.

The 3.2 miles (5.1 km) Berkeley Hills Tunnel was constructed through active faults between Berkeley and Orinda in order to avoid further use of the Caldecott Tunnel.

The centerpiece of the system, the 3.6 miles (5.8 km) Transbay Tube, connected Oakland and San Francisco beneath the San Francisco Bay. Restoring transbay passenger rail service for the first time since Key System service was discontinued across the Bay Bridge, the tube is the world's longest and deepest immersed tunnel with a cost of $180 million ($1.2 billion adjusted for inflation) and was completed in August 1969. It was constructed in 57 sections, each positioned and installed individually by sinking them into a dredged trough across the bay (that was later filled in).

BART constructed right-of-ways utilizing several rail and freeway corridors. For the initial system, these included: the Sacramento Northern Railway right-of-way in Concord, Contra Costa Center and Walnut Creek; State Route 24 and Interstate 980 from the Berkeley Hills Tunnel to Oakland; Western Pacific Railroad from Fruitvale to Niles Canyon; Atchison, Topeka and Santa Fe Railway and Key System right-of-ways between Richmond and Berkeley (which also became the Ohlone Greenway and Richmond Greenway); and the San Francisco and San Mateo Electric Railway[5] and original Southern Pacific Peninsula Commute[8] right-of-ways to Daly City.

Pleasant Hill station under construction in 1970

The final ceremonial spike for the original system was placed in 1971.

Entrance to the Berkeley station (bottom right) as seen in 1973, shortly after the station opened

Opening

Service began on September 11, 1972,[9] reporting more than 100,000 passengers in its first five days. The Market Street Subway opened on November 3, 1973[10] and the Transbay Tube finally opened on September 16, 1974, linking the four branches to Daly City, Concord, Richmond, and Fremont. Service then was still 14 hours a day, and for five years BART operated weekday-only: Saturday trains began November 1977 and Sunday in July 1978. Fare in 1972–74 was $1.20 ($5.95 adjusted for inflation) from Concord or $1.25 ($6.20 adjusted for inflation) from Fremont to any station west of the bay; Richmond to Fremont was $1.10 ($5.46 adjusted for inflation).

BART diverted 44,000 trips made by private cars by 1976, this fell well short of the anticipated 157,000.[11]

BART's cost in 1976 was pegged at $1.586 billion,[12] which included both the initial system, rolling stock and the Transbay Tube. (Adjusted for inflation, equivalent to $9.28 billion in 2017.) Critics have said BART took four decades to develop at a high cost.[13]

Infill Station

Service at Embarcadero began on May 27, 1976, three years after the other San Francisco stations.[14] The station was not part of the original plans for the system. As a result of increasing development in the lower Market Street area, the basic structure of the station was added into the construction of the Market Street subway, anticipating a later opening.[15]

Automation

The BART Operations Control Center

BART was one of the first U.S. systems of any size to have substantial automated operations. As a first-generation installation, the automation system was plagued with numerous operational problems during its first years of service. Shortly after revenue service began, an on-board electronics failure caused one two-car test train (with car 143 as the lead car) to run off the end of the elevated track at the Fremont station and into a parking lot. This incident was dubbed the Fremont Flyer, and there were no serious injuries.[16][17]

Back of an early magnetic striped encoded paper ticket.

The original signaling technology and subsequent enhancements used to control the trains was developed by Westinghouse. When revenue service began, "ghost trains" (or false occupancies), trains that show up on the computer system as being in a specific place but don't physically exist, were common, and real trains could at times disappear from the system. This was the result of dew on the tracks and too low of a voltage (at 0.6 volts rather than the industry standard 15 volts) being passed through the rails for train detection.[17] Under such circumstances, trains had to be operated manually and were restricted to a speed of 25 mph (40 km/h). Enhancements were made to the train control system to address these "ghost trains" (or false occupancies). However, manual blocking — operators in a booth on the platform at alternate stations, with a telephone and red/green lights — that kept trains in stations until the train ahead had left its station were mandated for several years. This caused a great outcry in the press and led to a flurry of litigation between Westinghouse, the original controls contractor, and BART, as well as public battles between the state government (advised by University of California professor Dr. Bill Wattenburg), the federal government, and the district, but in time these problems were resolved and BART became a reliable service.[17] Ghost trains persisted on the system as late as 2007, and while usually cleared quickly enough to avoid significant delay, they can occasionally cause an extended backup of manually operated trains in the system.[18] In addition, the fare card system was easily hackable with equipment commonly found in universities, although most of these flaws have been fixed.[19]

Running logistics were originally handled from a central control room, but that was replaced by the more modern Operations Control Center (OCC) and headquarters at the Kaiser Center in Downtown Oakland.

Train-control failures

Before the system began revenue service, serious problems in the design and operation of the Automatic Train Control (ATC) system were observed. Three engineers working for BART, Max Blankenzee, Robert Bruder, and Holger Hjortsvang, identified safety problems with the ATC in 1969–1971. BART management was dismissive of their concerns, so the three took the issue to the board of directors. All but two of the directors voted in February 1972 to support management and reject the safety concerns.[20] Management retaliated against the engineers, firing them in March 1972.[21] The IEEE later filed the first amicus curiae brief in its history to support the engineers.[21]

The California Society of Professional Engineers reported to the California State Senate in June 1972 that there were serious safety risks with the ATC.[21] Legislative analyst A. Alan Post opened an investigation immediately,[21][22] and brought in electrical engineering Professor Bill Wattenburg of the University of California, Berkeley as a consultant.[23]

Train operations were observed by top management:

[BART General Manager] B.R. "Bill" Stokes was showing a visiting transit executive the system's Space Age control system at the Oakland headquarters [on October 2, 1972]. "Watch," Mr. Stokes said. "There is a train headed for the Fremont station." But the moving light on the map moved through the station and went out. The operator called on the radio. "I've just landed in the parking lot!" he said.[24]
The "Fremont Flyer" accident in 1972

An ATC failure caused the train to run off the end of the elevated track and crash to the ground, injuring four people on board,[25] and drawing national and international attention.[26][24] The “Fremont Flyer” led to a comprehensive redesign of the train controls. The California State Public Utilities Commission imposed stringent oversight over train operations, and stationed State inspectors inside BART central control.[22]

The legislative analyst issued the first of three “Post Reports” in November 1972. The report was “sharply critical” of BART,[26] finding that the ATC system was unreliable, the ATC program was mismanaged, and “no solution was in sight.”[25][27] The report accused BART of paying excessive fees for engineering services.[25] BART’s general manager called the indictment of safety in the Post Report “not only disappointing, but deplorable as well.”[26] At the same time, management deemed that the ATC “could not now be trusted to detect one train stalled on the tracks in the path of another going at full speed,” so automatic controls were dropped. Telephone calls were placed manually between stations, instead.[25]

The California State Senate, California Public Utilities Commission, and National Transportation Safety Board launched separate investigations.[28] Several managers were replaced, and the general manager came under fire.[29][30] The legislative analyst reported in March 1974 that BART “suffered from a lack of direction and control on the part of the board and management.”[31] The state legislature held hearings lasting one month in 1974 into the financial mismanagement at BART.[32] Following the hearings, legislative analyst A. Alan Post recommended that the general manager be fired.[32] Legislators also threatened to withhold funding from BART unless the general manager quit,[33] and forced the general manager to resign in May 1974.[33]

State legislators moved to completely replace the appointed board of directors,[34] and passed legislation that led to the election of a new board in 1974.[35] The train-control problems and management turmoil delayed the start of service to San Francisco, from 1973 to 1974.[25][35]

In 1978, engineers Blankenzee, Bruder and Hjortsvang received an ethics award from the IEEE.[36] The “BART Case” is a case study in whistleblowing, used for courses on engineering ethics.[37]

Loma Prieta earthquake

BART served as the only direct link between San Francisco and the East Bay for just over a month after the earthquake.

The 1989 Loma Prieta earthquake severed the San Francisco–Oakland Bay Bridge for a month and destroyed the Cypress Street Viaduct. With some Bay Area freeways damaged or destroyed, BART trains, within five hours of the earthquake, were again running; full service resumed at 5 am the next day.[38] Even with service interruptions following aftershocks for inspection of tracks, over- and under-crossings, and tunnels, BART continued to run on a 24-hour timetable until December 3 of that year.[39][40]

San Francisco International Airport extension (1984–2003)

Southbound train between Balboa Park and Daly City

Service south of Daly City was outlined in the 1961 proposal,[5] but the exit of San Mateo County from the planning district caused these plans to be shelved.

Efforts were started as early as 1984 for extension south from San Francisco, the first step being the Daly City Tailtrack Project, upon which turnaround project the San Francisco Airport Extension would later build.[41] Expansion of the system was finally made possible by an agreement under which San Mateo County was to contribute $200 million ($321 million adjusted for inflation) to East Bay extensions as a "buy-in" to the system without actually joining the BART district.

Service into San Mateo (outside of Daly City) commenced in 1996 with the opening of Colma station. At that time, funding had not been secured for the full airport extension.[42] This station served as the end of the line for over seven years.

Ground was broken on the project in November 1997. Four new stations were added to the system: the SFO station, South San Francisco, San Bruno, and Millbrae. The Millbrae station has a cross-platform connection to Caltrain, the first of its kind west of the Mississippi.[43] The $1.5 billion ($2 billion adjusted for inflation) extension of BART southward to San Francisco International Airport's (SFO) Garage G, adjacent to the International Terminal, was opened to the public on June 22, 2003. The right of way had been served by Muni's 40 San Mateo interurban (previously the San Francisco and San Mateo Electric Railway) streetcar line until 1949. The airport extension between SFO and Millbrae station was initially hosted a shuttle service which operated with two train operators—one on each end of the train—between the San Bruno and Millbrae stations to reduce dwell time at SFO during peak hours. The train entered the SFO stub-end station under the control of the primary operator and exited in the opposite direction towards Millbrae controlled by the secondary. Since SFO is now the terminus of the line that serves it, this practice was discontinued as it would not reduce the in-transit time for any trips.

Dedication plaque at SFO station

The airport extension project added 8.7 miles (14.0 km) of new railway; 6.1 miles (9.8 km) of subway, 1.2 miles (1.9 km) of aerial, and 1.4 miles (2.3 km) of at-grade track. The launch point was the Daly City Tailtrack project, which extended the tracks further south of the existing terminus in San Francisco and was completed in the 1980s.[44][45]

The project has not been without problems, however. The SFO extension drew 35,107 daily riders by 2008, significantly less than its opening target of 50,000 average weekday riders.[46] The most use the new line has gotten on any single day was 37,200;[47] the SFO Station received an average of 6,781 daily passenger exits in 2015.[48] Another significant problem of note had been the rocky relationship between BART and San Mateo County Transit District (SamTrans) which was not a part of the BART district, but by agreement was responsible for the extension's operating costs. Fueled by the reality that the extension was not paying for itself, the acrimony between BART and SamTrans over changes and reductions in bus and train service reached a high.[49][50][51] BART wanted to increase service to attract ridership, while SamTrans wanted to reduce service to trim costs. Thus, service along the extension was changed several times.[52][53] Eventually SamTrans and BART worked out a deal in which SamTrans paid BART $32 million, plus approximately $2 million a year, and BART assumed all costs and control of operating the extension.[54]

The disappointing passenger numbers and the fight with SamTrans meant that between 2003 and 2010, BART repeatedly changed its routing patterns on the line south of Daly City, offering at least five distinct service patterns on different lines (Richmond, Pittsburg/Bay Point, Dublin/Pleasanton), with trips terminating at either Millbrae or SFO. The January 1, 2008 change eliminated most direct service between SFO and Millbrae on weekdays, except for a few morning and evening trips. Finally, in 2010 BART settled on a routing pattern that has Pittsburg/Bay Point trains running to SFO at all times. During peak times Mondays through Fridays, Richmond trains run directly to Millbrae without stopping at SFO. During off-peak hours (nights and weekends), Pittsburg/Bay Point trains serve both SFO and Millbrae sequentially. Passengers on the Fremont, Richmond, and Dublin/Pleasanton lines must make a transfer to the Pittsburg/Bay Point line to reach the airport. In addition, the cessation of direct BART service between Millbrae and SFO during weekday peak hours requires Caltrain passengers wanting to travel to the airport from Millbrae to travel to San Bruno Station and make a transfer to an SFO train.

Spur lines (1995–2018)

Part of San Mateo's buy in was used to offset funding for extensions of the core system in the East Bay. Trains to North Concord/Martinez began on December 16, 1995 and to Pittsburg/Bay Point on December 7, 1996. On May 10, 1997 a new branch to Castro Valley and Dublin/Pleasanton[55] opened via a right of way constructed in the median of Interstate 580. The Dublin/Pleasanton extension now has transbay trains, but it was planned to have just shuttle trains between Dublin/Pleasanton and Bay Fair.[56] (Long term plans involve running short trains to a coupling point at Bay Fair to increase system-wide capacity while still providing a one-seat ride.) This line has at various times extended further south from Daly City, and was most recently truncated in 2009.

The Oakland Airport Connector traversing Interstate 880.

To save on construction cost compared to a "traditional" third-rail BART buildout, two spur lines were constructed using different technologies; they are neither heavy rail nor electrified. The Oakland Airport Connector was built as a replacement for the bus-serviced AirBART and brought the airport into the system's fare zone. The Coliseum–Oakland International Airport line, as it came to be known, utilizes automated guideway transit (AGT) technology: cable-drawn cars that operate in discrete cable loops on guided rubber tires. The AGT’s connection to the existing BART system at Coliseum Station resembles the AirTrain JFK and AirTrain Newark airport people movers' existing off-airport connections to other rail transit lines, though it is run by the transit authority itself rather than an out-of-system operator. Service along the line began on November 22, 2014.

Test eBART DMU departing the under construction Pittsburg Center station.

eBART was conceived to bring service to the eastern communities in Contra Costa County. Initially studied for full BART service buildout, it was decided to construct the line with standard gauge rail and utilizing diesel multiple unit light rail trains. This allowed BART to roll out service at 60% the cost of traditional buildout with the option to regauge and electrify the route at a later date. The service debuted on May 26, 2018 and included a stop at Pittsburg Center station, which was primarily funded with money from the city of Pittsburg. It is referred to by BART as simply an extension of the existing Pittsburg-Bay Point line to Antioch rather than a separate route.[57]

Infill station

Because West Dublin / Pleasanton station was originally planned to enter into service as part of the original extension to Dublin/Pleasanton, the station's foundation along with some communication and train control facilities already existed on-site. Final construction of the station for revenue service began on October 29, 2006.[58] Possible faulty construction delayed its opening until 2011.[59] Its cost was estimated at $106 million[60] ($115 million adjusted for inflation), with funding coming from a unique public-private partnership and the proceeds of planned transit-oriented development (TOD) on adjacent BART-owned property.

Silicon Valley extension (2009–present)

Warm Springs / South Fremont station under construction in January 2014

Santa Clara County was originally to have been a member of the BART district, but local leaders voted down participation early in the project. Minor service at Palo Alto, right over the border from San Mateo County was also planned originally. However, San Mateo County also opted out, leaving Fremont the closest end of line.[61] In 2000, Santa Clara County voters approved a 30-year-long half cent sales tax increase to fund a BART extension to San Jose.

Construction of the Warms Springs extension began in 2009, with a planned opening in 2014.[62][63] By the time of the extension's opening on March 25, 2017, the start of revenue service had been delayed over two years.[64][65] The extension to Berryessa started construction in 2012.

Earthquake safety

Despite the robustness of the system following the 1989 Loma Prieta quake, a 2010 study showed that BART overhead structures could collapse in a major earthquake,[66] which has a significant probability of occurring within three decades.[67] Seismic retrofits were necessary to address these deficiencies, although one in particular, the penetration of the Hayward Fault Zone by the Berkeley Hills Tunnel, will be left for correction after a large earthquake.

Seismic retrofitting at El Cerrito del Norte station

An earthquake early warning system called ShakeAlert, sponsored by the United States Geological Survey, was instituted in 2012 with the help of UC Berkeley seismologists who linked BART to 200 stations of the California Integrated Seismic Network. These electronic signals travel much faster than seismic waves. For quakes outside the Bay Area, they provide advance notice that shaking is on the way; for quakes in the Bay Area, they provide an earlier warning. If the seismic network warns of ground motion above a threshold, the train control computers will order “service” braking, slowing from normal speeds of up to 70 miles per hour (110 km/h) to 26 miles per hour (42 km/h) .

“The earthquake early warning system will enable BART to stop trains before earthquake shaking starts and thereby prevent derailment, and save passengers from potential injuries”, said BART Board President John McPartland. “We are the first transit agency in the United States to provide this early warning and intervention.”[68]

The 3.6-mile (5.8 km) Transbay Tube has also required earthquake retrofitting. The immersed tube lies in a shallow trench dredged on the bottom of San Francisco Bay, and was anchored to the bottom by packing around the sides and top with mud and gravel. This fill may be prone to soil liquefaction during an earthquake, which could allow the buoyant hollow tube to break loose from its anchorages. Retrofitting outside the tube compacted the fill, to make it denser and less prone to liquefaction. Inside the tube, BART installed heavy steel plates, to reduce sideways movement in an earthquake. The work was performed between March and December 2013, and BART closed one of the two bores of the tube early on some weeknights. Trains shared a single tunnel between Embarcadero and West Oakland after 10 pm, with travel delays of 15–20 minutes.[69] The work, estimated to take 14 months, was completed after 8 months.[70]

Replacement fleet (2012–present)

Old and new trains in Hayward Yard, October 2017

As the age of the main fleet passed 40 years, BART sought to replace all of its cars. In 2012 BART awarded a $900 million contract to Canadian railcar manufacturer Bombardier Transportation for 410 new cars, 260 with an option for 150 more.[71][72] The cars are designed by Morelli Designers of Canada.[73] In late 2013, BART purchased 365 more cars, for a total fleet size of 775, accelerated the delivery schedule by 21 months (from 10 cars per month up to 16 cars per month) and lowered cost.[74][75]

The 10-car test pilot train had been previously scheduled for delivery in 2015, followed by an 18-month testing period. Due to potential access issues for people with disabilities, the pilot car layout was modified by the BART board in February 2015 to include two wheelchair spaces in the center of the car, as well as alternative layouts for bike and flexible open spaces.[76] More recently, the Canadian manufacturer of the cars encountered delays in other cities and a cancellation in Toronto. A loan bailout from the Canadian government is pending. As of early 2016, the scheduled delivery of the 10-car test train was delayed one year until late 2016.[77] The train was put into revenue service on January 19, 2018,[78] though some cars were removed for servicing several days later.[79]

The first 140 cars had been set to begin service in 2017, but this number was subsequently cut to 54 cars.[77][80] Delivery of all 775 cars was delayed from 2021 to 2022.[80][81] The first ten-car train received CPUC certification on January 17, 2018,[82] and began revenue service two days later on January 19.[83] Plans to have 198 new cars by July 2018 did not materialize, and the agency had put only 20 in service at that time.[84]

Labor

BART workers are currently organized in 4 unions: the Service Employees International Union Local 1021, Amalgamated Transit Union Local 1555, American Federation of State, County and Municipal Employees Local 3333, and the BART Police Officer's Association.

1976 strike

BART has a unionized work force that went on strike for two weeks in 1976 in solidarity with the BART Police Officers Association. During the 1970s BART union workers received quarterly cost of living increases.

1979 lockout/strike

In 1979 there was a 90-day lockout by management, or a strike by union workers. Trains ran during this period because one of the unions, AFSCME, was then only an informal association known as BARTSPA, and management and BARTSPA had enough staff to keep trains running. One result of this strike is that the cost-of-living increases were greatly reduced to an amount far below the Consumer Price Index, and such raises are only received if no other raise occurs in a particular year.

1997 strike

For seven days starting from 7 September 1997, a BART strike caused a system-wide shutdown. This resulted in a four-year contract offering a 7% raise, and a one-time payment of $3,000 to all employees in lieu of a raise the first year. In addition, BART began large scale layoffs of rank and file workers, increasing the workload on those remaining.

2001 negotiations

In its 2001 negotiations, the BART unions fought for, and won, a 24 percent wage increase over four years with continuing benefits for employees and retirees.[85]

2005 negotiations

Another threatened strike on July 6, 2005 was averted by a last-minute agreement between management and the unions. In this agreement, Union workers received a 7% raise over four years, and paid an increase in the cost of medical insurance. The net increase (3%) was well below inflation, which was about 10% cumulative (about 2.4% per year) over the period of the contract.[86] The net increase was also below the average private sector raise, which was 4.6% for 2006.

2009 negotiations

The outcome of the 2009 contract negotiations were a four-year wage freeze, reduced pensions, and changes to work rules.[87] These new terms provided a $100 million savings to BART from 2009 to 2013.[88]

2013 strikes

BART employees went on strike on July 1, 2013, over pay and safety issues. The strike was ended July 5, when both sides agreed to a 30-day cooling off period (which ended Monday, August 5).[89] A second strike began on Friday, October 18, 2013, over unresolved compensation and work rule issues. Management offered a 12% wage increase over 4 years, of which 4% would be taken back as an increase in the required pension contribution; 9.5% increase in healthcare premiums, and changes to work rules including fewer fixed work schedules. Unions were willing to accept the financial terms but requested binding arbitration for the work rules. Management refused the arbitration offer.[90]

Awards

BART was designated a Historic Mechanical Engineering Landmark by the American Society of Mechanical Engineers in 1997, calling it the "most advanced automated urban rail transit system incorporating many innovations, marking a new generation of rail travel."[91]

In October 2004 BART received the American Public Transportation Association's Outstanding Public Transportation System Award for 2004 in the category of transit systems with 30 million or more annual passenger trips.[92] BART issued announcements and began a promotional campaign declaring that it had been named Number One Transit System in America.[93] In 2006 the same industry trade group presented BART with the token AdWheel award for 'creative approaches to marketing transit' in recognition for BART's development of an iPod-based trip planner.[94]

Incidents and accidents

There have been no accidents attributed to brake failure. The following incidents are known to have occurred on the BART system:

  • In 1972, shortly after the system opened, a test train carrying no passengers, dubbed the Fremont Flyer, failed to stop at the end of the line at Fremont and ran into the parking lot. There were several injuries.[16]
  • The Transbay Tube was closed from January 17 to April 4, 1979, after a train caught fire in the tube, injuring dozens, killing a fireman, and damaging equipment.[95] Most of the injuries were caused by inhalation of toxic smoke from the burning polyurethane in the seats, leading to a $118,000 replacement program which was completed in November 1980.[3]
  • On December 17, 1992, a BART train derailed south of 12th Street station and caused a five-day closure of the line.[96]
  • On March 9, 2006, debris on BART tracks between Montgomery and Embarcadero stations caught fire and caused a 1.5 hour system-wide shutdown. Frustrated passengers accused BART of mishandling the incident.[97]
  • On March 28 and 29, 2006, BART experienced computer glitches in its system during rush hour, which left about 35,000 commuters stranded inside trains or stations while the problem was being resolved.
  • On December 1, 2006, a BART train jumped the tracks near the Oakland Wye, between 12th Street and Lake Merritt stations. There were no injuries.[98]
  • On May 10, 2008, two separate early morning fires at different power substations disrupted service on the Fremont line. No injuries were reported from the incident. The resulting damage left the Fremont line impaired as several computer control loops went offline between South Hayward and Union City Stations. Train operators were forced to manually drive trains at a reduced speed of 25 miles per hour (40 km/h). Normal service was finally restored on July 13, 2008, two weeks before initial estimates.
  • On October 14, 2008, a BART track worker, James Strickland, was killed by a train near the Concord-Walnut Creek border. The Pittsburg/Bay Point line was the most affected by the accident.
  • On December 29, 2008, shortly after 7 PM, an electrical fire broke out near the Walnut Creek station. The fire apparently started after a train ripped off a portion of the electric third rail, dragging it under the train and sparking a fire along the rail. The fire caused major delays of 2–3 hours, as Pittsburg/Bay Point bound trains could travel no further than Lafayette station, and San Francisco Airport bound trains were held at Concord station, having to be taken out of service as the delays continued. A bus shuttle system was set up to take passengers along the Concord, Pleasant Hill, Walnut Creek, and Lafayette BART stations. Trains were eventually allowed through the station in both directions, sharing one track until the rail was repaired.
  • On January 1, 2009, there was an officer-involved shooting at the Fruitvale station, killing one person. See BART Police shooting of Oscar Grant.
  • On February 3, 2009, two trains collided at low speed while approaching the 12th Street station, injuring a dozen people.[99]
  • On July 16, 2009 a westbound Dublin/Pleasanton train struck a construction worker at the upcoming West Dublin Station. None of the 75–100 passengers on the train were hurt. Service was affected for 30 minutes on both lanes and passengers were forced to stay on their trains until BART decided for the affected train to head back to the Dublin/Pleasanton Station where passengers could exit. Operations resumed a few hours later.[100]
  • On December 9, 2009 a train derailed between Lake Merrit and 12th Street stations in Oakland, California.
  • On Sunday, March 13, 2011 the eighth and ninth cars of a ten car train derailed after leaving the Concord station at slow speed. Three minor back injuries were reported.[101] The train carried about 65 people at that time.[102] After the derailment, buses were employed to shuttle the passengers between the BART stations of Pleasant Hill and Pittsburg/Bay Point.[101] The repairs lasted into the night and were completed before the Monday morning commute.[102] A similar event occurred at the same location on the evening of February 21, 2014 to a train not in passenger service,[101] and a similar bus bridge was employed among North Concord, Concord, and Pleasant Hill stations on February 22, 2014 while emergency repairs were made.
  • On October 19, 2013 two BART workers were struck and killed while inspecting a track section between the Walnut Creek and Pleasant Hill stations.[103]
  • On April 22, 2016 a new test car, which had recently been delivered to the agency, overshot the end of a track while undergoing tests at the Hayward Maintenance Complex. No passengers were on board the car as the only occupant was the BART train operator. No injuries were reported.[104]
  • On February 7, 2017, a northbound train struck a pedestrian on the Richmond line, shutting down service north of North Berkeley; the man was pronounced dead at the scene.[105]

Crime

In the summer of 2017 BART came under severe criticism for 'politically correct' suppression of video evidence of crimes committed at Oakland stations. That spring and summer, in at least three incidents, 'gangs' of youths (composed primarily of African-Americans) had swarmed stopped trains and attacked and robbed train riders.[106] BART's justification for the suppression of this evidence was “To release these videos would create a high level of racially insensitive commentary toward the district,” ... “And in addition it would create a racial bias in the riders against minorities on the trains.” According to a memo distributed to BART Directors, the agency did not put out a press release on the June 30 theft because it was a “petty crime” that would make BART look “crime ridden.” Furthermore, it would “unfairly affect and characterize riders of color, leading to sweeping generalizations in media reports.”

In July 2017, a BART rider created a website, bartcrimes.com, to disseminate publicly available information he thought BART made difficult to find. BART officials say crime rates remain low, but according to data requested by the San Francisco Chronicle after the mob robbery in April, figures showed a 45 percent increase in robberies aboard BART trains in its stations during the first quarter of the year.[107]

In September 2017, six people (victims of the robberies/assaults) filed suit against BART for gross negligence, claiming BART does not provide adequate security for its riders.[108]

Defunct lines

In the ten months between the openings of the Market Street Subway and the Transbay Tube (November 5, 1973 to September 16, 1974), the San Francisco segment between Montgomery and Daly City operated as an independent line. This was discontinued with through service to Oakland and Concord when the Transbay Tube opened.[109]

Detail from 2003 BART map showing the SFO-Millbrae shuttle service

On July 10, 1995, BART began limited direct service between Concord and Bay Fair as traffic mitigation during reconstruction of the I-680/SR 24 interchange in Walnut Creek. The service, which ran with two five-car trains, was extended to South Hayward on July 24. The special service ended on May 5, 1997 to free the trains for the opening of the extension to Dublin/Pleasanton five days later.[109]

At the time when the BART-SFO Extension opened on June 22, 2003, there was a Millbrae–SFO Line, a shuttle line that operated every 20 minutes between Millbrae and San Francisco Airport, formerly depicted as a purple line. This line has been defunct as of February 2004. It was replaced by the Pittsburg/Bay Point line and the Richmond Line, and in 2005 by the Dublin/Pleasanton line. On January 1, 2008, direct service between Millbrae and SFO was eliminated; passengers traveling between Millbrae and SFO have the inconvenience of boarding a train at Millbrae, traveling to San Bruno, and then take a different train back to the airport. Direct service to SFO from Millbrae was restored in September 2009, but only during off-peak hours and weekends.

AirBART, a dedicated bus line, operated between the current Coliseum Station and the Oakland International Airport. The service was discontinued on November 22, 2014 with the opening of the Coliseum–Oakland International Airport line automated guideway transit system. AirBART was a joint project of BART and the Port of Oakland, which owns and operates the airport.[110] It was operated by Transdev under contract. As of December 2009, the AirBART fleet consisted of five Eldorado Axess buses running on compressed natural gas (CNG).[111]

Timeline of service expansion

Segment description Date opened Line(s) Endpoints # of new
stations
Length
(miles)[112][113]
Oakland Subway September 11, 1972      MacArthur to Fremont 12 28
Berkeley Subway January 29, 1973      Richmond to MacArthur 6 11
Berkeley Hills Tunnel May 21, 1973      Concord to MacArthur 6 17
Market Street Subway November 5, 1973 San Francisco Montgomery Street to Daly City 8 7.5
Transbay Tube September 16, 1974          West Oakland to Montgomery Street 1 8
Original System              33 71.5
May 27, 1976              Embarcadero 1 0[lower-alpha 1]
Pittsburg/Antioch Extension December 16, 1995      North Concord/Martinez to Concord 1 2.5
February 24, 1996          Colma to Daly City 1 1.6
Pittsburg/Antioch Extension December 7, 1996      Pittsburg/Bay Point to North Concord/Martinez 1 5.3
Dublin/Pleasanton extension May 10, 1997      Bay Fair to Dublin/Pleasanton 2 14.7
San Francisco Airport Extension June 22, 2003                 [lower-alpha 2] Colma to SFO/Millbrae 4 8.7
February 19, 2011      West Dublin/Pleasanton 1 0[lower-alpha 1]
Oakland Airport Connector November 22, 2014      Coliseum to Oakland International Airport 1 dagger3.2
Silicon Valley Warm Springs extension March 25, 2017          Warm Springs/South Fremont to Fremont 1 5.4
eBART May 26, 2018      Antioch to Pittsburg/Bay Point 2 Section-sign10.1
TOTAL 48 119.8[lower-alpha 3]
dagger3.2
Section-sign10.1
Silicon Valley Berryessa extension 2019 (estimated)          Warm Springs to Berryessa 2 10
San Jose Subway 2026 (estimated)          Santa Clara to Berryessa 4 6
  1. 1 2 Infill station
  2. Service reduced to Pittsburg/Bay Point–SFO/Millbrae trains by 2008.
  3. Likely varies from the "official" BART figure due to rounding differences.

dagger Automated guideway transit line
Section-sign Standard gauge track

References

  1. Hartlaub, Peter (10 August 2016). "For 'luxury' BART in 1965, the future looked shiny and bright". San Francisco Chronicle. Retrieved 3 June 2017.
  2. "REPORT ON MARKET STREET RAPID TRANSIT TUNNEL". Electric Railway Journal. XL: 883. 19 October 1912. Retrieved 23 July 2018.
  3. 1 2 "History of BART (1946–1972)". BART. Archived from the original on 2006-09-22. Retrieved 2007-01-07.
  4. See BART Composite Report, prepared by Parsons Brinkerhof Tutor Bechtel, 1962
  5. 1 2 3 "Rapid Transit for the San Francisco Bay Area" (PDF). LA Metro Library. Parsons Brinkerhoff / Tudor / Bechtel. Retrieved 21 July 2018.
  6. "History of BART to the South Bay". the San Jose Mercury News. January 8, 2005. Retrieved 2007-01-07.
  7. "The Composite Report Bay Area Rapid Transit". Archive.org. Parsons Brinkerhoff / Tudor / Bechtel. Retrieved 23 July 2018.
  8. Callwell, Robert (September 1999). "Transit in San Francisco: A Selected Chronology, 1850-1995" (PDF). San Francisco Municipal Railway.
  9. A Full BART Chronology (269k .pdf) Archived 2013-10-13 at the Wayback Machine.
  10. Webber, Melvin (1976). "The BART experience: what have we learned?" (PDF): 95. Retrieved 31 May 2016.
  11. Webber, Melvin (1976). "The BART experience: what have we learned?" (PDF): 93. Retrieved 31 May 2016.
  12. Hall, Peter Geoffrey (1982). Great Planning Disasters. California Series in Urban Development. pp. 109–130. ISBN 978-0-520-04607-8.
  13. "Celebrating 40 Years of Service 1972 • 2012 Forty BART Achievements Over the Years" (PDF). Bay Area Rapid Transit (BART). 2012. Retrieved 2013-11-30.
  14. "A History of BART: The Project is Rescued". Bay Area Rapid Transit (BART). Retrieved 2013-11-30.
  15. 1 2 Pirmann, David (1995–2012). "BART Bay Area Rapid Transit". world.nycsubway.org. Retrieved 30 January 2018.
  16. 1 2 3 Bill Wattenburg (October 11, 2004). "BART—Bay Area Rapid Transit System (1972–74)". PushBack.com. Retrieved 2007-01-07.
  17. "'Ghost Train,' Malfunctions Causing BART Delays". Bay City News. FoxReno.com. February 16, 2005. Archived from the original on May 18, 2006. Retrieved January 29, 2018.
  18. Peter Sheerin (October 11, 2004). "Magnetic Credit Cards". PushBack.com. Retrieved 2007-01-18.
  19. Anubhav Jain (May 1, 2004). "Ethics in technical presentations: BART case study" (PDF). Archived from the original on March 2, 2007. Retrieved March 15, 2017.
  20. 1 2 3 4 Stephen Unger (April 29, 2010). "The BART Case". The Online Ethics Center for engineering and science. Retrieved March 15, 2017.
  21. 1 2 Peter Sheerin (October 1, 1990). "Bill Wattenburg's Background: BART—Bay Area Rapid Transit System". Retrieved March 15, 2017.
  22. Dr. W.H. Wattenburg (December 1, 1972). "The BART Train Control Game" (PDF). Retrieved March 15, 2017.
  23. 1 2 "B.R. Stokes, ex-BART general manager, dies". San Francisco Chronicle. May 25, 2013. Retrieved March 15, 2017.
  24. 1 2 3 4 5 "Troubles Beset Transit System in San Francisco Bay Area". December 9, 1972. Retrieved March 15, 2017.
  25. 1 2 3 Bill Northwood (November 29, 1972). "What is BART, and why are we saying such terrible things about it?". KPFA Pacifica Radio. p. 2 min : 00 sec. Retrieved March 15, 2017.
  26. "Bigger bugs in BART?" (PDF). IEEE Spectrum Magazine. March 1, 1973. p. 34. Retrieved March 15, 2017.
  27. "Automatic Train Control in Rail Rapid Transit" (PDF). United States Congress Office of Technology Assessment. May 1, 1976. pp. 45–49. Retrieved March 15, 2017. Investigations of BART were undertaken by the California Senate, the California Legislative Analyst, the California Public Utilities Commission, and the National Transportation Safety Board. The cause of the accident was traced to a faulty crystal oscillator…
  28. Peter Sheerin (October 1, 1990). "Bill Wattenburg's Background: BART—Bay Area Rapid Transit System". Retrieved March 15, 2017. Wattenburg challenged the credentials of three successive chief engineers at BART. All of them left or were fired.
  29. "Bigger bugs in BART?" (PDF). IEEE Spectrum Magazine. March 1, 1973. p. 36. Retrieved March 15, 2017. David Hammond, BARTD’s assistant general manager submitted his resignation…
  30. J. Allen Whitt (14 July 2014). Urban Elites and Mass Transportation: The Dialectics of Power. Princeton University Press. pp. 77–. ISBN 978-1-4008-5745-6.
  31. 1 2 "Legislative Analyst's Office 75th anniversary". Legislative Analyst's Office (LAO) of the State of California. May 25, 2013. Retrieved March 15, 2017. After the state legislature held a month-long series of hearings on the financial mismanagement at Bay Area Rapid Transit (BART), Alan Post recommended the firing of BART’s general manager.
  32. 1 2 "B.R. Stokes, ex-BART general manager, dies". San Francisco Chronicle. May 25, 2013. Retrieved March 15, 2017. BART officials had to ask the Legislature for more money... but the price was high. Nearly all of the Bay Area's legislators said they would oppose giving BART money unless Mr. Stokes resigned. He quit May 24, 1974...
  33. Bill Wattenburg (February 15, 1974). "BART: Countdown to San Francisco". Commonwealth Club of California. p. 28 min : 30 sec. Retrieved March 15, 2017.
  34. 1 2 "BART historical timeline" (PDF). BART. Retrieved March 15, 2017. November 5, 1974, Nine-member Board of Directors elected to replace 12-member appointed board.
  35. Unger, Stephen. "September 1973 Newsletter". IEEE Committee on Social Implications of Technology (CSIT). IEEE. Retrieved February 13, 2014.
  36. Unger, Stephen. "September 1973 Newsletter". IEEE Committee on Social Implications of Technology (CSIT). IEEE. Retrieved February 13, 2014.
  37. Healy, Michael (2016). BART : the dramatic history of the Bay Area Rapid Transit system. Berkeley, California: Heyday. ISBN 9781597143707.
  38. "25 years after Loma Prieta quake: BART, then a lifeline, now stronger than ever". BART. Retrieved October 3, 2014.
  39. "San Francisco Earthquake History 1915–1989". The Museum of the City of San Francisco. Archived from the original on March 4, 2016. Retrieved October 3, 2014.
  40. C. M. Hogan, Kay Wilson, M. Papineau et al., Environmental Impact Statement for the BART Daly City Tailtrack Project, Earth Metrics, published by the U.S Urban Mass Transit Administration and the Bay Area Rapid Transit District 1984
  41. Dan Levy (24 February 1996). "Rollicking Opening for Colma BART / Transit system moves closer to S.F. airport". San Francisco Gate. Retrieved 16 September 2016.
  42. "About the San Mateo County Transit District". SamTrans. Retrieved 2007-01-07.
  43. Michael Cabanatuan (April 18, 2003). "BART to link to SFO June 22 After many delays, latest date is firm, transit officials say". the San Francisco Chronicle. Retrieved 2007-01-07.
  44. "Transportation Alternatives for the Bay Area, "Nothing but the Facts"" (PDF). Samceda Peninsula Policy Partnership. April 12, 2002. Archived from the original (PDF) on 2005-12-21. Retrieved 2007-01-07.
  45. Denis Cuff (April 23, 2008). "Ridership soars on BART line to SFO". Contra Costa Times. Retrieved 2008-04-28.
  46. BART to SFO ridership jumps 65%, BART News, June 26, 2008, access date August 26, 2008
  47. "BART Fiscal Year Weekday Average Exits". Bay Area Rapid Transit (BART). Retrieved 9 February 2016.
  48. Erik Nelson (May 14, 2006). "BART to SFO falls short of success story". San Mateo County Times. Retrieved 2007-01-07.
  49. Tom Dempsey (May 31, 2005). "San Mateo County BART disaster: We told you so, in 1995". San Mateo County Times. Retrieved 2007-01-07.
  50. Edward Carpenter (July 27, 2006). "SamTrans struggles with fiscal woes". San Francisco Examiner. Retrieved 2007-01-07.
  51. Michael Cabanatuan (August 12, 2005). "BART's directors approve plan to trim service to S.F. airport". the San Francisco Chronicle. Retrieved 2007-01-07.
  52. "Bay Area Rapid Transit's past, present, and possible futures". San Francisco Cityscape. Archived from the original on 2006-12-29. Retrieved 2007-01-07.
  53. Manekin, Michael (2007-02-16). "SamTrans, BART to dissolve 17-year partnership". East Bay Times. Retrieved 2018-06-03.
  54. "The Story of LAVTA and Wheels". Archived from the original on 2006-12-17. Retrieved 2007-01-18. "
  55. "Dublin Line: Castro Valley – Dublin". Transit-Rider.com. Retrieved 2007-01-07.
  56. https://www.bart.gov/about/projects/ecc/faq
  57. Pal, Meera (May 9, 2007). "Pleasanton gets look at 'transit village'". Tri-Valley Herald. ANG Newspapers. Retrieved 2007-05-09.
  58. Louie, Eric (August 10, 2009). "Welding issues could delay new West Dublin/Pleasanton BART station". Contra Costa Times. ANG Newspapers. Retrieved 2009-08-23.
  59. "BART riders celebrate grand opening of West Dublin/Pleasanton Station Saturday". Bay Area Rapid Transit (BART). February 18, 2011. Retrieved 2013-12-01.
  60. Gary Richards (May 8, 2009). "BART extension to San Jose moving ahead". San Jose Mercury News. Retrieved 2014-08-25.
  61. Bowers, Wes (October 2, 2009). "Warm Springs BART link breaks ground in Fremont". San Jose Mercury News. Archived from the original on August 4, 2016. Retrieved July 10, 2016. Construction on the second phase, which includes track work, the station, line and systems, is anticipated to start next year. BART officials believe construction will last about three and a half years, and the new station to be named South Fremont should be open in 2014.
  62. "Warm Springs Extension Project Overview". BART. May 5, 2011. Archived from the original on May 30, 2011. Retrieved 2015-08-12. Commencement of revenue service to Warm Springs Target Late 2014
  63. Geha, Joseph (December 10, 2016). "BART says Warm Springs/South Fremont won't open until winter 2017". East Bay Times. Retrieved December 12, 2016.
  64. "Software Snafu Delays BART's Warm Springs Station Project". Archived from the original on January 19, 2017. Retrieved January 29, 2017. Software troubles could mean BART’s $900 million Warm Springs extension in Fremont will not be up and running until spring, officials acknowledge.
  65. "Earthquake Safety Program Technical Information". Bay Area Rapid Transit District. Retrieved November 8, 2010.
  66. "Earthquake Safety Program". Bay Area Rapid Transit District. February 11, 2013. Retrieved February 5, 2014.
  67. "BART teams with UC Berkeley to adopt earthquake early warning system". Bay Area Rapid Transit District. September 29, 2012. Retrieved November 24, 2012.
  68. Jordan, Melissa (March 20, 2013). "Late-night work over next 14 months will strengthen Transbay Tube against a quake". Bay Area Rapid Transit District. Retrieved February 5, 2014.
  69. "Transbay Tube retrofit work wraps up early ending late night single tracking". Bay Area Rapid Transit District. December 2, 2013. Retrieved February 5, 2014.
  70. Richman, Josh (May 10, 2012). "BART board approves contract for 410 new train cars". San Jose Mercury News. Retrieved May 11, 2012.
  71. Bowen, Douglas John (May 11, 2012). "BART taps Bombardier; U.S. content at issue". Railway Age. Retrieved May 11, 2012.
  72. "BART – San Francisco" (in French). Morelli Designers. Retrieved July 2, 2015.
  73. "BART Board approves additional 365 cars for Fleet of the Future". BART. November 21, 2013. Retrieved November 26, 2013.
  74. "Board Meeting Agenda" (PDF). San Francisco Bay Area Rapid Transit District. November 21, 2013. pp. 91–92. Retrieved December 5, 2013.
  75. Cuff, Denis (February 26, 2015). "BART changes new train car design to satisfy disabled riders' concerns". Contra Costa Times. Retrieved February 28, 2015.
  76. 1 2 Barmann, Jay (March 22, 2016). "Company Building New BART Cars Has History Of Missed Deadlines". sfist. Archived from the original on March 27, 2016. Retrieved March 30, 2016. Bombardier will be tasked with delivering another nine cars by the end of the year to complete one full, ten-car test train. Following that, they're supposed to be cranking up the assembly line and delivering another 54 cars in 2017.
  77. Hollyfield, Amy (19 January 2018). "BART's Fleet of the Future put into service today". KGO-TV ABC7. Retrieved 31 January 2018.
  78. Cestone; Silletto (22 January 2018). "VIDEO: 2 of 10 new 'Fleet of the Future' BART cars out of service for repairs after 3 days". KRON4. Retrieved 31 January 2018.
  79. 1 2 "New Train Car Project Delivery Plan". Retrieved July 2, 2014.
  80. Richards, Gary (2016). "BART trying to squeeze in more parking spaces". Retrieved November 26, 2016. by 2022 all 775 new cars will be in service.
  81. Cabanatuan, Michael (January 18, 2018). "New BART rail cars approved for service". San Francisco Chronicle.
  82. Hollyfield, Amy (2018-01-19). "BART's Fleet of the Future put into service today". ABC7 San Francisco. Retrieved 2018-01-20.
  83. Matier, Phil (16 July 2018). "BART's Fleet Of The Future Is Already Spending The Present Getting Repaired". KPIX. Retrieved 17 July 2018.
  84. Patrick Hoge (2005-07-03). "BART pay ranks high for transit workers". The San Francisco Chronicle. Retrieved 2007-01-18.
  85. CoinNews (2013). "Current US Inflation Rates: 2003–2013". CoinNews. Retrieved 2013-10-23.
  86. BART (2009). "AGREEMENT BETWEEN SAN FRANCISCO BAY AREA RAPID TRANSIT DISTRICT AND BART SUPERVISORY AND PROFESSIONAL ASSOCIATION (BARTSPA) AFSCME LOCAL 3993" (PDF). BART. Archived from the original (PDF) on 2013-10-21. Retrieved 2013-10-21.
  87. Zach Williams (August 27, 2009). "BART Talks Come to an End as Union Approves Contract". Daily Californian. Retrieved 2013-10-21.
  88. Micheline Maynard (July 5, 2013). "San Francisco BART Strike Ends, Ride-Sharing Raises Its Profile". Forbes. Retrieved 2013-08-01.
  89. Laura Clawson (October 10, 2013). "San Francisco BART workers strike". Daily Kos. Retrieved 2013-10-21.
  90. "Bay Area Rapid Transit System". The American Society of Mechanical Engineers. The American Society of Mechanical Engineers. Retrieved 14 October 2016.
  91. Virginia Miller (October 10, 2004). "BART Receives National Recognition As APTA 2004 Outstanding Public Transportation System". American Public Transportation Association. Archived from the original on 2006-03-25. Retrieved 2007-01-07.
  92. "BART Newsletter: BART named #1 Transit System in US". BART. August 24, 2004. Archived from the original on May 20, 2008. Retrieved 2007-01-07.
  93. "Get BART schedules on your iPod". BART. December 4, 2006. Archived from the original on July 6, 2008. Retrieved 2007-02-09.
  94. "Reflections, the 1970s". the San Francisco Chronicle. December 26, 1999. Retrieved 2007-01-11.
  95. "BART Chronology January 1947 – June 2005" (PDF). BART. 2006-06-30. Archived from the original (PDF) on 2013-10-13. Retrieved 2007-10-26.
  96. Ramas, George L.; Tom Busse (2006-03-14). "Letters to the Editor: BART mishandled SF subway track fire". San Francisco Chronicle. Retrieved 2007-10-26.
  97. Hoffman, Ian (2006-12-02). "Car derailment stalls BART for hours". Oakland Tribune.
  98. "13 Passengers Sustain Minor Injuries In BART Collision". KTVU. 2009-02-03. Archived from the original on 2009-04-14. Retrieved 2009-06-22.
  99. "East Bay News: Construction Worker Struck by BART Train". KGO-TV 7. 2009-07-16. Retrieved 2009-07-16.
  100. 1 2 3 "BART train derails in Northern California; 3 injured". LA Times. 13 March 2011. Retrieved 16 March 2011.
  101. 1 2 "East Bay BART service crippled following derailment". SF Examiner. 13 March 2011. Archived from the original on 1 June 2012. Retrieved 16 March 2011.
  102. http://www.mercurynews.com/breaking-news/ci_24347326/two-bart-workers-killed-during-maintenance-work-strike
  103. "New BART Train Derails During Testing in East Bay". NBC Bay Area. 22 April 2016. Retrieved 9 June 2016.
  104. Cameron, Katrina (7 February 2017). "BART fatality: Pedestrian killed in Richmond". East Bay Times. Retrieved 14 February 2017.
  105. http://sanfrancisco.cbslocal.com/2017/07/09/bart-withholding-surveillance-videos-of-crime-to-avoid-stereotypes/
  106. http://www.sfchronicle.com/news/article/Rider-outs-BART-reports-on-crime-11732835.php
  107. http://www.eastbaytimes.com/2017/09/14/bart-mob-robbery-six-victims-sue-transit-agency-over-brazen-attacks/
  108. 1 2 "BART Chronology January 1947 – March 2009" (PDF). San Francisco Bay Area Rapid Transit District. March 2009. Archived from the original (PDF) on October 13, 2013.
  109. "AirBART fares going up". San Francisco Business Times. February 21, 2007.
  110. "Archived copy". Archived from the original on 2010-01-03. Retrieved 2009-12-17.
  111. "BART Historical Timeline" (PDF). BART.gov. Retrieved 13 May 2016.
  112. Demery, Jr., Leroy W. (November 2011). "U.S. Urban Rail Transit Lines Opened From 1980" (PDF). publictransit.us. Archived from the original (pdf) on November 4, 2013. Retrieved May 13, 2016.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.