Roserock Solar

The Roserock Solar Facility is a 157 MWAC (212 MWp) photovoltaic power station in Pecos County, Texas. It was the largest solar project in Texas when completed in late 2016. The facility is dispersed over about 1300 acres of land already developed for oil and gas by Apache Corporation. It is located about a mile north of Interstate-10, and 20 miles west of Fort Stockton.[1][2]

Roserock Solar Facility
CountryUnited States
LocationPecos County, Texas
Coordinates30°57′37″N 103°18′24″W
StatusOperational
Commission dateDecember, 2016
Construction cost$275 million
Owner(s)Southern Company and Recurrent Energy
Solar farm
TypeFlat-panel PV
single-axis tracking
Site area1,300 acres (5.26 km2)
Power generation
Make and model700,000 CS6X-P modules
Nameplate capacity212 MWp, 157 MWAC
Capacity factor28.8% (average 2017)
Annual net output396 GW·h, 305 MW·h/acre

Facility details

The project was developed by Recurrent Energy, which was acquired by the Sharp Corporation in late 2010.[3] Recurrent Energy was subsequently acquired by the Chinese photovoltaic panel manufacturer Canadian Solar in February 2015.[4] Construction on the project was financed for about $275 million[5] and began in November 2015. The engineering, procurement, and construction contractor was McCarthy Building Companies and the project employed about 480 workers at its peak.[1]

The project uses approximately 700,000 CS6X-P series panels (~300 MWp each)[6] from Canadian Solar that are mounted on single-axis trackers.[1] It began sending electricity to the grid in late November 2016.[7] On November 30, 2016, Recurrent Energy sold a controlling interest in the completed facility to Southern Power. The electricity is being sold to Austin Energy under a 20-year power purchase agreement.[5]

Electricity production

Generation (MW·h) of Roserock Solar [7]
YearJanFebMarAprMayJunJulAugSepOctNovDecTotal
2016 6,49520,330 26,825
2017 27,37129,28039,76737,91641,44237,49641,30136,70231,01931,13221,14520,819 396,390
2018 26,47925,71030,53524,28611,74918,36820,46215,30118,01319,46423,80718,111 252,285
Average Annual Production (years 2017-2018)324,337

See also

References

  1. "Roserock Solar Facility fact sheet" (PDF). Southern Company. Retrieved February 12, 2019.
  2. "Roserock Solar Facility fact sheet". Recurrent Energy. Retrieved February 12, 2019.
  3. "Sharp Corp. to acquire Recurrent Energy" (Press release). Recurrent Energy. September 21, 2010. Retrieved February 12, 2019.
  4. "Canadian Solar Finally Acquires Recurrent Energy for $265 Million in Cash" (Press release). GreenTech Media. February 2, 2015. Retrieved February 12, 2019.
  5. "Recurrent Energy Sells Majority Stake In 212 MW Roserock Solar Project" (Press release). Solar Industry. November 30, 2015. Retrieved February 12, 2019.
  6. "Canadian Solar CS6X-P series module". Retrieved February 12, 2019.
  7. "Roserock Solar, Monthly". Electricity Data Browser. Energy Information Administration. Retrieved March 13, 2019.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.