Agua Caliente Solar Project

The Agua Caliente Solar Project is a 290 megawatt (MWAC) photovoltaic power station, built in Yuma County, Arizona using 5.2 million cadmium telluride modules made by the U.S. thin-film manufacturer First Solar. It was the largest solar facility in the world when the project was commissioned in April 2014.[1][2]

Agua Caliente Solar Project
CountryUnited States
LocationYuma County, Arizona
Coordinates32°58′00″N 113°30′00″W
StatusOperational
Construction began2011
Commission dateApril, 2014
Construction cost$1.8 billion
Owner(s)NRG Energy and BHE Renewables
Operator(s)First Solar Services
Solar farm
TypeFlat-panel PV
fixed tilt
Site area2,400 acres (971 ha)
Power generation
Units operational5.2 million First Solar panels
Nameplate capacity290 MWAC
Capacity factor28.8% (average 2014–2019)
Annual net output732 GW·h, 310 MW·h/acre
External links
Websitehttp://www.firstsolar.com/Resources/Projects/Agua-Caliente-Solar-Project

History

39 MW was online as of December 2011 and 100 MW was completed as of April 2012.[3][4] 200 MW was completed as of July 2012,[5] and 247 MW in August 2012, when the 10th section was completed.[6] The addition of more panels has halted until 2013, with crates of panels covered to protect them.[7] Full power was achieved ahead of schedule in September 2013.[8]

Project overview

In August 2011, the Department of Energy finalized a $967 million loan guarantee for the project. The project sponsor, NRG Solar, estimated the photovoltaic generation facility would fund approximately 400 construction jobs and 16 full-time operating jobs, and would become one of the largest plants of its kind in the world when completed.[9] The power produced is being sold to PG&E (Pacific Gas & Electric) in California in a 25-year Power Purchase Agreement.[10][11]

The Series 3 thin film panels use CdS/CdTe,[12] and are rated from 77 watts to 82.5 watts each,[13] and are mounted at a fixed tilt angle. 20,940 are connected in each array, rated at 1.26 MWAC, and over 400 SMA 720CP inverters are used. Two inverters are connected to each array.[14]

Award

In February 2012, Agua Caliente competed in the Excellence in Renewable Energy Awards and won Project of the Year Award.[11]

Electricity production

2017 production
Generation (MW·h) of Agua Caliente Solar Project [8]
YearJanFebMarAprMayJunJulAugSepOctNovDecTotal
2012 2,83041,75049,64050,44052,65054,14052,83041,78033,535 379,595
2013 34,13845,55553,72061,05064,99865,45263,63161,47064,87064,60548,29447,742 675,525
2014 50,79050,56066,49069,91274,99073,53371,02267,40163,91260,67655,18936,706 741,181
2015 46,00754,67065,49570,82972,74269,88069,30770,31960,02356,97454,11049,378 739,734
2016 49,41258,32767,22766,99775,38569,15973,13669,13560,66260,66250,34843,083 743,533
2017 47,67146,84067,08268,62672,99172,21968,46468,56563,26361,65445,67945,686 728,740
2018 50,15150,87763,71167,51274,18769,70564,46969,55063,47756,04351,74641,896 723,324
2019 45,97946,91262,93067,18171,99971,16866,64670,40062,67964,27047,11938,884 716,167
Average Annual Production (years 2014-2019) -->732,113

See also

References

  1. "World's Biggest Solar PV Plant a Feather in DOE's Cap". breakingenergy.com. April 30, 2014. Retrieved 2020-04-18.
  2. "Agua Caliente, World's Largest Solar Photovoltaic Plant, Helps Advance America's Solar Leadership". U.S. Department of Energy. April 29, 2014. Retrieved 2020-04-18.
  3. Cheyney, Tom (October 14, 2011). "Utility-scale with a capital 'U': First Solar's Agua Caliente PV project pushes toward initial power". PVTech. Archived from the original on 2012-07-22. Retrieved 2012-07-18.
  4. "Arizona project reaches 100MW mark". UPI. 26 April 2012.
  5. Katie Fehrenbacher (16 July 2012). "Huge Arizona solar panel farm now 2/3 completed". Archived from the original on 2012-07-17. Retrieved 2012-07-16.
  6. "World's Largest Operational Solar PV Project, Agua Caliente, Achieves 250 Megawatts of Grid-Connected Power" (Press release). Tempe, Arizona: First Solar. September 10, 2012. Archived from the original on 2013-05-01. Retrieved June 17, 2013.
  7. Martin, Christopher; Doom, Justin (August 30, 2012). "First Solar Stops Installation at Agua Caliente Project". Bloomberg. Retrieved June 17, 2013.
  8. "Agua Caliente Solar Project, Monthly". Electricity Data Browser. Energy Information Administration. Retrieved 2020-04-18.
  9. "Department of Energy Finalizes a $967 Million Loan Guarantee to Support the Agua Caliente Solar Project". Energy.gov. August 5, 2011.
  10. "Agua Caliente Solar Project". CleanEnergy Action Project. Archived from the original on 2013-08-13. Retrieved June 17, 2013.
  11. "Excellence in Renewable Energy Awards Winners: Project of the Year and Readers' Choice". Renewable Energy World. 17 February 2012.
  12. http://www.power-technology.com The world's biggest solar power plants, 29 August 2013
  13. http://www.powermag.com/agua-caliente-solar-project-yuma-county-arizona/?pagenum=1
  14. Olson, Syanne (March 7, 2012). "SMA tapped to deliver more than 400 inverters for Agua Caliente solar project". PVTech. Retrieved June 17, 2013.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.