Line 1 (São Paulo Metro)

Line 1 (Blue) (Portuguese: Linha 1–Azul) is one of the six lines that make up the São Paulo Metro and one of the thirteen lines that make up the Metropolitan Rail Transportation Network. It was the first line built for the São Paulo Metro and also the first metro line built in Brazil. It links Tucuruvi Station to Jabaquara Station. Construction began in the late 1960s and was completed in the early 1970s.

São Paulo Metro Line 1 (Blue)
Overview
TypeRapid transit
SystemSão Paulo Metro
StatusOperational
LocaleSão Paulo, Brazil
TerminiTucuruvi
Jabaquara
Stations23
Operation
Commenced1968
OpenedSeptember 14, 1974
Owner Government of the State of São Paulo
Operator(s) Companhia do Metropolitano de São Paulo
Depot(s)Jabaquara rail yard
Rolling stock
Technical
Line length20.2 kilometres (12.6 mi)
Track gauge1,600 mm (5 ft 3 in)[1]
Electrification750 V DC third rail
Operating speed100 km/h (62 mph)
SignallingAutomatic block signaling
Route map

Tucuruvi
Parada Inglesa
Jardim São Paulo-
Ayrton Senna
Santana
Carandiru
Portuguesa-Tietê
Armênia
Tamanduateí River
Av. do Estado
Tiradentes
 11 
 7 
Luz
 4 
São Bento
 3  to Palmeiras-Barra Funda
 3 
Japão-Liberdade
São Joaquim
 6 
Vergueiro
Paraíso
 2 
Ana Rosa
 2 
Vila Mariana
Santa Cruz
 5 
Praça da Árvore
Saúde
São Judas
Av. Afonso
d'Escragnolle Taunay
Conceição
Jabaquara
Jabaquara rail yard

History

Originally called North-South Line, line 1 began construction on December 14, 1968. Commercial operation began September 14, 1974, with trains running in the first seven kilometers between Jabaquara and Vila Mariana stations. In 1975 it was expanded, first to Liberdade, then to Santana.

In 1978 the Sé station was opened.

In 1998 the line expanded to Tucuruvi,because Santana station didn't settle the number from uses.

Moema branch

Project from expansion by a branc, passing by a importante and big bark and Moema district. That part, is today, in part, the Line 5 lilac.

Stations

Code Station Platforms Position Connections District
TUC Tucuruvi Side platforms Partially underground Tucuruvi Bus Terminal Tucuruvi
PIG Parada Inglesa Side platforms Elevated Parada Inglesa Bus Terminal Tucuruvi
JPA Jardim São Paulo-Ayrton Senna Island platform Underground - Santana
SAN Santana Side platforms Elevated Santana Bus Terminal Santana
CDU Carandiru Side platforms Elevated - Santana
TTE Portuguesa-Tietê Side platforms Elevated Tietê Road Terminal Santana
PPQ Armênia Side platforms Elevated Armênia Bus Terminal Bom Retiro
TRD Tiradentes Island platform Underground - Bom Retiro
LUZ Luz Island and side platforms Underground Line  4 
Lines  7 ,  11  and  13  (Airport-Express)
Bom Retiro
BTO São Bento Split platforms Underground Line  19  (Planned)
PSE Island and side platforms Underground Line  3 
LIB Japão-Liberdade Side platforms Underground -
JQM São Joaquim Side platforms Underground Line  6  (Future) Liberdade
VGO Vergueiro Side platforms Underground - Liberdade
PSO Paraíso Split platforms Underground Line  2  Vila Mariana
ANR Ana Rosa Island platform Underground Line  2 
Ana Rosa Bus Terminal
Vila Mariana
VMN Vila Mariana Side platforms Underground Vila Mariana Bus Terminal Vila Mariana
SCZ Santa Cruz Side platforms Underground Line  5  Vila Mariana
ARV Praça da Árvore Side platforms Underground - Saúde
SAU Saúde Side platforms Underground - Saúde
JUD São Judas Side platforms Underground - Saúde
CON Conceição Side platforms Underground - Jabaquara
JAB Jabaquara Side platforms Underground Line  17  (Planned)
Jabaquara Bus Terminal
Jabaquara Road Terminal
Jabaquara

References

  1. Ferreira, Robert; Tharcisiu Alves. (January 2012). "São Paulo Metro". nycsubway.org. Archived from the original on February 2, 2014. Retrieved February 2, 2014. On Lines 1, 2 and 3, the track gauge is a non-standard 1600 mm, the third rail is 750 V DC and under running. For Lines 4 and 5, the track gauge is 1435 mm and they use overhead pantograph, precluding any connection to the rest of the system, plus the 4 and 5 lines can't connect because the trains on the 4 line use drive-less technology while trains on 5 line are OPTO. Lines 7, 8, 9, 10, 11 and 12 (operated by CPTM) are all 1600mm and use overhead pantograph.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.