Belgrade Metro

The Belgrade Metro (Serbian: Београдски метро / Beogradski metro) is a planned rapid transit system in Belgrade, the capital city of Serbia. Construction of the full metro system has been delayed repeatedly, mostly due to lack of funding.

Belgrade Metro
Proposed metro lines (2018)
Overview
LocaleBelgrade
Transit typeRapid transit
Number of lines2
Number of stations43
Operation
Operation will startunknown
Technical
System length40.5 km

Belgrade has a population of over 1.6 million people, making it the largest city by population without a rapid transit system in Europe. Traffic congestion is common and poor infrastructure has put additional strain on the city, while the existing public transport system is incapable of efficiently shuttling passengers even from the suburbs to the downtown and back, let alone from one outlying end of the city to another. At the same time, the suburban railway system BG Voz, which runs underground through the city centre, is only considered to have a role of S-Train. The construction of a metro is meant to alleviate these problems in the near future.

Due to the decades of misfortune concerning the construction of the metro system, using play-on-words, Belgrade has been jokingly called "half of a metropolis" (in Serbian: "metropolis" - metropola; "subway" - metro; "half" - pola),[1] or the project has been humorously referred to as "Waiting for Metro" (Serbian Latin: čekajući metroa), which in Serbian rhymes with the title of Samuel Beckett's play Waiting for Godot (Serbian Latin: Čekajući Godoa), in which the title character actually never arrives.[2]

History

1920s

Subway has been mentioned for the first time in 1923. It was envisioned by the first urban plan of Belgrade adopted after the international design competition.[3]

1930s

In 1938 the first three routes were proposed: Bulevar kralja Aleksandra-Zemun, Kalemegdan-Autokomanda and Topčider-Viline Vode (Railway station "Dunav"). The Kalemegdan line was planned to be a touristic line, which would be connected with the regular, above the ground tracks and continue to the Avala mountain, outside of the city. The plans were abandoned due to the outbreak of World War II.[1][3]

1950s

After the war ended, authorities concentrated on reconstructing the demolished city infrastructure, pushing the introduction of trolleybuses.[1] City planners have been contemplating the possibility of introducing a metro into Belgrade's transit system again, since the early 1950s, but there were no real projects in that direction.[4] Several ideas have been discussed since the 1950s "General Urban Plan" discussions as to how to build the metro.[5] The first proper plan came in 1958, when architect Nikola Dobrović suggested a line that runs along Kalemegdan, Terazije, Slavija, and Čubura.[1]

1960s

First specialized traffic surveys for the purpose of the future subway were conducted in 1965, only three years after the first such surveys were conducted in Chicago.[6] In 1968, a comprehensive plan came about, led by Savo Janjić. The plan envisioned three lines, totaling a length of 33 km (21 mi), with 35 stations.[7][8] The neighborhoods, projected for the inclusion in the metro grid were: Zemun, New Belgrade, Zvezdara, downtown, Dorćol, Čubura, Banjica, Čukarica, Palilula, Višnjica with later additions of Braće Jerković and Dunavski Venac.[1]

According to the city's general urban plan (GUP) in the 1960s, Cvetni Trg was envisioned as the location of the future central underground subway station of Belgrade, which would also replace the Belgrade Main railway station. The tunnels would conduct the traffic in the north to south direction. The railroad authorities opposed the project, so the plans were abandoned.[9]

1970s

1976 Belgrade Metro plan

The proper work on creating the metro project began with the tenure of mayor Branko Pešić.[1] In 1972,[10] the decision was made to build the new Belgrade railway junction, which would include tunnels under Vračar and Dedinje. Upon completion of the railway junction, construction of a subway system was planned.[1]

For that purpose, the Subway section within the city administration was formed in the early 1970s, headed by Branislav Jovin, Belgrade's chief urban planner at the time.[10] Jovin, and members of his team, visited Munich, Germany, prior to the 1972 Summer Olympics. Munich was chosen specifically as a city with one of the best traffic schematics in Europe, while its subway, Munich U-Bahn, which was finished in 1971, was constructed using the fastest and most modern techniques of the day.[11]

The Section produced the most comprehensive of all metro plans in 1976. The planners envisioned five different metro lines and four additional regional lines. Over 150 experts worked in the section. Geotechnical and geodetic surveys were conducted before the plans were drafted. First lines were supposed to be Zemun-Vukov Spomenik (via New Belgrade and Terazije; with later extension to Mali Mokri Lug) and Kalemegdan-Autokomanda, and it was planned that they would be finished in 8 or 9 years. Projected price of the first 14 km (8.7 mi) of metro was 1 billion euros (in 2009 rates).[10] Other three planned lines were Dorćol-Braće Jerković, Bežanija-Jajinci and Dorćol-Kneževac. From those outer stations, Belgrade would be directly connected via trains with the towns of Zrenjanin, Ruma, Požarevac and Pančevo.[1]

The plan envisioned that Zemun and Terazijska Terasa would be connected by the 1980s, and for that purpose an additional, metro bridge over the Sava was to be built, which would extend from the Nemanjina Street.[1] The entire grid was to have 74 km (46 mi) of tracks and 84 stations while the final deadline for the completion of all lines and other planned objects above the ground was 2021.[2]

1980s

In December 1981, the plan Metro Belgrade was finished and was presented to the city council in 1982. One of the ideas was that the Soviet Union could build the metro, and in doing so free itself of debt owed to Yugoslavia. This was however opposed by the republics Slovenia and Croatia. Due to their objections, this plan has never been carried out.[5]

City organized a compulsory, self-imposed tax (samodoprinos), imposed on the salaries of all employed Belgraders. Set specifically for the construction of the subway, the fund grew to $200 million. As a comparison, city of Vienna, Austria, built its first metro line in 1967 for $100 million. Suddenly, the idea was then declared "too expensive" and the chief city executive Radoje Stefanović suspended the original subway construction plan from 1976 in favor of the expansion of the existing Belgrade tram system network in 1982 ("With trams into the 21st century" project).[1][10] According to architect Dragoljub Bakić, Stefanović summoned the engineers who worked on the project for 12 years, told them to dig a hole and bury all the metro projects in it.[3]

This brought the first chapter of the idea to build a subway system in Belgrade to an ignominious end. The same project was later re-launched a number of times, but it was used for short-term political gains. In 1986, new chief city executive Živana Olbina restored the subway section.[10]

1990s

The economic crisis facing Yugoslavia in the late 1980s became worse in the 1990s. War in the neighbouring republics and economic sanctions only helped to make things worse. Mayor Milorad Unković rejected the project in 1991 and accepted the concept of the light rail transit (LRT).[10] Yet, discussion of a metro system returned, after the completion of the Belgrade railway junction, in 1995. According to officials' talks on the bridge across the Sava river for the metro was planned in 1998.

At first, two underground stations, Vukov Spomenik and Karađorđev Park were opened in 1995 and integrated into the suburban rail system of Beovoz. These are located in tunnels which were constructed for the abandoned metro project and they resemble conventional column metro stations.[12]

Mayor Zoran Đinđić in 1997 revitalized the idea of the full subway, but as he was soon ousted from the office, the new chief city executive Spasoje Krunić later that year suspended the subway section again.[1][4][10]

2000s

2004 Belgrade Metro plan

On 3 July 2004,[13] the BELAM project was presented to the public. Feasibility study from 2004 estimated that the construction of the full subway would be unprofitable as the city is not growing as much as it did in the 1970s, thus the number of commuters is not growing that much either. Project of LTR, partially above and partially under the ground was favored. Price is also taken in account as the study claimed that the LTR line Zemun (Tvornička street)-Konjarnik (Ustanička street) line would cost half of the money, or some 500 million euros. The project of LTR was pushed by mayor Nenad Bogdanović. After hiring two companies to do a study; Juginus, a local company from Belgrade, and the Spanish Ineco, a conclusion was reached that a light rail system should be built. Construction was included into the city's new general plan of 2003 and construction was intended to start in 2006. The opening of the first section was due for 2012 with all two lines complete by 2021. Ineco projected that the train will go above the ground through the longest street in central Belgrade, Bulevar Kralja Aleksandra, but by 2009 that idea was dropped.[10][13]

This decision was severely criticized by a large number of urban planners, led by Branislav Jovin, while architects close to city authorities were advocating the construction, resulting in a substantial polarization between the opponents and proponents of the light metro plan. Announcements were made that the construction would start next spring. Yet, this never came, and the plan for the construction of the light railway system inconspicuously faded out.

As time went on beyond 2004, the plan was altered. The light metro was to have three lines. Construction was supposedly set to begin in 2008, the first line opening in 2013 at a cost of 450 million euros.

Later, mayor Dragan Đilas returned to the idea of the full metro, contrary to the light version.[1] In late 2008, he announced that a metro along the lines of the 1976 plan would be more likely than a light metro. At the session of the National Council for Infrastructure, the Belgrade Metro is, according to the Minister of Infrastructure Milutin Mrkonjić, the third most important project in Serbia, after road and railway networks. Though the Metro became a national issue, there were still no definite plans.

In 2009, Russian delegation visited Belgrade and the loan of 500 million euros for the subway was arranged. However, it failed as Belgrade had no finished project. It was announced that it will take at least 2 years to finish the project and that whether it will be the full or the light metro is still not decided.[10]

2010s

2010-2013

In 2010, it was stated that construction of the Metro would begin in two years. The first line would be an east–west line, going above ground in Novi Beograd and under ground in the centre and neighbouring districts. The second line was planned from north to south, going underground in the centre through the already-constructed tunnels. The two lines would cross in the city centre near the incomplete main railway station Beograd Centar (Prokop).[14]

Funding has not been allocated for the project yet, but it is expected that French or Russian funding sources will be used.[15]

In November 2011, it was stated that the metro would be built with close cooperation/assistance from French companies.[16] The Egis Group would produce an overall metro concept for the city, while the company Alstom envisaged being responsible for tracklaying, electrification, signalling equipment and rolling stock.[16] Again, it was also announced that construction would start in two years.[17]

Some sources say that the system will initially have 36 km (22 mi), and 55 stations, while others say it will have 15 km (9.3 mi) and 25 stations.[16][17] The average speed should be 28.2 km/h (17.5 mph).[17] The construction should last 10 years, as was previously estimated, with each kilometer (0.6 miles) costing some 60 million euros.[18]

In December 2011, the French government talked about allocating one billion euros worth of credit for financing the construction of the metro.[19]

In 2011, it was said that the first metro line was expected to open in 2017 and run from Ustanička street in Central Belgrade to Tvornička street in Zemun.[20]

2014-2019

In 2014, Belgrade's Mayor Siniša Mali talked about the Metro construction being started by 2016, and that the even the French government may support the building and financing of the subway.[21]

As of July 2017 nothing has been done on any of the projects and the metro is still on hold. Instead, a new plan was announced on 3 July 2017, which envisions first two lines as the 22 km (14 mi) long Makiš-Mirijevo (via Sava Amphitheatre and Karaburma) and the 19.8 km (12.3 mi) long Zemun-Ustanička. The construction should start in the end of 2019 or the beginning of 2020 and should be finished in 3 to 4 years. Unlike any of the previous projects, metro is to be complementary with the already existing rail system BG Voz, including the exchange of the passengers. The pre-feasibility study is to be conducted by the Egis Group. The plan is that the study will take nine months to complete and then the main project is to be drafted.[22] The project also differs from all the previous ones as it sets the crossing of the major lines under the Belgrade Waterfront on the Sava bank, a highly controversial pet project of President of Serbia Aleksandar Vučić and mayor Mali, instead under the central city squares of Terazije or Republic Square as planned in the previous decades. Mali also announced that the first line is actually going to be Makiš Field-Mirijevo (that is, Višnjičko Polje). Architects and engineers reacted negatively, especially since both terminuses are at the moment nothing more than still un-urbanized heaths, though mayor Mali said that this line will connect the future projects which will "with the development of metro, bring billions of euros in investments and millions of square meters of the new business areas". Dr Ratomir Vračarević, traffic engineer and professor at the University of Belgrade's Faculty of Technical Sciences said how the surveys showed that this direction has a very low number of potential commuters, well below the profitability level. He added that we still don't know how much of it will go below or above the ground and the Belgrade Waterfront section is going to be costly in general, especially if it goes underground because the area had been built on a landfill. Branislav Jovin, who authored the 1970s subway project, said that everything in the city is being subordinated to the Belgrade Waterfront. He addressed the right of 1.65 million inhabitants of Belgrade who deserve more to have a metro instead of the, still non-existing, population of Belgrade Waterfront, as not one building has been done yet. As the project is made as an ultra luxurious complex for the rich, Jovin asked "do you really believe that people who live in those luxurious apartments will commute via metro?". He also believes that Makiš was chosen because of the announced project of Tesla Grad ("Tesla City") by Bogoljub Karić, Karić, a tycoon who fled the country so that he wouldn't be trialed for financial schemes, returned after the change of government and announced the "Tesla Grad", a business-residential complex in the Makiš Field. The critics also pointed to the fact that Makiš is the major water purification facility in Belgrade and made negative remarks on mayor's assessment that his SMART plan is the "first serious survey" on the subject.[6] Some architects, like Marin Krešić, openly called the Makiš project "pesty".[23]

Stanko Kantar, head of the city's rail transportation section defended the new, meadow-to-meadow, orientation. He basically disputed the 1976 study calling numerous parts of it an error: population density, directions with highest number of commuters, bad connection of the traffic changing points, a distance from the proposed stations. He added that Makiš is good because there is enough space for depot, station and parking and that city will "make money" because the price of the surrounding land will grow. He added that the old study is also bad because it was allegedly made for the projected city of 3 to 3.5 million people while projections set number of 1.9 million by year 2033. Architect Jovin called the entire explanation a manipulation. He claims that Belgrade had 1.4 million people at the time, that grid was made for the city of 2 million and that "distributive journey" envisioned by the plan actually allows for 80% of the inhabitants to arrive from any point A to point B in maximum 30 minutes. He also asserted that methodology used for the 2017 project (numbering of passengers, projected loading) was abandoned in Europe right after World War II and remarked that people who made the plan, in general, are not experts on the matter.[1]

Mayor Mali issued a statement in February 2018 saying that "nowhere in the world the subway is built in densely populated sections of the city". This caused a massive public mockery of his statement in social media, while experts published maps and explanations refuting his claim.[24] Criticism of the pushed Makiš-Višnjica route continued. Members of the Serbian Academy of Sciences and Arts, transportation engineer Dušan Teodorović and a public transportation expert Vukan Vučić disapproved the project. Vučić said that the projected crossing of two lines at Belgrade Waterfront is pointless because both the main bus and railway stations will be dislocated from that position. Teodorović asserted that investors and city administration draw all sorts of lines (metro, railway, etc.) like children do with the markers. Nenad Kecman, executive manager of the Serbian Railways, stated that this is the only case in the world that metro line is not connected to any railway stations. Former head of the Belgrade's Urban Institute and architect Borislav Stojkov also pointed to the disconnection of the planned system with the other routes of the urban transportation and a fact that professionals from the field were not consulted.[25][26]

In February and March 2018 the future metro was one of the focal points of the city government in the campaign for the local elections in Belgrade. A fast construction of the metro was promised and a motto "as quick as saying 'metro'" was coined. Celebrities were enlisted to promote it and to buy the tickets for the future subway.[27][28] After winning the elections, later in March city administration announced a new spatial plan which prioritized a whole series of other projects and pushed the construction of the metro behind. New schedule includes: finishing of the paperwork and starting of the first phase of the first line (Makiš-Ada Huja or Mirijevo) in 2027; finishing of the second phase of the first line (e.g., completing it), finishing of the paperwork for the second line (Ustanička-Zemun) and beginning of its construction in 2033.[29]

The timeline was changed once again in June 2018 when city parliament adopted a new plan. It envisioned drafting of the plan in the next 27 months, beginning of the construction in 2020 and ending of the first line by 2022. Still, deputy mayor Goran Vesić stated that he is not optimistic the project will be finished as planned.[30][31] In the mid-2000s the complete geological surveys have been conducted to examine the Zemun-Ustanička route. For the newly proposed route no actual surveys of any kind were done, and 1,5 to 2 years in needed only for that.[32]

In September 2018, the City Assembly of Belgrade approved the incorporation of a public agency called "Belgrade Metro & Rail" with the purpose of coordinating the upcoming metro project. Deputy mayor Vesić reiterated that the entire project will cost €3 billion, with the first phase expected to cost €1.3 billion. The first phase would see the aforementioned Makiš-Mirijevo line only being built up to Karaburma. "Belgrade Metro & Rail" will also handle the existing "BG Voz" infrastructure, as that system will be integrated with the upcoming metro lines along with a connection to Belgrade Nikola Tesla Airport. Construction of the first phase of the project is said to begin in 2020.[33] The total length of two lines from the first phase should be 42 km (26 mi). Kantar was appointed to head the new metro company.[34] Despite previous arrangements between Serbian and French governments, in April 2019 deputy mayor Vesić announced that the metro will be funded by the Chinese company "Power China" and built in partnership with the city.[35]

Criticism about almost everything about the adopted project continued: routes (starting in non-urbanized areas, missing some of the major streets and medical and university centers, crossing at Belgrade Waterfront instead of in downtown), price (announced by the Egis Group to be €4 billion for the first two lines, €1.8 billion for the first and €2.2 billion for the second), selection of the construction companies without public bidding, lack of numerous studies still needed for the works to be conducted, etc. Deputy mayor Vesić announced that "if everything goes well", the construction will start "by the end of 2020" and that all the needed surveys and studies won't be finished first, before the construction commence, but that project will develop "as it goes".[36][37][38][39] Price turned out to be a major issue. While the same number of lines with roughly the same length was expected to cost €2.2 billion during the previous administration, the estimated price began to grow: €3 billion (mid-2018), €3.6 billion (December 2018), €4.4 billion (June 2019; €2.33+€2.07).[3]

Critics from the NGO sector pointed out to other troublesome facts about the project, following the statements of transportation minister Zorana Mihajlović, Mali (now a finance minister) and Vesić, after the meeting of the French and Serbian presidents Emmanuel Macron and Aleksandar Vučić. After the meeting, Mali stated that "we are closer to the subway than we have ever been." Concerns include: apparently already chosen French and Chinese contractors even though no official contracts for the actual construction of the subway have been signed; lack of an actual project by the government, as the negotiating with the companies includes the possible routes which are being adjusted to the contractors, not to the transportation problems in the city; still non-existing financial construction; absolute bypassing of all the obligatory legal procedures and total lack of transparency, as the deals are being made in direct conversations between few domestic politicians and foreign companies.[40][41] On 19 September 2019, it was decided that the Government of the Republic of Serbia, and not the City of Belgrade, will be the investor.[42] The projected finish of the Tesla City project was set for 2030.[43]

2018-2019 project

Lines

Two lines were planned, with 43 stations, connected to the BG Voz system. Line 1 should start in Železnik and finish in Mirijevo, while Line 2 will start in Mirijevo and finish in Zemun.[44] It was also proposed that in the future, the third line from Banjica will be built.[45] Deputy mayor Goran Vesić also announced the third line, but from Voždovac to the New Belgrade Railway Station,[37] in order to connect the system with the Belgrade Centre railway station as the first two lines go around it completely. However, transportation minister Zorana Mihajlović said that Line 3 is not the "subject of conversations" with the French companies.

The following metro lines are proposed at Phase 1:

Line Route Length Stations Notes[44][46]
L1 Železnik ↔ Mirijevo 21.3 km (13.2 mi) (planned) 23 Construction planned to start in 2020, moved to the end of 2021
L2 Zemun railway station ↔ Mirijevo 19.2 km (11.9 mi) (planned) 20 Construction planned to start in 2020, moved to the end of 2021
TOTAL: 40.5 km (25.2 mi) 43

Stations

Characteristics of the lines and stations include:[44]

  • 42 will be fully underground, with the section at Makiš being above the ground
  • Lines will have connection at Sava Square
  • Mirijevo will have parallel station for both lines
  • Tunnel is planned under the Sava river for Line 2

Line 1

Železnik-Makiš marshalling yard-Žarkovo and Bele Vode-Trgovačka Street-Požeška Street-Banovo Brdo farmers market-Ada Bridge-Belgrade Fair-Gazela Bridge-Palace of Justice-Sava Square-Republic Square-Francuska Street-Port of Belgrade-Dunav Station-Pančevo Bridge-Karaburma railway station-Diljska Street-Višnjička Street-Mirijevo Boulevard-Mirijevo Gymnasium-Mirijevo

Line 2

Zemun railway station-New Novi Sad Road-Filipa Višnjića Street-Zemun Stadium-Senjski Trg-Aleksandra Dubčeka Street-New Belgrade Municipality-Mercator Center Belgrade-Belgrade Arena-Sava Centar-Sava Square-Manjež-Makenzijeva Street-Južni Bulevar-Šumatovačka Street-Vojislava Ilića Street-Cvetkova Pijaca-Mite Ružića Street-Ustanička Street-Mirijevo

2020s

In February 2020, deputy mayor Vesić confirmed the construction will start by the end of 2020,[47] but in May he moved the starting date again, saying they are doing everything for construction to start "by the end of 2021".[46] Company Alstom announced its project, which includes the new bridge across the Sava, and stated that the construction of Line 1 will last for 5 years, once the construction starts.[48] France donated €8.3 million for the feasibility and environmental studies and conceptual design, both of which still haven't been done. Minister Mihajlović also lifted the total price to €4.5-5.5 billion.[49]

See also

  • Belgrade tram system
  • BG Voz
  • Beovoz
  • List of rapid transit systems

References

  1. Dejan Aleksić, Daliborka Mučibabić (11 February 2018). "Metro pola veka na početnoj stanici" [Metro still on the starting point after half a century]. Politika (in Serbian).
  2. Miroslav Simeunović-Simeun (18 September 2018). "Омаж архитекти Браниславу Јовину" [Homage to architect Branislav Jovin]. Politika (in Serbian).
  3. Sandra Petrušić (20 June 2019). Замлаћивање о нашем трошку [Messing around with our money]. NIN, No. 3573 (in Serbian). pp. 22–25.
  4. "Zašto Beograd odavno nema metro?". B92.net (in Serbian). 8 November 2011.
  5. Uroš Komlenović (5 July 1997). "Lightly made promises". Vreme (300). Retrieved 19 October 2010.
  6. Maja Nikolić (9 July 2017). "Ukrštanje linija metroa, umesto u centru, u Beogradu na void" (in Serbian). N1.
  7. Biljana Korica Vukaјlović (22 April 2004). "Laki metro: Težak ispit". Issue 200 (in Serbian). Ekonomist. Archived from the original on 19 June 2015. Retrieved 25 September 2007.
  8. Јanjić, p. 98104 and grid plan.
  9. Arch. Đorđe Petrović (23 July 1968). "Ругло или модерна метро-станица" [Eyesore or a modern subway station]. Politika (in Serbian).
  10. Marijana Avakumović (30 October 2009), "Metro opet na čekanju", Politika (in Serbian)
  11. Miroslav Simeunović Simeun (7 March 2018). "Čekajući metro" [Waiting for metro]. Politika] (in Serbian).
  12. "Energoprojekt". Niskogradnja. Archived from the original on 15 March 2012. Retrieved 8 January 2011.
  13. "Belgrade Metro Project". Urban Rail. 2004. Archived from the original on 14 May 2011. Retrieved 9 September 2009.
  14. "News - Mayor: Construction of metro to begin in two years". B92. 15 May 2010. Archived from the original on 3 November 2012. Retrieved 8 January 2011.
  15. "Trid newspaper: To build the metro in Belgrade" (in Russian). Trud.ru. Retrieved 8 January 2011.
  16. "Beograd metro planning agreement signed". Railway Gazette. 18 November 2011.
  17. "Beogradski metro postaje stvarnost" [Belgrade subway becomes a reality]. s|media (in Serbian). 18 November 2011. Archived from the original on 19 November 2011.
  18. "Prvi koraci ka izgradnji metroa u Beogradu" [The first steps towards building a subway in Belgrade]. Beta.rs (in Serbian). 17 November 2011. Archived from the original on 18 May 2012.
  19. "Od Francuza milijarda evra za metro" [From the French billion euros for subway]. B92.net (in Serbian). 1 December 2011.
  20. "Prva linija metroa 2017. godine od Ustaničke do Tvorničke ulice" [The first subway line in 2017 from Ustaničke to Factory Street]. 24sata.rs (in Serbian). 4 October 2011. Archived from the original on 14 July 2014. Retrieved 1 February 2012.
  21. "Mali: Metro otpočinjemo do 2016". B92.net (in Serbian). 4 July 2014.
  22. Dejan Aleksić (4 July 2017), ""BG vozom" do Resnika naredne godine, metroom tek od 2023", Politika (in Serbian), p. 14
  23. Ivana Nikoletić (21 June 2018). "Da li je Beograd kapitulirao kao grad" [Has Belgrade capitulated as a city]. Danas (in Serbian).
  24. "Niko ne gradi metro u gusto naseljenim delovima grada" [No one builds metro in densely populated parts of the city] (in Serbian). Istinomer. 8 February 2018.
  25. A.Popović (18 April 2018). "Prokop najkatastrofalnija greška saobraćaja u Beogradu" [Prokop (is) the most disastrous error of the Belgrade transportation] (in Serbian). Danas.
  26. Dejan Aleksić, Daliborka Mučibabić (18 April 2018). "Plan za metro u interesu putnika, a ne investitora" [Plan for the metro (should be) in the interest of the passengers, not of the investors]. Politika (in Serbian). p. 14.
  27. "Aja Jung: Metro će Beogradu doneti novu dimenziju" [Aja Jung: Metro will bring a new dimension to Belgrade] (in Serbian). Radio Television Serbia. 21 February 2018.
  28. FoNet (21 February 2018). "Aja Jung: Metroom brže do muzeja, pozorišta, baletske škole" [Aja Jung: faster to museums, theaters, ballet school...by metro] (in Serbian). N1.
  29. A. Popović (23 March 2018). "Rok se produžuje, metro prioritet tek za 2027. godinu" [Deadline is extending, metro priority only in 2027] (in Serbian). Danas.
  30. Branka Vasiljević (27 June 2018). "Plan za metro – za dve godine" [Plan for the metro - in two years]. Politika (in Serbian).
  31. Emina Kovačević (26 June 2018). "Do prve linije metroa ipak teško do 2022, ni Vesić ne veruje" [Hardly to the first metro line by 2022, Vesić doesn't believe it either] (in Serbian). N1.
  32. Daliborka Mučibabić, Dejan Aleksić (30 September 2018). "Нови саобраћајни тунели под водом, кроз брдо и центар града" [New traffic tunnels under water, through the hill and downtown]. Politika (in Serbian).
  33. "Весић: Изградња метроа најважнији пројекат за Београд". City of Belgrade. 25 September 2018.
  34. Branka Vasiljević, Dejan Aleksić (26 September 2018). "Престоница добија предуѕеће за метро" [Capital got a subway company]. Politika (in Serbian). p. 14.
  35. Maja Đurić (26 April 2019). "Planovi za izgradnju metroa u Beogradu - posle Francuza u igri i Kinezi" [Plans for the construction of the Belgrade Metro - Chinese in the game after the French] (in Serbian). N1.
  36. Dejan Aleksić (8 June 2019). "Studija opravdanosti i generalni projekat za metro" [Feasibility study and general project for metro]. Politika (in Serbian). p. 15.
  37. Mladen Savatović (10 June 2019). "Protivnici usvojenih trasa metroa: Zaobilazi Bulevar i centar grada" [Experts against the adopted metro route: bypassing Bulevar kralja Aleksandra and downtown] (in Serbian). N1.
  38. FoNet (10 June 2019). "Ežis: Dve linije beogradskog metroa koštaće četiri milijarde evra" [Egis: two Belgrade metro lines will cost 4 billion Euros] (in Serbian). N1.
  39. FoNet (9 June 2019). "Vesić: Izgradnja metroa počinje sledeće godine" [Vesić: Construction of metro starts next year] (in Serbian). N1.
  40. Jelena Popović (16 July 2019). Никад ближи изградњи београдског метроа [Never closer to the building of the Belgrade Metro]. Politika (in Serbian). p. 6.
  41. Beta (16 July 2019). "Transparentnost: Izgradnja Beogradskog metroa se dogovara mimo zakona" [Transparency: construction of the Belgrade Metro is being negotiated bypassing the law] (in Serbian). N1.
  42. Daliborka Mučibabić (20 September 2019). "Vlada investitor metroa" [Government investor of the metro]. Politika (in Serbian). p. 15.
  43. Dejan Aleksić (12 June 2019). Трећа линија метроа на чекању [Third metro line on hold]. Politika (in Serbian). p. 12.
  44. Beta, eKapija (7 June 2019). "eKapija: Grad prihvatio finalnu trasu metroa, planiran i tunel ispod Save" [eKapija: City adopted final metro route, tunnel under the Sava also planned] (in Serbian). N1.
  45. Mondo.rs (4 December 2019). "Koje delove Beograda će spajati metro" [Which part of Belgrade will be connected by the metro] (in Serbian). Mondo.rs.
  46. Dejan Aleksić (13 May 2020). Камен темељац за метро померен за годину дана [Subways's foundation stone laying moved for a year]. Politika (in Serbian). p. 17.
  47. Beta (10 February 2020). "Vesić: Izgradnja metroa počinje krajem godine, autobusi samo na gas ili struju" [Vesić: Building of the metro begans by the end of the year, buses only on gas or electricity] (in Serbian). N1.
  48. Nikola Kojić (6 February 2020). "Projekat "Alstoma": Gradnja prve linije beogradskog metroa trajala bi pet godina" [Alstom's project: construction of the first line of Belgrade metro would last for five years] (in Serbian). N1.
  49. Beta (12 May 2020). "Srbija i Francuska potpisale sporazum o donaciji 8,3 miliona evra za beogradski metro" [Serbia and France signed an agreement on 8.3 million euros donation for Belgrade metro]. Politika (in Serbian).
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.