Sarah Mildred Long Bridge
Sarah Mildred Long Bridge | |
---|---|
![]() The replacement bridge, as seen from the New Hampshire side | |
Coordinates | 43°05′09″N 70°45′39″W / 43.0859°N 70.7609°WCoordinates: 43°05′09″N 70°45′39″W / 43.0859°N 70.7609°W |
Carries |
![]() ![]() |
Crosses | Piscataqua River |
Locale | Portsmouth, NH, and Kittery, ME |
Official name | Sarah Mildred Long Bridge |
Owner | NHDOT & MaineDOT |
Maintained by | Maine-New Hampshire Interstate Bridge Authority |
Characteristics | |
Design | Concrete lift bridge |
Total length | 2,800 feet (850 m)[1] |
Longest span | 300 feet (91 m)[1] |
No. of lanes | Two |
Rail characteristics | |
No. of tracks | One |
Track gauge | Standard |
History | |
Designer | Hardesty & Hanover |
Engineering design by | Figg Engineering |
Constructed by | Cianbro Corp. |
Opened | March 30, 2018 |
The Sarah Mildred Long Bridge is the name of both a former and present lift bridge spanning the Piscataqua River between Portsmouth, New Hampshire, and Kittery, Maine, carrying traffic of U.S. Route 1 Bypass. The original bridge was in operation from 1940 until 2016. A replacement bridge opened in March 2018.
Original bridge
Sarah Mildred Long Bridge | |
---|---|
![]() The original Sarah Mildred Long Bridge, as seen from Kittery, ME | |
Coordinates | 43°05′09″N 70°45′39″W / 43.0859°N 70.76091°W |
Carries |
![]() ![]() |
Crosses | Piscataqua River |
Locale | Portsmouth, NH, and Kittery, ME |
Official name | Sarah Mildred Long Bridge |
Maintained by | Maine-New Hampshire Interstate Bridge Authority |
ID number | 021702510010800[2] |
Characteristics | |
Design | Steel Truss Lift Bridge |
Total length | 854.7 m (2,804 ft) |
Width | 9.1 m (29.9 ft) |
Clearance above | 5.09 m (16.7 ft) |
Clearance below | 41 m (134.5 ft) (Lift span open) |
History | |
Opened | November 8, 1940[3] |
Closed | August 24, 2016 |
Statistics | |
Daily traffic |
14,000 (2014) 14,900 (1990) |
The original Sarah Mildred Long Bridge was a double-deck truss bridge, with a road deck above and a railroad bed below.
The bridge featured two separate movable spans, the central auto-bearing main lift and a retractable bridge for rail traffic near the Kittery shore. When not in use, the rail span lifted up and retracted south atop its own tracks inside the trusswork. The main span lifted on an as-needed basis for ocean-going commercial traffic, and on a varying set schedule for recreational craft unable to pass beneath the rail span, which was left in an open position by default to accommodate small boats and minimize interruption of auto traffic caused by raising the lift.
History
The original Sarah Mildred Long Bridge was the third span to carry motor vehicle traffic between Maine and New Hampshire at Portsmouth, replacing a river crossing at its location dating from 1822.[4] The bridge was the direct result of the work of the Maine-New Hampshire Interstate Bridge Authority, which had been formed in 1937.[5] The major goal of the bridge project was to relieve congestion in downtown Portsmouth and Kittery, where U.S. Route 1 crossed the river via the Memorial Bridge, which had opened in 1923. The bridge was completed in 1940, a decade and a half before the United States embarked on construction of an ambitious Interstate Highway System.
From 1960 until 1972, the U.S. Route 1 Bypass filled a gap in Interstate 95, linking traffic traveling the otherwise unconnected New Hampshire Turnpike and Maine Turnpike. Although most of the bypass is four lanes wide, the bridge had only a three-lane roadbed, with traffic on the center lane originally switching direction depending on load. This, combined with being a drawbridge, placed the bridge far below Interstate Highway standards. The turnpikes, and I-95, did not directly connect until the opening of the "high level" Piscataqua River Bridge and the extensions of I-95 leading to it in the early 1970s. In the decades leading to the bridge's closure, vehicular traffic had been reduced to just two lanes.
On October 12, 1989, a worker was killed when he was riding on a counterweight as the bridge closed and he was crushed against the bridge's superstructure.[6][7]
On April 1, 2013, a large tanker struck the bridge, causing severe structural damage and leading to a temporary closure of vehicular traffic.[8] As the original Memorial Bridge had been closed in October 2011 and its replacement was under construction, the Piscataqua River Bridge was the only bridge between Kittery and Portsmouth remaining open. The bridge was repaired and re-opened to vehicle traffic on May 13, 2013.[9]
On August 21, 2016, the bridge became stuck in the closed position due to a mechanical failure after a shift in one of its trunnions caused a sheave and thrust block in the south tower to jam. On August 22, officials managed to partially raise the main span to allow shipping to pass under, which is given priority by federal law over road traffic. It was deemed unsafe to resume regular lifting,[10][11] and with NHDOT and MaineDOT officials determining repairs would cost $1 million and take at least six weeks (and permanent closure just four weeks after the earliest possible re-opening), a decision was made to leave the span partially open until demolition.[10] The premature closure of the bridge was announced on August 24, 2016.[12]
Major demolition began with the overnight removal of the center span on October 14, 2016.[13] Removal of the bridge's towers followed, with a goal of removing both towers by November 18, 2016,[14] completed in April 2017.
Railroad
The railroad track that ran across the bridge was originally part of the Boston & Maine Railroad, which connected to South Berwick, Maine, via an easement that is now Maine Route 236.[15] In addition to replacing a vehicular span, the bridge absorbed the traffic of a railroad trestle located just upriver which had collapsed on September 10, 1939.[16] It had been weakened when a caisson used in the construction of the new bridge dragged its anchor cables, which pulled out several of the trestle's bents,[17] sending B&M engine No. 3666 and a baggage car to the bottom of the river, where they remain.[18]
The tracks led to Kittery Junction, at which point one route split off towards York, Maine, on the York Harbor and Beach Railroad, while the other fork led to the Portsmouth Naval Shipyard in Kittery. The York Harbor and Beach branch was abandoned in 1925,[19] leaving only the shipyard branch still in service. That branch is primarily used for the transportation of nuclear materials.[20]
Name
Upon its dedication in 1940 the Sarah Long was simply known as the Maine-New Hampshire Bridge, later the Maine-New Hampshire (Interstate) Bridge. It was renamed in 1987 to honor Sarah Mildred Long, a 50-year employee of the Maine-New Hampshire Interstate Bridge Authority. Starting with the authority at its creation in 1937, Ms. Long rose from secretary to executive director.[21]
Replacement bridge
Construction of a replacement bridge began in January 2015, scheduled to open to traffic in September 2017. The original bridge had been set to close in November 2016,[22] but a mechanical problem that would have cost $1 million to repair moved closure up to August 21, 2016.[11][12][10]
A $158.5 million replacement bridge was constructed by contractor Cianbro Corp. It was designed by a joint venture of Hardesty & Hanover and Figg Engineering. The replacement's 56 feet (17 m) of vertical clearance when closed was designed to be approximately 35 feet (11 m) higher than the original bridge, allowing an estimated 68% fewer openings.[10] Heavily employing cantilevered, post-tensioned concrete spans, it was designed to have eleven fewer piers and an improved ability to absorb ship impact. The bridge deck was also designed to have wider shoulders for bicycle lanes.
An award of $25 million was made by the U.S. Department of Transportation for the railroad portion of the work, reflecting its role in supporting the Portsmouth Naval Shipyard downriver.[23] The replacement bridge features a single 300-foot (91 m) lift span;[24] the lift span has an integrated set of rails, and lowers from the road deck to the railroad level when rail traffic must cross.
The replacement bridge was scheduled to open on September 1, 2017, but the opening was delayed several times. Maine and New Hampshire's DOT officials denied rumors that the bridge is unsafe and stated that the bridge had been "commissioned" in late January 2018. That means that the bridge was lifted under several simulated scenarios, allowing the states to take possession of and open the bridge. Cianbro, the lead contractor, could have been penalized, per the contract terms, $1000 per day for every day the bridge was not open for traffic past September 1, 2017. Additional penalties could have been assessed if the project was not completed by June 1, 2018.[25]
The replacement bridge was officially opened on March 30, 2018.[26][27]
Image gallery
Original bridge
- Sarah Mildred Long Bridge seen from Portsmouth
- Movable rail bed on the bridge
- View upstream from the Memorial Bridge of the Sarah Mildred Long Bridge and Piscataqua River Bridge
- Lift towers
- Nuclear fuel transport train leaving Kittery
Replacement bridge
- Bridge and ramps, from the New Hampshire side
- View from the Maine side
- Incomplete rail bed as of April 2018
See also
Bridges portal New Hampshire portal Maine portal
References
- 1 2 "Sarah Mildred Long Bridge Replacement". cianbro.com. Retrieved April 2, 2018.
- ↑ Nationalbridges.com. "National Bridge Inventory Bridges - 021702510010800". Archived from the original on 2007-09-27. Retrieved 2006-09-29.
- ↑ "New Interstate Bridge Opened". Fitchburg Sentinel. Fitchburg, Massachusetts. AP. November 8, 1940. p. 4. Retrieved March 31, 2018 – via newspapers.com.
- ↑ "Summary of The Sarah Mildred Long Bridge: A History of the Maine-New Hampshire Interstate Bridge from Portsmouth, New Hampshire, to Kittery, Maine". nh.gov. Retrieved 2006-10-02.
- ↑ "Bill for New Bridge Signed by President". The Portsmouth Herald. Portsmouth, New Hampshire. July 29, 1937. p. 1. Retrieved March 31, 2018 – via newspapers.com.
- ↑ "FIRM CITED BEFORE WORKER'S DEATH". The Boston Globe. October 25, 1989. p. 33. Retrieved March 31, 2018 – via pqarchiver.com.
- ↑ "Bridge operator places blame on victim". The Burlington Free Press. Burlington, Vermont. AP. October 21, 1989. p. 15. Retrieved March 31, 2018 – via newspapers.com.
- ↑ "Sarah Long Bridge sustains 'severe structural damage' in crash, DOT says; Bridge closed to vehicular traffic after incident". WMUR-9. Retrieved April 2, 2013.
- ↑ McDermott, Deborah (May 14, 2013). "Sarah Mildred Long Bridge reopens ahead of schedule". Seacoast Online. Retrieved August 24, 2016.
- 1 2 3 4 "A Maine-N.H. Lift Span Retires Early Due to Stuck Sheave". Engineering News-Record. bnp media. September 5–12, 2016.
- 1 2 DeCosta-Klipa, Nik. "New Hampshire lift bridge to Maine stuck in raised position, may not ever come down". Boston Globe. Retrieved August 23, 2016.
- 1 2 "Sarah Long Bridge permanently closed to traffic". WGME-TV. August 24, 2016. Retrieved August 24, 2016.
- ↑ Tranchemontagne, Cam. "DOT Crews remove middle section of Sarah Mildred Long Bridge". WMUR-TV. Retrieved 22 October 2016.
- ↑ Early, Brian. "Removal of Sarah Long Bridge's lift towers begins". Seacoast Online. Seacoast Media Group. Retrieved 22 October 2016.
- ↑ "Eliot History Time Line". Old Berwick Historical Society. March 16, 2001. Retrieved March 31, 2018.
- ↑ "Train Wreck Takes Two Lives". The Portsmouth Herald. Portsmouth, New Hampshire. September 11, 1939. p. 1. Retrieved March 31, 2018 – via newspapers.com.
- ↑ "Boston & Maine Train Accident 1939 Portsmouth NH". Retrieved March 31, 2018 – via YouTube.
- ↑ "TrainWreck #3666, in the Piscataqua River, NH". Retrieved March 31, 2018 – via YouTube.
- ↑ "York Beach Branch is to be Closed by B&M Next Month". The Portsmouth Herald. Portsmouth, New Hampshire. May 15, 1925. p. 1. Retrieved March 31, 2018 – via newspapers.com.
- ↑ "Cianbro Prepares for Milestone Project to Replace Sarah Mildred Long Bridge". cianbro.com. September 26, 2014. Retrieved March 31, 2018.
- ↑ "Portsmouth Herald Obituaries from: Tuesday, March 2, 2004". Archived from the original on April 27, 2006. Retrieved 2006-10-02.
- ↑ Nadeau, Gregory (January 6, 2015). "Breaking ground: A new year, a new bridge". FHWA. US Government. Retrieved August 24, 2016.
- ↑ Koeing, Seth (September 25, 2014). "States agree on price for Kittery-Portsmouth bridge replacement". Bangor Daily News. Retrieved September 25, 2014.
- ↑ "Sarah Mildred Long Bridge Replacement, New Hampshire". roadtraffic-technology.com. Retrieved March 31, 2018.
- ↑ Portsmouth Herald Staff (February 9, 2018). "State officials rebut 'rumors' that new $170M bridge is unsafe". Bangor Daily News. Retrieved February 9, 2018.
- ↑ "New bridge between Maine, New Hampshire opens to traffic". Boston.com. AP. March 30, 2018. Retrieved March 31, 2018.
- ↑ LaCasse, Alex (March 30, 2018). "Sarah Long Bridge opens to traffic amid dispute". seacoastonline.com. Retrieved March 31, 2018.
Further reading
- Openo, Woodard D. (1988). The Sarah Mildred Long Bridge: A History of the Maine-New Hampshire Interstate Bridge from Portsmouth, New Hampshire, to Kittery, Maine. Peter E. Randall. ISBN 0915819120.
- Robinson, J. Dennis (November 1, 2016). "The Ghosts of Sarah Mildred Long". seacoastonline.com. Retrieved March 31, 2018.
- "Sarah Mildred Long (SML) Bridge Replacement". MaineDOT. Retrieved March 31, 2018.
- "Tour of new Sarah Long Bridge". Foster's Daily Democrat. Dover, New Hampshire. March 30, 2018. Retrieved March 31, 2018.
- Barndollar, Hadley (June 8, 2018). "New Sarah Long Bridge celebrated". Foster's Daily Democrat. Dover, New Hampshire. Retrieved June 8, 2018.
External links
![]() |
Wikimedia Commons has media related to Sarah Mildred Long Bridge. |
- gencourt.state.nh.us Legislation outlining the formation of the Maine-New Hampshire Interstate Bridge Authority
- massroads.com Pictures of the original bridge, including the movable rail section in the closed position, via Wayback Machine
- Photographic record of the bridge replacement, by a resident of Portsmouth
- Webcam on the Memorial Bridge, providing a view of the Sarah Mildred Long Bridge