Kennedy Space Center Launch Complex 39

Launch Complex 39 (LC-39) is a rocket launch site at the John F. Kennedy Space Center on Merritt Island in Florida, United States. The site and its collection of facilities were originally built for the Apollo program and later modified for the Space Shuttle program.

Launch Complex 39
Aerial view of Launch Complex 39, showing the Vehicle Assembly Building (front), and launch pads 39B (back left) and 39A (back right)
Launch siteKennedy Space Center
Location28°36′30.2″N 80°36′15.6″W
Short nameLC-39
OperatorNASA
Total launches172 (13 Saturn V, 4 Saturn IB, 135 Shuttle, 1 Ares I, 16 Falcon 9, 3 Falcon Heavy)
Launch pad(s)3
Min / max
orbital inclination
28°–62°
Pad 39A launch history
StatusActive; additions underway for SpaceX Starship
Launches113 (12 Saturn V, 82 Shuttle, 16 Falcon 9, 3 Falcon Heavy)
First launchNovember 9, 1967
Saturn V / Apollo 4
Last launchJanuary 19, 2020
Falcon 9/Crew DragonIn Flight Abort Test
Associated
rockets
Pad 39B launch history
StatusFacility modifications underway for mid 2020 SLS launch
Launches59 (1 Saturn V, 4 Saturn IB, 53 Shuttle, 1 Ares I-X)
First launchMay 18, 1969
Saturn V / Apollo 10
Last launchOctober 28, 2009
Ares I-X
Associated
rockets
Pad 39C launch history
StatusCompleted June 2015
LaunchesTo be determined
Launch Complex 39
LocationJohn F. Kennedy Space Center, Titusville, Florida
Area7,000 acres (2,800 ha)
Built1967
MPSJohn F. Kennedy Space Center MPS
NRHP reference No.73000568[1]
Added to NRHPMay 24, 1973
Launch Complex 39--Pad A
LocationJohn F. Kennedy Space Center, Titusville, Florida
Area160 acres (65 ha)
Built1964-1968
MPSJohn F. Kennedy Space Center MPS
NRHP reference No.99001638[1]
Added to NRHPJanuary 21, 2000
Launch Complex 39--Pad B
LocationJohn F. Kennedy Space Center, Titusville, Florida
Area160 acres (65 ha)
Built1967-1968
MPSJohn F. Kennedy Space Center MPS
NRHP reference No.99001639[1]
Added to NRHPJanuary 21, 2000

Launch Complex 39 consists of three launch sub-complexes or "pads"—39A, 39B, and 39C—a Vehicle Assembly Building (VAB), a Crawlerway used by crawler-transporters to carry Mobile Launcher Platforms between the VAB and the pads, Orbiter Processing Facility buildings, a Launch Control Center which contains the firing rooms, a news facility famous for the iconic countdown clock seen in television coverage and photos, and various logistical and operational support buildings.[2]

SpaceX leases Launch Complex 39A from NASA and has modified the pad to support Falcon 9 and Falcon Heavy launches.[3][4] NASA began modifying Launch Complex 39B in 2007 to accommodate the now defunct Project Constellation, and is currently preparing it for the Space Launch System,[5][6] whose first launch is scheduled for no earlier than June 2020.[7][8] A pad to be designated 39C, which would have been a copy of pads 39A and 39B, was originally planned for Apollo but never built. A smaller pad, 39C, was constructed from January to June 2015, to accommodate small-lift launch vehicles.[9]

NASA launches from pads 39A and 39B have been supervised from the NASA Launch Control Center (LCC), located 3 miles (4.8 km) from the launch pads. LC-39 is one of several launch sites that share the radar and tracking services of the Eastern Test Range.

History

Early history

Northern Merritt Island was first developed around 1890 when a few wealthy Harvard University graduates purchased 18,000 acres (73 km2) and constructed a three-story mahogany clubhouse, very nearly on the site of Pad 39A.[10] During the 1920s, Peter E. Studebaker Jr., son of the automobile magnate, built a small casino at De Soto Beach eight miles (13 km) north of the Canaveral lighthouse.[11]

In 1948, the Navy transferred the former Banana River Naval Air Station, located south of Cape Canaveral, to the Air Force for use in testing captured German V-2 rockets.[12] The site's location on the East Florida coast was ideal for this purpose, in that launches would be over the ocean, away from populated areas. This site became the Joint Long Range Proving Ground in 1949 and was renamed Patrick Air Force Base in 1950. The Air Force annexed part of Cape Canaveral, to the north, in 1951, forming the Air Force Missile Test Center, the future Cape Canaveral Air Force Station (CCAFS). Missile and rocketry testing and development would take place here through the 1950s.[13]

After the creation of NASA in 1958, the CCAFS launch pads were used for NASA's civilian uncrewed and crewed launches, including those of Project Mercury and Project Gemini.[14]

Apollo and Skylab

In 1961, President Kennedy proposed to Congress the goal of landing a man on the Moon by the end of the decade. Congressional approval led to the launch of the Apollo program, which required a massive expansion of NASA operations, including an expansion of launch operations from the Cape to adjacent Merritt Island to the north and west.[15] NASA began acquisition of land in 1962, taking title to 131 square miles (340 km2) by outright purchase and negotiating with the state of Florida for an additional 87 square miles (230 km2). On July 1, 1962, the site was named the Launch Operations Center.[16]

Initial design

Launch Complex Plan – 1963
Warning lamps for the planned 3 pads, including the unbuilt pad C

At the time, the highest numbered launch pad at CCAFS was Launch Complex 37. When the lunar launch complex was designed, it was designated as Launch Complex 39. It was designed to handle launches of the Saturn V rocket, the largest, most powerful rocket then designed, which would propel Apollo spacecraft to the Moon. Initial plans envisioned four pads (five were considered) evenly spaced 8,700 feet (2,700 m) apart to avoid damage in the event of an explosion on a pad. Three were scheduled for construction (A, B, and C, to the southeast), and two (D and E, west and north) would have been built at a later date. The numbering of the pads at the time was from north to south, with the northernmost being 39A, and the southernmost being 39C. Pad 39A was never built, and 39C became 39A in 1963. With today's numbering, 39C would have been north of 39B, and 39D would have been due west of 39C. Pad 39E would have been due north of the midpoint between 39C and 39D, with 39E forming the top of a triangle, and equidistant from 39C and 39D. The Crawlerway was built with the additional pads in mind. This is the reason the Crawlerway turns as it heads to Pad B; continuing straight from that turn would have led to the additional pads.[17]

Integration of space vehicle stack

Apollo-Saturn 506 with Apollo 11 spacecraft being moved from the VAB to LC39A (1969)
A restored Crawler-Transporter (2004)

Months before a launch, the three stages of the Saturn V launch vehicle and the components of the Apollo spacecraft were brought inside the Vehicle Assembly Building (VAB) and assembled, in one of four bays, into a 363-foot (111 m)-tall space vehicle on one of three Mobile Launcher Platforms (MLP). Each mobile launcher consisted of a two-story, 161-by-135-foot (49 by 41 m) launch platform with four hold-down arms and a 446-foot (136 m) Launch Umbilical Tower (LUT) topped by a crane used to lift the spacecraft elements into position for assembly. The MLP and unfueled vehicle together weighed 12,600,000 pounds (5,715 t).[18]

The umbilical tower contained two elevators and nine retractable swing arms that were extended to the space vehicle—to provide access to each of the three rocket stages and the spacecraft for people, wiring, and plumbing—while the vehicle was on the launch pad and were swung away from the vehicle at launch.[18][19] Technicians, engineers, and astronauts used the uppermost Spacecraft Access Arm to access the crew cabin. At the end of the arm, the white room provided an environmentally controlled and protected area for astronauts and their equipment before entering the spacecraft.[20]

Transportation to the pad

When the stack integration was completed, the Mobile Launcher Platform was moved atop one of two crawler-transporters, or Missile Crawler Transporter Facilities, 3–4 miles (4.8–6.4 km) to its pad at a speed of 1 mile per hour (1.6 km/h). Each crawler weighed 6,000,000 pounds (2,720 t) and was capable of keeping the space vehicle and its launcher platform level while negotiating the 5 percent grade to the pad. At the pad, the MLP was placed on six steel pedestals, plus four additional extensible columns.[18]

Mobile Service Structure

Saturn V with fixed (left) and mobile (right) service structures
Apollo-era walkway and white room, on display at Kennedy Space Center Visitor Complex

After the MLP was set in place, the crawler-transporter rolled a 410-foot (125 m), 10,490,000-pound (4,760 t) Mobile Service Structure (MSS) into place to provide further access for technicians to perform a detailed checkout of the vehicle, and to provide necessary umbilical connections to the pad. The MSS contained three elevators, two self-propelled platforms, and three fixed platforms. It was rolled back 6,900 feet (2,100 m) to a parking position shortly before launch.[18]

Flame deflector

While the MLP was sat on its launch pedestals, one of two flame deflectors was slid on rails into place under it. Having two deflectors allowed for one to be used while the other was being refurbished after a previous launch. Each deflector measured 39 feet (12 m) high by 49 feet (15 m) wide by 75 feet (23 m) long, and weighed 1,400,000 pounds (635 t). During a launch, it deflected the launch vehicle's rocket exhaust flame into a trench measuring 43 feet (13 m) deep by 59 feet (18 m) wide by 449 feet (137 m) long.[18]

Launch control and fueling

The four-story Launch Control Center (LCC) was located 3.5 miles (5.6 km) away from Pad A, adjacent to the Vehicle Assembly Building, for safety. The third floor had four firing rooms (corresponding to the four bays in the VAB), each with 470 sets of control and monitoring equipment. The second floor contained telemetry, tracking, instrumentation, and data reduction computing equipment. The LCC was connected to the Mobile Launcher Platforms by a high-speed data link; and during launch a system of 62 closed-circuit television cameras transmitted to 100 monitor screens in the LCC.[18]

Large cryogenic tanks located near the pads stored the liquid hydrogen and liquid oxygen (LOX) for the second and third stages of the Saturn V. The highly explosive nature of these chemicals required numerous safety measures at the launch complex. The pads were located 8,730 feet (2,660 m) away from each other.[18] Before tanking operations began and during launch, non-essential personnel were excluded from the danger area.

Emergency evacuation system

Each pad had a 200-foot (61 m) evacuation tube running from the Mobile Launcher platform to a blast-resistant bunker 39 feet (12 m) underground, equipped with survival supplies for 20 persons for 24 hours. There was also a cab/slidewire system running from the 322-foot (98 m) tower level to evacuate astronauts and technicians 2,503 feet (763 m) away from the pad.[21]

Pad Terminal Connection Room

Connections between the Launch Control Center, Mobile Launcher Platform, and space vehicle were made in the Pad Terminal Connection Room (PTCR), which was a two-story series of rooms located beneath the launch pad on the west side of the flame trench. The "room" was constructed of reinforced concrete and protected by up to 20 feet (6.1 m) of fill dirt.[22][23]

Apollo and Skylab launches

Apollo 11, carrying the first men to land on the Moon, lifts off from pad 39A, July 16, 1969
Final launch of a Saturn IB (AS-210) from pad 39B, carrying the Apollo-Soyuz Test Project Command Module into orbit, July 24, 1975

The first launch from Launch Complex 39 came in 1967 with the first Saturn V launch, which carried the uncrewed Apollo 4 spacecraft. The second uncrewed launch, Apollo 6, also used Pad 39A. With the exception of Apollo 10, which used Pad 39B (due to the "all-up" testing resulting in a 2-month turnaround period), all crewed Apollo-Saturn V launches, commencing with Apollo 8, used Pad 39A.

A total of thirteen Saturn Vs were launched for Apollo, and the uncrewed launch of the Skylab space station in 1973. The mobile launchers were then modified for the shorter Saturn IB rockets, by adding a "milk-stool" extension platform to the launch pedestal, so that the S-IVB upper stage and Apollo spacecraft swing arms would reach their targets. These were used for three crewed Skylab flights and the Apollo-Soyuz Test Project, since the Saturn IB pads 34 and 37 at Cape Canaveral AFB had been decommissioned.[24][25]

Space Shuttle

The thrust to allow the Space Shuttle to achieve orbit was provided by a combination of the Solid Rocket Boosters (SRBs) and the Space Shuttle Main Engines (SSMEs). The SRBs used solid propellant, hence their name. The SSMEs used a combination of liquid hydrogen and liquid oxygen (LOX) from the External Tank (ET), as the orbiter did not have room for internal fuel tanks. The SRBs arrived in segments via rail car from their manufacturing facility in Utah, the External Tank arrived from its manufacturing facility in Louisiana by barge, and the orbiter waited in the Orbiter Processing Facility (OPF). The SRBs were first stacked in the VAB, then the External Tank was mounted between them, and then, with the help of a massive crane, the orbiter was lowered and connected to the External Tank.

The payload to be installed at the launch pad was independently transported in a payload transportation canister and then installed vertically at the Payload Changeout Room. Otherwise, payloads would have already been pre-installed at the Orbiter Processing Facility and transported within the orbiter's cargo bay.

The original structure of the pads was remodeled for the needs of the Space Shuttle, starting with Pad 39A after the last Saturn V launch, and, in 1977, that of Pad 39B after the Apollo-Soyuz Test Project in 1975. The first usage of the pad for the space shuttle came in 1979, when Enterprise was used to check the facilities prior to the first operational launch.

Launch towers

Each pad contained a two-piece access tower system, the Fixed Service Structure (FSS) and the Rotating Service Structure (RSS). The FSS permitted access to the Shuttle via a retractable arm and a "beanie cap" to capture vented LOX from the External Tank. The RSS contained the Payload Changeout Room, which offered "clean" access to the orbiter's payload bay, protection from the elements, and protection in winds up to 60 knots (110 km/h).

The FSS on Pad 39A was constructed from most of the umbilical tower of Mobile Launcher Platform 2, while the FSS that was on 39B was constructed from most of the umbilical tower of Mobile Launcher Platform 3.

Sound Suppression Water System

A Sound Suppression Water System (SSWS) was added to protect the Space Shuttle and its payload from effects of the intense sound wave pressure generated by its engines. An elevated water tank on a 290-foot (88 m) tower near each pad stored 300,000 U.S. gallons (1,100,000 liters) of water, which was released onto the Mobile Launcher Platform just before engine ignition.[26] The water muffled the intense sound waves produced by the engines. Due to heating of the water, a large quantity of steam and water vapor was produced during launch.

Swing arm modifications

The doors to the White Room, which provided entry to the Shuttle crew compartment, are seen here at the end of the access arm walkway

The Gaseous Oxygen Vent Arm positioned a hood, often called the "Beanie Cap", over the top of the External Tank (ET) nose cone during fueling. Heated gaseous nitrogen was used there to remove the extremely cold gaseous oxygen that normally vented out of the External Tank. This prevented the formation of ice that could fall and damage the shuttle.[27]

The Hydrogen Vent Line Access Arm mated the External Tank's Ground Umbilical Carrier Plate (GUCP) to the launch pad hydrogen vent line. The GUCP provided support for plumbing and cables, called umbilicals, that transferred fluids, gases, and electrical signals between two pieces of equipment. While the External Tank was being fueled, hazardous gas was vented from an internal hydrogen tank, through the GUCP, and out a vent line to a flare stack where it was burned off at a safe distance. Sensors at the GUCP measured gas level. The GUCP was redesigned after leaks created scrubs of STS-127 and were also detected during attempts to launch STS-119 and STS-133.[28] The GUCP released from the ET at launch and fell away with a curtain of water sprayed across it for protection from flames.

Emergency pad evacuation

M113 armored personnel carriers parked near LC-39

In an emergency, the launch complex used a slidewire escape basket system for quick evacuation. Assisted by members of the closeout team, the crew would leave the orbiter and ride an emergency basket to the ground at speeds reaching up to 55 miles per hour (89 km/h).[29] From there, the crew took shelter in a bunker. A modified M113 Armored Personnel Carrier could carry injured astronauts away from the complex to safety.[30]

During the launch of Discovery on STS-124 on May 31, 2008, the pad at LC-39A suffered extensive damage, in particular to the concrete trench used to deflect the SRB's flames.[31] The subsequent investigation found that the damage was the result of carbonation of epoxy and corrosion of steel anchors that held the refractory bricks in the trench in place. The damage had been exacerbated by the fact that hydrochloric acid is an exhaust by-product of the solid rocket boosters.[32]

Space Shuttle launches

After the launch of Skylab in 1973, Pad 39A was reconfigured for the Space Shuttle, with shuttle launches beginning with STS-1 in 1981, flown by the Space Shuttle Columbia.[33] After Apollo 10, Pad 39B was kept as a backup launch facility in the case of the destruction of 39A, but saw active service during all three Skylab missions, the Apollo-Soyuz test flight, and a contingency Skylab Rescue flight that never became necessary. After the Apollo-Soyuz Test Project, 39B was reconfigured similarly to 39A; but due to additional modifications (mainly to allow the facility to service a modified Centaur-G upper stage), along with budgetary restraints, it was not ready until 1986. The first shuttle flight to use it was STS-51-L, which ended with the Challenger disaster, after which the first return-to-flight mission, STS-26, was launched from 39B.

Constellation Program and LC-39B

Ares I-X launches from LC-39B, 15:30 UTC, October 28, 2009

The last Shuttle launch from pad 39B was the nighttime launch of STS-116 on December 9, 2006. To support the final Shuttle mission to the Hubble Space Telescope STS-125 launched from pad 39A in May 2009, Endeavour was placed on 39B if needed to launch the STS-400 rescue mission.

After the completion of STS-125, 39B was converted to launch the single test flight of the Constellation Program Ares I-X on October 28, 2009.[34] This program was later cancelled.

2011–2013

With the retirement of the Shuttle in 2011,[35] and the cancellation of Constellation Program in 2010, the future of the Launch Complex–39 pads was uncertain. By early 2011, NASA began informal discussions on use of the pads and facilities by private companies to fly missions for the commercial space market,[36] culminating in a 20-year lease agreement with SpaceX for Pad 39A.[37]

LC-39A

Just as for the first 24 shuttle flights, LC-39A supported the final shuttle flights, starting with STS-117 in June 2007 and ending with the retirement of the Shuttle fleet in July 2011. Prior to the SpaceX lease agreement, the pad remained as it was when Atlantis launched on the final shuttle mission on July 8, 2011, complete with a mobile launcher platform.

KSC Director Bob Cabana announces the signing of the pad 39A lease agreement on April 14, 2014. SpaceX COO Gwynne Shotwell stands nearby.

Talks for use of the pad were underway between NASA and Space Florida—the State of Florida's economic development agency—as early as 2011, but no deal materialized by 2012, and NASA then pursued other options for removing the pad from the federal government inventory.[38]

By early 2013, NASA publicly announced that it would allow commercial launch providers to lease LC-39A,[39] and followed that, in May 2013, with a formal solicitation for proposals for commercial use of the pad.[40] There were two competing bids for the commercial use of the launch complex.[41] SpaceX submitted a bid for exclusive use of the launch complex, while Jeff Bezos' Blue Origin submitted a bid for shared non-exclusive use of the complex, so that the launchpad would handle multiple vehicles, and costs could be shared over the long-term. One potential shared user in the Blue Origin plan was United Launch Alliance.[42] Prior to the end of the bid period, and prior to any public announcement by NASA of the results of the process, Blue Origin filed a protest with the U.S. General Accounting Office (GAO) "over what it says is a plan by NASA to award an exclusive commercial lease to SpaceX for use of mothballed space shuttle launch pad 39A."[43] NASA had planned to complete the bid award and have the pad transferred by October 1, 2013, but the protest "will delay any decision until the GAO reaches a decision, expected by mid-December."[43] On December 12, 2013, the GAO denied the protest and sided with NASA, which argued that the solicitation contained no preference on the use of the facility as multi-use or single-use. "The [solicitation] document merely asks bidders to explain their reasons for selecting one approach instead of the other and how they would manage the facility."[44]

On December 13, 2013, NASA announced that it had selected SpaceX as the new commercial tenant.[45] On April 14, 2014, SpaceX signed a lease agreement[37] that gave it a 20-year exclusive lease on LC-39A.[41] SpaceX plans to launch their Falcon 9 and Falcon Heavy launch vehicles from the pad and build a new hangar nearby.[41][37][46] Elon Musk, CEO of SpaceX, stated that he wanted to shift most of SpaceX's NASA launches to LC-39A, including commercial cargo and crew missions to the International Space Station.[45][47]

Launch history

Pad 39A launches

2.5
5
7.5
10
12.5
15
1967
1970
1975
1980
1985
1990
1995
2000
2005
2010
2015
2020

Pad 39B launches

1
2
3
4
5
6
1969
'73
1975
1980
1985
1990
1995
2000
2005
2009

Current status

A 2006 aerial view of both launch pads at the complex, 39A (foreground) and 39B

Launch Complex 39A

Launch Complex 39A during the Crew Demo-1 mission to the ISS in February 2019, showing the crew access arm and the remodeled 39A service structure
Launch Complex 39A during pad testing of the first Falcon Heavy rocket in December 2017
The SpaceX CRS-10 mission lifts off to the International Space Station in February 2017

On April 14, 2014, the privately owned launch service provider SpaceX signed a 20-year lease for Launch Complex 39A (LC-39A).[48] The pad was modified to support launches of both Falcon 9 and Falcon Heavy launch vehicles, modifications that included the construction of a large Horizontal Integration Facility (HIF) similar to that used at existing SpaceX-leased facilities at Cape Canaveral Air Force Station and Vandenberg Air Force Base, horizontal integration being markedly difference from the vertical integration process used to assemble NASA's Apollo and Space Shuttle vehicles at the launch complex. Additionally, new instrumentation and control systems were installed, and substantial new plumbing was added for a variety of rocket liquids and gases.[49][50]

Construction

In 2015, SpaceX built the Horizontal Integration Facility just outside the perimeter of the existing launch pad in order to house both the Falcon 9 and the Falcon Heavy rockets, and their associated hardware and payloads, during preparation for flight.[51] Both types of launch vehicles will be transported from the HIF to the launch pad aboard a Transporter Erector (TE) which will ride on rails up the former crawlerway path.[38][51] Also in 2015, the launch mount for the Falcon Heavy was constructed on Pad 39A over the existing infrastructure.[52][53] The work on both the HIF building and the pad was substantially complete by late 2015.[54] A rollout test of the new Transporter Erector was conducted in November 2015.[55]

In February 2016, SpaceX indicated that they had "completed and activated Launch Complex 39A",[56] but still had more work yet to do to support crewed flights. SpaceX originally planned to be ready to accomplish the first launch at pad 39A—of a Falcon Heavy—as early as 2015,[49] as they had had architects and engineers working on the new design and modifications since 2013.[57][52] By late 2014, a preliminary date for a wet dress rehearsal of the Falcon Heavy was set for no earlier than July 1, 2015.[38] Due to a failure in a June 2015 Falcon 9 launch, SpaceX had to delay launching the Falcon Heavy in order to focus on the Falcon 9's failure investigation and its return to flight.[58] In early 2016, considering the busy Falcon 9 launch manifest, it became unclear if the Falcon Heavy would be the first vehicle to launch from Pad 39A, or if one or more Falcon 9 missions would precede a Falcon Heavy launch.[56] In the following months, the Falcon Heavy launch was delayed multiple times and eventually pushed back to February 2018.[59]

In 2019, SpaceX began substantial modification to LC 39A in order to begin work on phase 1 of the construction to prepare the facility to launch prototypes of the large 9 m (30 ft)-diameter methalox reusable rocket—Starship—from a launch stand, which will fly from 39A on suborbital test flight trajectories with six or fewer Raptor engines. A second phase of the construction is planned for 2020 to build a much more capable launch mount capable of launching the entire Starship launch vehicle,[60] powered by 43 Raptor engines and producing a total of 72 MN (16,000,000 lbf) liftoff thrust when departing 39A.[61]

Capabilities

SpaceX utilizes the former Fixed Service Structure (FSS) of the Pad 39A launch towers and intends to extend it above its former 350-foot (110 m) height. It did not need the Rotating Service Structure (RSS)[38] and removed it beginning in February 2016.[62]

NASA removed the Orbiter Servicing Arm—with intent to use the space later to build a museum—and the white room by which astronauts entered the Space Shuttle.[52] SpaceX indicated in late 2014 that additional levels to the FSS would not be added in the near term.[38] SpaceX plans to eventually add at least two additional levels to the FSS, to provide crew access for the Dragon 2 launches.[63]

SpaceX assembles its launch vehicles horizontally in a hangar near the pad, and transports them horizontally to the pad before erecting the vehicle to vertical for the launch.[57] For military missions from Pad 39A, payloads will be vertically integrated, as that is required per launch contract with the US Air Force.[57] A hammerhead crane is planned to be added to the FSS in order to support US military requirements for vertical payload integration.[63]

Pad 39A will be used to host launches of astronauts on the crewed-version of the Dragon space capsule in a public–private partnership with NASA. As of April 2014 the NASA plan called for the first NASA crewed missions in 2017.[57] SpaceX intends to add "a crew gantry access arm and white room to allow for crew and cargo ingress to the vehicle. The existing Space Shuttle evacuation slide-wire basket system will also be re-purposed to provide a safe emergency egress for the Dragon crew in the event of an emergency on the pad that does not necessitate using the Crew Dragon's launch abort system."[64]

In August 2018, SpaceX's Crew Access Arm (CAA) was installed on a new level, which was built at the necessary height to enter the Crew Dragon spacecraft atop a Falcon 9 rocket.[65] In September 2018, the refurbished Space Shuttle Emergency Egress System was raised to this new level.

SpaceX launch history

The first SpaceX launch from pad 39A was SpaceX CRS-10 on February 19, 2017, using a Falcon 9 launch vehicle; it was the company's 10th cargo resupply mission to the International Space Station,[66] and the first uncrewed launch from 39A since Skylab.

While Cape Canaveral's Space Launch Complex 40 (SLC-40) was undergoing reconstruction after the loss of the AMOS-6 satellite on September 1, 2016, all SpaceX's east coast launches were from Pad 39A until SLC-40 became operational again in December 2017. These included the May 1, 2017, launch of NROL-76, the first SpaceX mission for the National Reconnaissance Office, with a classified payload.[67]

On February 6, 2018, Pad 39A hosted the successful liftoff of the Falcon Heavy on its maiden launch, carrying Elon Musk's Tesla Roadster car to space;[68] and the first flight of the human-rated spacecraft Crew Dragon (Dragon 2) took place there on March 2, 2019.

The second Falcon Heavy flight, carrying the Arabsat-6A communications satellite for Arabsat of Saudi Arabia, successfully launched on April 11, 2019. The satellite is to provide Ku band and Ka band communication services for the Middle East and northern Africa, as well as for South Africa. The launch was notable as it marked the first time that SpaceX was able to successfully soft-land all three of the reusable booster stages, which will be refurbished for future launches.[69]

Notable future flights

As of October 2019, notable future missions include:

  • A second Dragon 2 mission, Demonstration Mission 2 (DM-2), scheduled for May 27, 2020, will launch Astronauts Bob Behnken and Doug Hurley on a crewed mission from Pad 39A.

Launch Complex 39B

The Mobile Launcher-1 on LC-39B in June 2019 with the Vehicle Assembly Building in the background
Launch Complex 39B as seen from aerial survey in September 2017

After the Ares I-X test flight in 2009, NASA stripped Launch Complex 39B (LC-39B) of its Flight Service Structure (FSS), returning the location to an Apollo-like "clean pad" design for the first time since 1977. This approach is intended to make the pad available to multiple types of vehicles that will arrive at the pad with service structures on the mobile launcher platform, as opposed to using fixed structures on the pad.[70] The LH2, LOX, and water tanks used for the sound suppression system are the only structures left from the Space Shuttle era.[71][72][73]

As of June 2012, repairs and modifications to selected facility systems at LC-39B for Space Launch System (SLS) processing and launch operations, as part of the first phase of a five-phase project, were being completed. The second phase of this project is currently budgeted for $89.2 million.[74]

In 2014, NASA announced that it would make LC-39B available to commercial users during times when it is not needed by the Space Launch System.[57]

In March 2015, pad 39B was undergoing modifications to the Catacomb Roof structure so that it can handle the loads from the SLS Block 1B rocket, increasing the load capacity to support the crawler-transporter and vertical rocket from 21,000,000 to 25,500,000 pounds (9,500,000 to 11,600,000 kg).[71]

Launch Complex 39C

Launch Complex 39C is a new facility for small-lift launch vehicle. It was built in 2015 within the Launch Complex 39B perimeter. It will serve as a multi-purpose site allowing companies to test vehicles and capabilities of the smaller class of rockets, making it more affordable for smaller companies to break into the commercial spaceflight market.

Construction

Construction of the pad began in January 2015 and was completed in June 2015. Kennedy Space Center director Robert D. Cabana and representatives from the Ground Systems Development and Operations (GSDO) Program and the Center Planning and Development (CPD) and Engineering directorates marked the completion of the new pad during a ribbon-cutting ceremony on July 17, 2015. "As America's premier spaceport, we're always looking for new and innovative ways to meet America's launch needs, and one area that was missing was small class payloads", Cabana said.[9]

Capabilities

The concrete pad measures about 50 feet (15 m) wide by about 100 feet (30 m) long and could support the combined weight of a fueled launch vehicle, payload, and customer-provided launch mount up to about 132,000 pounds (60,000 kg), and an umbilical tower structure, fluid lines, cables, and umbilical arms weighing up to about 47,000 pounds (21,000 kg). There is a universal propellant servicing system to provide liquid oxygen and liquid methane fueling capabilities for a variety of small-class rockets.[9]

With the addition of Launch Complex 39C, KSC can offer the following processing and launching features for companies working with small-class vehicles (maximum thrust up to 200,000 lbf or 890 kN):[75]

  • Processing facilities – i.e. Vehicle Assembly Building
  • Vehicle/payload transportation (KAMAG, flatbed trucks, tugs, etc.) from integration facility to pad
  • Launch site
  • Universal propellant servicing system (LOX, LCH4)
  • Launch control center/mobile command center options.[75]

Future development

A map shows the current and proposed elements on KSC.

Previous Kennedy Space Center (KSC) Master Plan recommendations—in 1966, 1972, and 1977—noted that an expansion of KSC's vertical launch capacity could occur when the market demand existed. The 2007 Site Evaluation Study recommended an additional vertical launch pad, Launch Complex 49 (LC-49), to be sited north of existing LC-39B.

As part of the Environmental Impact Study (EIS) process, this proposed launch complex was consolidated from two pads (designated in the 1963 plans as 39C and 39D) to one that would provide greater separation from LC-39B. The area was expanded to accommodate a wider variety of launch azimuths, helping to protect against potential overflight concerns of LC-39B. This LC-49 launch facility could accommodate medium to large launch vehicles.[76]

The 2007 Vertical Launch Site Evaluation Study concluded that a vertical launch pad could also be sited to the south of 39A, and to the north of pad 41, to accommodate small to medium launch vehicles. Designated as Launch Complex 48 (LC-48), this area is best suited to accommodate small to medium class launch vehicles, due to its closer proximity to LC-39A and LC-41. Due to the nature of these activities, required quantity-distance arcs, launch hazard impact limit lines, other safety setbacks, and exposure limits will be specified for safe operations.[76] Details of the proposed launch pads were published in the Kennedy Space Center Master Plan in 2012.

The Master Plan also notes a proposed New Vertical Launchpad northwest of LC-39B and a Horizontal Launch Area north of the LC-49 and converting the Shuttle Landing Facility (SLF) and it apron areas into a second Horizontal Launch Area.[77][76]

Space Florida has proposed that Launch Complex 48 be developed for use by Boeing's Phantom Express and that three landing pads be built for reusable booster systems, to provide more landing options for SpaceX's Falcon 9 and Falcon Heavy, Blue Origin's New Glenn, and other potential reusable vehicles.[78] The pads would be located east of the Horizontal Launch Area and north of LC-39B[79]

In August 2019, SpaceX submitted an Environmental Assessment for Starship launch system at Kennedy Space Center.[80] This document included plans for the construction of additional structures at LC-39A to support Starship launches, including a dedicated pad, liquid methane tanks, and a Landing Zone.[81] These are separate from the existing structures that support Falcon 9 and Falcon Heavy launches.

See also

References

  1. "National Register Information System". National Register of Historic Places. National Park Service. July 9, 2010.
  2. "KSC Facilities". NASA. Retrieved July 6, 2009.
  3. Dante D'Orazio (September 6, 2015). "After delays, SpaceX's massive Falcon Heavy rocket set to launch in spring 2016". The Verge. Vox Media.
  4. "Spacex seeks to accelerate falcon 9 production and launch rates this year". February 4, 2016.
  5. NASA (1993). "Launch Complex 39-A & 39-B". National Aeronautics and Space Administration. Retrieved September 30, 2007.
  6. NASA (2000). "Launch Complex 39". NASA. Archived from the original on September 27, 2012. Retrieved September 30, 2007.
  7. "NASA Completes Review of First SLS, Orion Deep Space Exploration Mission".
  8. Grush, Loren (July 12, 2019). "NASA administrator on recent personnel shakeup: 'There's no turmoil at all'". The Verge. Retrieved July 25, 2019.
  9. NASA (2015). "New Launch Pad will Enable Smaller Companies to Develop and Launch Rockets from Kennedy". NASA. Retrieved July 18, 2015.
  10. "NGS Datasheet for Clubhouse Southwest Gable". National Oceanic Atmospheric Administration (NOAA). Retrieved January 20, 2013.
  11. Eriksen, John M. Brevard County, Florida: A Short History to 1955. See Chapter Ten on De Soto Grove, De Soto Beach, and Playa Linda Beach.
  12. "EVOLUTION OF THE 45TH SPACE WING". US Air Force. Archived from the original on June 13, 2011. Retrieved July 6, 2009.
  13. "The History of Cape Canaveral, Chapter 2: The Missile Range Takes Shape (1949–1958)". Spaceline.org. Retrieved July 6, 2009.
  14. "Cape Canaveral LC5". Astronautix.com. Archived from the original on April 14, 2009. Retrieved July 6, 2009.
  15. "The History of Cape Canaveral, Chapter 3: NASA Arrives (1959–Present)". Spaceline.org. Retrieved July 6, 2009.
  16. "Kennedy Space Center Visitor and Area Information | NASA". Retrieved February 11, 2017.
  17. Petrone, Rocco A. (1975). "Chapter 6: The Cape". In Cortright, Edgar M. (ed.). Apollo Expeditions to the Moon. Washington, DC: Scientific and Technical Information Office, National Aeronautics and Space Administration. SP-350.
  18. Benson, Charles D.; Faherty, William B. (August 1977). "Appendix B: Launch Complex 39" (PDF). Moonport: A History of Apollo Launch Facilities and Operations. History Series. SP-4204. NASA.
  19. "Swing Arm Engineer". NASA. Archived from the original on November 7, 2010.
  20. "Launch Complexes 39-A and 39-B". Retrieved February 11, 2017.
  21. Nye, James (November 21, 2012). "Inside Nasa's blast room: Secret bunker on springs that would have protected Apollo astronauts in a disaster". Retrieved February 11, 2017.
  22. "NASA – Pad Terminal Connection Room".
  23. Young, John; Robert Crippen. Wings in Orbit: Scientific and Engineering Legacies of the Space Shuttle 1971–2010. p. 82. ISBN 978-0-16-086847-4.
  24. "Launch Complex 34". Retrieved February 11, 2017.
  25. "Launch Complex 37". Retrieved February 11, 2017.
  26. "Sound Suppression System". Retrieved October 22, 2007.
  27. "NASA – External Tank (ET) Gaseous Oxygen Vent Arm". nasa.gov. Retrieved December 9, 2016.
  28. "GUCP troubleshooting continues as MMT push for launch on June 17". NASA Spaceflight.
  29. "SPACE.com – NASA Conducts Shuttle Astronaut Rescue Drill". Retrieved October 22, 2007.
  30. "NASA Field Journal by Greg Lohning". Archived from the original on February 4, 2009. Retrieved November 1, 2008.
  31. "NASA Eyes Launch Pad Damage for Next Shuttle Flight". Space.com.
  32. Lilley, Steve K. (August 2010). "Hit the Bricks" (PDF). System Failure Case Studies. NASA. 4 (8): 1–4. Archived from the original (PDF) on September 28, 2011. Retrieved July 20, 2011.
  33. NASA (2006). "Shuttle-Era Pad Modifications". NASA. Retrieved September 30, 2007.
  34. "Pad 39B suffers substantial damage from Ares I-X launch – Parachute update | NASASpaceFlight.com". www.nasaspaceflight.com. Retrieved April 15, 2016.
  35. NASA: Lost in Space, Business Week, 2010-10-28, accessed 2010-10-31.
  36. Dean, James (February 6, 2011). "Up for grabs? Private companies eye KSC facilities". Florida Today. Retrieved February 6, 2011. As the shuttle program nears retirement, KSC officials are evaluating whether other facilities that supported three decades of shuttle flights will transition to serve new vehicles or be discarded. The center is offering use of its launch pads, runway, Vehicle Assembly Building high bays, hangars and firing rooms to private companies expected to play a bigger role in NASA missions and a growing commercial space market.
  37. Dean, James (April 14, 2014). "SpaceX takes over KSC pad 39A". Florida Today. Retrieved April 15, 2014.
  38. Bergin, Chris (November 18, 2014). "Pad 39A – SpaceX laying the groundwork for Falcon Heavy debut". NASA Spaceflight. Retrieved November 17, 2014.
  39. "NASA not abandoning LC-39A" January 17, 2013, accessed February 7, 2013.
  40. NASA requests proposals for commercial use of Pad 39A, NewSpace Watch, May 20, 2013, accessed May 21, 2013.
  41. "Selection Statement for Lease of Launch Complex 39A" (PDF). NASA. December 12, 2013. Retrieved December 23, 2013.
  42. Matthews, Mark K. (August 18, 2013). "Musk, Bezos fight to win lease of iconic NASA launchpad". Orlando Sentinel. Retrieved August 21, 2013.
  43. Messier, Doug (September 10, 2013). "Blue Origin Files Protest Over Lease on Pad 39A". Parabolic Arc. Retrieved September 11, 2013.
  44. Messier, Doug (December 12, 2013). "Blue Origin Loses GAO Appeal Over Pad 39A Bid Process". Parabolic Arc. Retrieved December 13, 2013.
  45. Clark, Stephen (December 13, 2013). "SpaceX to begin negotiations for shuttle launch pad". SpaceflightNow. Retrieved December 13, 2013.
  46. Gwynne Shotwell (March 21, 2014). Broadcast 2212: Special Edition, interview with Gwynne Shotwell (audio file). The Space Show. Event occurs at 20:00–21:10. 2212. Archived from the original (mp3) on March 22, 2014. Retrieved March 22, 2014.
  47. Clark, Stephen (December 12, 2013). "GAO decision opens door for commercial lease of pad 39A". Spaceflight Now. Retrieved December 23, 2013. Musk said he wants to launch SpaceX's commercial cargo and crew missions to the International Space Station from launch pad 39A
  48. Granath, Bob (April 22, 2014). "NASA, SpaceX Sign Property Agreement for Historic Launch Pad". NASA. Retrieved June 22, 2019.
  49. Dean, James (April 14, 2014). "With nod to history, SpaceX gets launch pad 39A OK". Florida Today. Retrieved April 15, 2014.
  50. https://blogs.nasa.gov/spacex/2017/02/19/first-launch-from-lc-39a-at-kennedy-since-2011/
  51. Clark, Stephen (February 25, 2015). "Falcon Heavy rocket hangar rises at launch pad 39A". Spaceflight Now. Retrieved February 28, 2015.
  52. "NASA signs over historic Launch Pad 39A to SpaceX". collectSpace. April 14, 2014. Retrieved April 15, 2014.
  53. Bergin, Chris (February 18, 2015). "Falcon Heavy into production as Pad 39A HIF rises out of the ground". NASASpaceFlight. Retrieved February 19, 2015.
  54. Gebhardt, Chris (October 8, 2015). "Canaveral and KSC pads: New designs for space access". NASASpaceFlight.com. Retrieved October 11, 2015.
  55. Bergin, Chris (November 9, 2015). "SpaceX conducts test rollout for 39A Transporter/Erector". NASASpaceFlight.com. Retrieved November 11, 2015.
  56. Foust, Jeff (February 4, 2014). "SpaceX seeks to accelerate Falcon 9 production and launch rates this year". SpaceNews. Retrieved February 6, 2016.
  57. Clark, Stephen (April 15, 2014). "SpaceX's mega-rocket to debut next year at pad 39A". SpaceflightNow. Retrieved April 16, 2014.
  58. Clark, Stephen (July 21, 2015). "First flight of Falcon Heavy delayed again". spaceflightnow.com. Retrieved October 6, 2015.
  59. Daily, Investor's Business (January 24, 2018). "SpaceX Performs Falcon Heavy Rocket Static Fire Test After Delays | Stock News & Stock Market Analysis - IBD". Investor's Business Daily. Retrieved February 6, 2018.
  60. https://www.nasaspaceflight.com/2019/10/construction-starship-39a-facility-pace/
  61. Groh, Jamie (September 28, 2019). "SpaceX debuts Starship's new Super Heavy booster design". Teslarati. Retrieved October 8, 2019.
  62. "SES-9". SES. SES. October 21, 2014. Archived from the original on October 21, 2014. Retrieved February 23, 2016.
  63. Bergin, Chris (July 28, 2014). "SpaceX Roadmap building on its rocket business revolution". NASAspaceflight. Retrieved July 28, 2014.
  64. Reisman, Garrett (February 27, 2015). "Statement of Garrett Reisman before the Subcommittee on Space Committee on Science, Space, and Technology U.S. House Of Representatives" (PDF). US House of Representatives publication of a SpaceX document provided to the committee. Retrieved February 28, 2015.
  65. Clark, Stephen (August 20, 2018). "SpaceX's astronaut walkway installed on Florida launch pad". Spaceflight Now. Retrieved August 22, 2018.
  66. spacexcmsadmin (January 29, 2016). "CRS-10 MISSION". SpaceX. Retrieved February 18, 2017.
  67. Bergin, Chris (March 9, 2017). "SpaceX Static Fires Falcon 9 for EchoStar 23 launch as SLC-40 targets return". NASASpaceFlight.com. Retrieved March 18, 2017.
  68. Wattles, Jackie. "SpaceX launches Falcon Heavy, the world's most powerful rocket". CNNMoney. Retrieved February 6, 2018.
  69. "Launch Schedule – Spaceflight Now". Spaceflightnow.com. Retrieved February 20, 2019.
  70. "Historic space shuttle pad soon to be scrap". USA Today. March 23, 2011.
  71. Bergin, Chris (March 22, 2015). "KSC Pads continue preparations for future vehicles". NASASpaceFlight.com. Retrieved March 24, 2015.
  72. NASA (2006). "Sound Suppression System". NASA. Retrieved September 30, 2007.
  73. "STS-127 Rollaround starts". Space Flight Now. Retrieved May 31, 2009.
  74. "NASA FY13 Budget" (PDF). NASA. Retrieved February 23, 2016.
  75. NASA (2015). "Launch Complex 39C". NASA. Archived from the original on July 19, 2015. Retrieved July 18, 2015.
  76. "Vertical Launch". NASA. Retrieved June 4, 2018.
  77. "Kennedy Space Center Master Plan Map by Nasa". masterplan.ksc.nasa.gov. August 1, 2017. Retrieved August 19, 2018.
  78. Dean, James (August 5, 2018). "Space Florida proposes launch landing pads at KSC". Florida Today. Retrieved August 19, 2018.
  79. Holton, Tammy (May 22, 2017). "Vertical Landing". masterplan.ksc.nasa.gov. Retrieved August 19, 2018.
  80. "Draft Environmental Assessment for the SpaceX Starship and Super Heavy Launch Vehicle at Kennedy Space Center (KSC)" (PDF). NASA Public NEPA Documents. SpaceX. Retrieved September 20, 2019.
  81. Ralph, Eric (September 18, 2019). "SpaceX prepares to break ground on Starship launch facilities at Pad 39A". TESLARATI. Retrieved September 20, 2019.

 This article incorporates public domain material from the National Aeronautics and Space Administration document: "Launch Pad 39C".