Hallett Wind Farm

Hallett Wind Farms
Country Australia
Location Hallett, South Australia, South Australia
Coordinates 33°22′4″S 138°43′43″E / 33.36778°S 138.72861°E / -33.36778; 138.72861Coordinates: 33°22′4″S 138°43′43″E / 33.36778°S 138.72861°E / -33.36778; 138.72861
Status Operational
Commission date 2008
Owner(s) AGL Energy
Operator(s) AGL Energy
Wind farm
Type Onshore
Power generation
Make and model 166x Suzlon S88,
1x Suzlon S97
Nameplate capacity 351 MW
Website
https://www.agl.com.au/about-agl/how-we-source-energy/renewable-energy/hallett-wind-farm
Hallett Wind Farm

The Hallett Wind Farm is the collective name for four wind farms near the town of Hallett, South Australia. They are owned and operated by AGL Energy.[1]

  • Brown Hill (Hallett 1): 95MW, completed June 2008
  • Hallett Hill (Hallett 2): 71MW, completed May 2010
  • North Brown Hill (Hallett 4): 132MW, completed May 2011
  • Bluff Range (Hallett 5): 53MW, completed March 2012

Brown Hill

Brown Hill Wind Farm, also known as Hallett 1, consists of 45 Suzlon S88 turbines each of a rated 2.1 megawatt (MW) for a total of around 95 MW. It is in the Mid-North of South Australia adjacent to the Hallett Power Station, a pre-existing 180 MW gas fired peaking power plant operated by EnergyAustralia.[2] The wind farm construction was carried out by Suzlon Energy Australia Pty. Ltd. This site utilises an innovative rock anchor solution to support the turbines using only one third of the concrete and reinforcement required in traditional foundations.

Hallett Hill

Hallett Hill Wind Farm, also known as Hallett 2 Wind Farm, was completed in late 2009. It consists of 34 Suzlon turbines each 2.1MW, giving an installed capacity of 71.4MW. Up to March 2011 it was averaging a capacity factor of 39%.

In December 2010, AGL identified that under certain wind conditions tones from the wind turbines were audible at the nearest residence. Resonance dampers have since been installed to address this tonality issue with the wind turbines.[3] Noise testing has confirmed that this permanent acoustic treatment has fixed the tonality issue.[4]

North Brown Hill

AGL's North Brown Hill Wind Farm, alternatively called Hallett 4 Wind Farm, has 63 turbines with a total installed capacity of 132MW, and cost A$334 million to build. The first power flowed into the south eastern Australian electricity grid in August 2010 and the project was up to full operation in early 2011.[5]

Bluff Range

AGL's Bluff Range Wind Farm, also known as Hallett 5 Wind Farm consists of 25 Suzlon turbines each of 2.1MW for a total of 52.5MW. Total project investment was $120 million.[6] The project was completed in early 2012.[7]

See also

References

  • Wind Power and Wind Farms in South Australia
  • Photographs of Hallett (Brown Hill Range) wind farm
  • AGL Energy to build wind power project
  • "AEMO Participant Registration List". Retrieved 14 March 2014.