A3 motorway (Romania)

A3 motorway shield}}

A3 motorway
Autostrada A3
Route information
Maintained by Compania Națională de Autostrăzi și Drumuri Naționale din România
Length 117 km (73 mi)
603 km (375 mi) planned
128 km (80 mi) under construction
Existed 2009 – present
Major junctions
South end Bucharest
 
North end Borș (planned to merge with the M4 at the border with Hungary)
Location
Counties Ilfov, Prahova, Brașov, Sibiu, Mureș, Cluj, Sălaj, Bihor
Major cities Bucharest, Ploiești, Brașov, Făgăraș, Sighișoara, Târgu Mureș, Cluj-Napoca, Zalău, Oradea
Highway system

Motorways in Romania

A2A4

The A3 motorway (Romanian: Autostrada A3) is a partially built (approx. 18%) motorway in Romania, planned to connect Bucharest with the Transylvania region and the north-western part of the country. It will be 603 km long and will run along the route: Ploiești, Brașov, Făgăraș, Sighișoara, Târgu Mureș, Cluj-Napoca, Zalău and Oradea, connecting with Hungary's M4 motorway near Borș.[1]

As of September 2018, there are two separate segments in service totalizing 107 km: the BucharestPloiești motorway (55 km) and the Câmpia TurziiNădășelu segment (61.2 km).[2][3]

A short segment (6.5 km) between the Bucharest Ring Road and the Bucharest downtown remains under construction as of September 2018, with a close to completion status.[4]

In January 2015, the motorway section between Câmpia Turzii and Târgu Mureş was awarded for construction. It is divided into two segments, with a total of five lots, which sum up to 56.5 km.[5]

The remaining works on the Suplacu de BarcăuBorș segment (64.5 km) were auctioned for the third time in the first half of 2018,[6][7] with some of the winners of the bids still pending.

Bucharest – Brașov section

A3 motorway between Bucharest and Ploieşti
Construction of the Motorway Bucharest–Brașov
Section Length Period of construction Contractor Total cost Financier Status
BucharestMoara Vlăsiei 19.5 km May 2008 – August 2017 Impresa Pizzarotti and Tirrena Scavi 673.7 m lei State budget 13.0 km in service;
6.5 km under construction
Moara Vlăsiei – Ploiești 43.0 km July 2007 – August 2012 Spedition UMB, Pa&Co Internațional, Euroconstruct 98, Com-Axa 883.7 m lei State budget In service
Ploiești – Comarnic 48.6 km 379.4 m Euro (est.) planned
Comarnic – Brașov 58 km State budget broken into lots; tendering restarted

This motorway section (also called the "Snow Motorway") will cross the Carpathian Mountains along the Prahova Valley (the ComarnicBrașov segment is considered the most difficult section to be built). It will also provide access to the future Terminal 2 of the Henri Coandă Airport and to the future Bucharest – Chișinău motorway, via the Ploiești South-East/Dumbrava interchange.

It was split into three segments: the BucharestPloiești segment (62 km), the PloieștiComarnic segment (48.6 km) and the ComarnicBrașov segment (58 km).

Works on the BucharestPloiești section started on 15 March 2007 and were due to be completed by October 2012.[8] The first segment, from Bucharest to Moara Vlăsiei, is built as a six-lane set of carriageways to accommodate commuting and holiday surplus traffic. It was built by the Italian joint venture between Impresa Pizzarotti and Tirrena Scavi, while the second segment, from Moara Vlăsiei to Ploiești, was built by the Romanian companies Spedition UMB, Pa&Co Internațional and Euroconstruct '98. Total construction cost of this section was estimated at 450 million euro.[9] The section between the Bucharest Ring Road and Ploiești (55.5 km) was opened on 19 July 2012, while the rest of the section towards downtown Bucharest remained to be completed.[10]

A3 motorway near Snagov. The section between Bucharest and Moara Vlăsiei is the only motorway in Romania that currently has three lanes in each direction.

The Bucharest – Bucharest Ring Road segment is part of the Bucharest – Moara Vlăsiei section and is currently under construction. It starts with a roundabout at the junction between the Fabrica de Glucoză and the Petricani Street (near 44°28′43″N 26°07′31″E / 44.47861°N 26.12528°E / 44.47861; 26.12528), crosses over the Balta Saulei Lake, intersects the Gherghiței Street with a second roundabout (near 44°28′43″N 26°08′16″E / 44.47861°N 26.13778°E / 44.47861; 26.13778), then continues northbound, crossing over the CFR Line 800, the Popasului Street (in Voluntari, where it has a diamond interchange near 44°29′33″N 26°08′57″E / 44.49250°N 26.14917°E / 44.49250; 26.14917) and the Bucharest Ring Road, as well as the railroad again.

On the Popasului Street (Voluntari) – Bucharest Ring Road segment (4 km) works have started in April 2012. On the Petricani Street (Bucharest) – Popasului Street (Voluntari) segment (2.5 km) works have constantly been delayed, partly because of remaining unfinished expropriations,[11] until the contract was finally terminated.[12] In December 2015, the construction works of the first 3.3 km of the motorway, the Bucharest Ring Road junction and the still under construction Moara Vlăsiei exit were awarded to the joint-venture between Aktor and EuroConstruct Trading 98, for a cost of 129.2 million lei.[12] They were planned to be completed by 2018, but the progress remains slow.[13]

The PloieștiComarnic section has been in pre-feasibility phase and its profitability is being considered.[14] It is complemented by a relatively settlement-free section of the parallel national road DN1.

Comarnic – Brașov section

Construction of the section Comarnic–Brașov
Section Length Period of construction Contractor Total cost Financier Status
Section 1: Comarnic Sud – Comarnic Nord 3.4 km[15] Tendered
Section 2: Comarnic Nord – Buşteni 16.3 km[15] Feasibility studies
Section 3: Buşteni – Predeal 12.8 km[15] Feasibility studies
Section 4: Predeal – Râşnov 15.2 km[15] Feasibility studies
Section 5: Râşnov – Cristian 5.4 km[15] Contract signed

Works on the ComarnicBrașov section, the most difficult segment of the motorway, were due to begin in 2010 and take around four years to complete,[16] but the FrenchGreek consortium VinciAktor denounced the contract and construction was canceled.[17] Total construction cost of this section was estimated at 1.2 billion euro.[18]

The segment was re-tendered as a concession contract in February 2013.[19] It has been awarded in December 2013 to the joint venture between Vinci, Strabag and Aktor,[20] for a period of 29 years,[21] with an estimated construction cost of 1.8 billion euro.[22] This section of the motorway would have three twin tunnels, with a total length of 19.4 km,[23][24] at Sinaia, Bușteni and Predeal,[25] and four interchanges, at Comarnic, Bușteni, Predeal and Râșnov.[26] The route would follow the river valley until Posada,[26] where it would cross on the opposite side of the river and would run along the mountain range until Sinaia, from where it would then run nearly straight until Azuga, crossing through two twin tunnels that would bypass Sinaia and Bușteni, before crossing again to the eastern side of the river.[27] According to media reports, works were expected to begin in April 2014,[21] but they were still pending, due to financial arrangements and the environmental certificate.[28] According to the same reports, they had to be finalized in 2017.[29]

As of 19 June 2015, the concession had been canceled.[30]

As of 15 October 2015, section 1 (3.4 km) and section 5 (5.4 km) at the ends of the Comarnic – Braşov section were separately tendered. For section 1, a bid by Spedition UMB and Tehnostrade remained the only one, while the other tender was leaning towards a consortium led by the Spanish construction company Copisa.[31][32] However, as of December 2017, only the Râşnov – Cristian segment was awarded for construction, to the Cypriot company Alpenside.[33]

Brașov – Oradea section

A3 motorway between Gilău and Turda
A3 motorway near Cheile Turului
Suplacu de Barcău Viaduct under construction

This motorway segment, known as the Transylvania Motorway (Romanian: Autostrada Transilvania), was split into three parts, with several subsections: the Brașov (Cristian) – Târgu Mureș (Ogra) segment (160.1 km), the Târgu Mureș (Ogra) – Cluj-Napoca West (Gilău) segment (89.7 km) and the Cluj-Napoca West (Gilău) – Oradea West (Borș) segment (165.5 km).[34]

Of this section, only the Câmpia TurziiCluj-Napoca West (Gilău) segment (51.7 km) is completed and opened for traffic, since November 2010. The Suplacu de BarcăuBorș segment (64.5 km) has been under construction since 2004, but the contract was terminated in May 2013,[35] with the construction progress around 50%.[36]

In June 2014, new tenders were announced for several segments: Târgu MureșOgra (14.6 km)[37] and OgraCâmpia Turzii (37.2 km),[38] as well as for the remaining works on the Suplacu de BarcăuBorș segment (60.2 km).[39]

In the autumn of 2014, the GilăuNădășelu segment (8.7 km) was set to begin construction.[36]

Bechtel controversy

The entire section was originally scheduled to be built by the American company Bechtel Corporation together with its regional partner Enka A.Ş. of Turkey. The contract was awarded in 2004 to the Bechtel Corporation by the Social Democrat Prime-Minister Adrian Năstase without an open bidding process, invoking "national security" as an excuse.[40] The estimated construction cost was 2.8 billion € in 2003 and it rose to 4.7 billion € in a 2007 estimate.[41] Although officially the deadline was set for 2013, the final cost and finalization date remained unknown.[42]

As per the Romanian ministry of transportation, Anca Boagiu, the original contract was highly disadvantageous to the Romanian side. Following the contract renegotiation that occurred in June–July 2011,[43] Bechtel agreed to lower the building cost per kilometer by 50% down to 6.9 million euro.[44] Also it was decided that the American company will build only two segments (BorșSuplacu de Barcău and GilăuCâmpia Turzii), leaving all the other segments of the motorway open for tendering.[45]

Construction progress

The official groundbreaking ceremony for the Transylvania Motorway was held near the village of Vălișoara on 16 June 2004. On 1 December 2009, the TurdaGilău segment (42 km) was opened for traffic, followed on 13 November 2010, by the Câmpia TurziiTurda segment (10 km). As of January 2012, works were being performed only on the Suplacu de Barcău – Oradea West (Borș) segment,[46] with 17 km planned to be opened on 15 November 2012 and other 18 km on 30 August 2013.[47] However, not much progress was visible on this section by August 2012,[48] and the bridge across the Someșul Mic river, part of the Câmpia Turzii – Cluj-Napoca West (Gilău) segment, was also yet to be built.[49] In May 2013, the contract with the Bechtel Corporation was terminated through mutual agreement.[35] The construction status of the Suplacu de Barcău – Borș segment is reportedly at 50%.[36]

An additional 8.7 km segment, between Gilău and Nădășelu, was tendered in August 2012,[50] and awarded to the joint venture between Spedition UMB and Tehnostrade in April 2013.[51] Works on this segment were scheduled to begin as late as six months after signing the contract and take one year and a half to complete.[52] The segment would act as a bypass for Cluj-Napoca, the second most populous city in the country, on the route towards Zalău and Baia Mare.[53] The contract was reportedly terminated in June 2013, before any construction works started,[54] but works began in the summer of 2014, with an expected opening date in April 2016.[36][55] As of April 2017, the segment was largely completed, but unusable due to the fact that the bridge bridge across the Someșul Mic river connecting with the Câmpia Turzii – Cluj-Napoca West (Gilău) segment was not completed.[56] A contract for the remaining works to this bridge was signed in September 2017, and they were expected to be completed by August 2018.[57] The works were finally completed in September 2018.[3] The contractor was the Italian company Tirrena Scavi.

The Section 2A from Târgu Mureş, via Ogra, to Câmpia Turzii, with a length of 52 km, was tendered in 2014,[58] and for four out of five lots, contracts have been signed at the end of February and early March 2015. Construction was set to take between 12 and 16 months, depending on the lot. The Târgu Mureş – Ogra lot 1 (between Târgu Mureş – Ungheni, 4.5 km of motorway and 4.7 km of connecting road) was awarded to the joint-venture Lemacons - Vega 93 - Arcada Company, for a cost of 179.8 million lei (excluding VAT). The Târgu Mureş – Ogra lot 2 (between Ungheni – Ogra, 10.1 km) was awarded to the joint-venture between Strabag and Straco Grup, for a cost of 251.3 million lei (excluding VAT). The Ogra – Câmpia Turzii lot 1 (between Ogra – Iernut, 3.6 km) was awarded to the joint-venture Geiger Transilvania - Wilhelm Geiger GmbH & Co. KG, for a cost of 55.8 million lei (excluding VAT). The Ogra – Câmpia Turzii lot 2 (between Iernut – Cheţani, 17.9 km) was awarded to the joint-venture between Astaldi and Max Bögl, for a cost of 379.7 million lei (excluding VAT). The Ogra – Câmpia Turzii lot 3 (between Cheţani – Câmpia Turzii, 15.7 km) was awarded to the joint venture Straco Grup - Specialist Consulting - Total Road, for a cost of 279.7 million lei (excluding VAT).

The contract for the Târgu Mureş – Ungheni section (lot 1) was terminated in April 2016, due to delays in pre-construction arrangements by the CNADNR,[59] and was awarded again in November 2017, to the Austrian company Strabag.[60]

The remaining works on the Suplacu de BarcăuBorș segment (64.5 km) were also awarded for construction in April 2015 (to the joint-venture of Corsán and Corviam Construcción),[6] but no progress had been recorded as of January 2016.[61] In November 2016, the contract was reportedly close to being terminated.[62] Works were auctioned for the third time in the first half of 2018,[6][7] with some of the winners of the bids still pending. The section is divided into three lots: lot 1, Suplacu de Barcău – Chiribiş (26.3 km); lot 2, Chiribiş − Biharia, lot 2 (28.6 km), lot 3, Biharia − Borş (5.4 km). Two of the lots were reportedly awarded to the Romanian company Selina.[7]

Openings timeline

Segments currently under construction

  • Next scheduled opening: Bucharest (Petricani Street) – Bucharest Ring Road segment (6.5 km) is mostly complete and will be likely be opened to use in November 2018
  • Râşnov – Cristian segment (5.4 km) is due to begin construction and likely to be completed in 2019
  • Târgu Mureş – Ogra segment (4.6 km) is currently being auctioned, likely to be completed in 2019
  • Ogra – Câmpia Turzii (37.2 km) is in construction, with scheduled openings in 2018 and 2019
  • Suplacu de Barcău – Borş (60.2 km) is currently being auctioned.

Exit list

Exits and buildings (Northbound)
Bucharest – Ploiești (62 km)
km 6 Gherghiţei Street, Bucharest under construction
km 9 Popasului Street, Voluntari under construction
km 13 Bucharest Ring Road opened July 2012
km 16 Parking under construction
km 23 Parking under construction
km 25 Moara Vlăsiei under construction
km 26 Parking southbound only
km 30 Snagov opened July 2012
km 34 Parking under construction
km 38 Ialomița River opened July 2012
km 41 Parking under construction
km 43 Gherghița / Potigrafu opened November 2015
km 47 Prahova River opened July 2012
km 49 Parking under construction
km 56 Parking under construction
km 63 Parking under construction
km 68 Ploiești South opened July 2012
Câmpia Turzii – Nădășelu(61 km)
km 0 Câmpia Turzii opened 2010
km 9 Turda / Aiud opened 2009
km 9 Sebeş, Alba Iulia opened July 2018
km 10 Parking under construction
km 12 Arieș River opened 2009
km 12 U-turn exit northbound only
km 44 U-turn exit southbound only
km 46 Parking under construction
km 51 Cluj-Napoca West / Gilău opened 2009
km 52 Someșul Mic River opened Sept 2018
km 61 Nădășelu opened Sept 2018

See also

References

  1. "Autostrazile din Romania au fost conectate cu cele din Ungaria. Pe hartie". Hotnews.ro. 5 July 2011.
  2. "De azi, România are 500 de kilometri de autostradă. S-au deschis A2, A3 și A4". Obiectivbr.ro. 20 July 2012.
  3. 1 2 3 https://monitorizari.hotnews.ro/stiri-infrastructura_articole-22726584-video-fost-deschi-traficului-rutier-cei-9-6-dintre-gil-elu-a3-transilvania.htm
  4. https://www.capital.ro/o-noua-autostrada-in-romania-este-aproape-gata-foto-video.html
  5. http://monitorizari.hotnews.ro/stiri-infrastructura_proiecte-20249457-autostrada-a3-campia-turzii-ogra-mures-afacerea-bechtel-fondurile-europene-pierd.htm
  6. 1 2 3 http://monitorizari.hotnews.ro/stiri-infrastructura_articole-19848067-segmentul-autostrada-suplacu-barcau-bors-are-constructor-desemnat-trebui-realizeze-doi-ani-pretul-celor-64-este-701-milioane-lei-plus-tva.htm
  7. 1 2 3 http://www.bihon.ro/selina-doua-loturi-pe-autostrada-bors-suplacu-de-barcau/2067379
  8. "Au inceput lucrarile la tronsonul lipsa din Autostrada Bucuresti - Ploiesti". Finantistii.ro. 17 April 2012. Archived from the original on 16 May 2012.
  9. "Deschiderea autostrăzii București-Ploiești, amânată din nou". Mediafax.ro. 28 June 2012.
  10. 1 2 "Autostrada A3 Bucuresti - Ploiesti, deschisa traficului de joi dimineata". Hotnews.ro. 19 July 2012.
  11. "Circulatie deschisa pe Autostrada Bucuresti - Ploiesti. Constructia ultimului sector mai dureaza totusi 2 ani". Finantistii.ro. 19 July 2012. Archived from the original on 22 July 2012.
  12. 1 2 https://monitorizari.hotnews.ro/stiri-infrastructura_articole-22056656-video-imagini-din-drona-ciotul-3-din-autostrada-a3-care-construieste-intrarea-bucuresti-zona-pipera-petricani-unde-exista-blocaj-cand-putea-gata-autostrada.htm
  13. https://monitorizari.hotnews.ro/stiri-infrastructura_articole-22512997-video-imagini-din-dron-ciotul-autostrad-care-intr-bucure-lucr-rile-treneaz-iar-cei-3-risc-nu-fie-gata-nici-anul-acesta.htm
  14. "Se relansează proiectul autostrăzii Comarnic-Braşov". Romania Libera. 26 February 2012.
  15. 1 2 3 4 5 "Prezentarea Proiectului de concesiune Autostrada Comarnic–Brasov" (PDF) (in Romanian). CNADNR. p. 15 f. Archived from the original (PDF) on 28 March 2016. Retrieved 12 May 2016.
  16. "Bucharest - Brasov highway works launched". Hotnews.ro. 15 March 2007.
  17. "Ministerul Transporturilor va "revizui" în martie Autostrada Brașov – Comarnic". Adevarul.ro. 25 February 2012.
  18. "Autostrada Comarnic-Brasov, scumpa dar spectaculoasa". Stirileprotv.ro. 27 January 2010.
  19. "Regii români ai asfaltului se bat cu italienii de la Astaldi şi austriecii de la Strabag pentru concesionarea autostrăzii de sud a Capitalei". ZF.ro. 28 February 2013.
  20. "Asocierea Vinci-Strabag-Aktor va construi în concesiune Autostrada Comarnic-Braşov pentru 1,2 miliarde de euro". Adevărul. 19 December 2013.
  21. 1 2 "Autostrada A3, trambulină pentru europarlamentare?". Romania Libera. 9 January 2014. Retrieved 10 January 2014.
  22. http://www.romanialibera.ro/actualitate/eveniment/ponta-autostrada-comarnic-brasov-va-costa-1-8-miliarde-de-euro-323120.html
  23. "Ανακοινωση Σημ Γεγ Comarnic Brasov eng" (PDF). Ellaktor. 20 December 2013. Retrieved 8 January 2014.
  24. "VINCI named preferred bidder for the concession contract covering the Comarnic - Brașov section of the Bucharest - Brașov motorway in Romania". Vinci. 20 December 2013. Retrieved 8 January 2014.
  25. "Construirea Autostrăzii Braşov-Comarnic începe în martie. Anul viitor începe şi construirea Autostrăzii Sibiu-Braşov, iar în 2015 demarează Sibiu-Piteşti". Adevărul. 25 November 2013.
  26. 1 2 http://www.vptv.ro/demareaza-proiectul-comarnic-brasov/
  27. "Archived copy". Archived from the original on 2014-02-23. Retrieved 2014-02-17.
  28. http://www.bzb.ro/stire/dilema-inceperii-lucrarilor-la-autostrada-comarnic-brasov-a75022
  29. http://www.romanialibera.ro/bani-afaceri/economie/cati-kilometri-de-autostrada-s-ar-fi-putut-construi-din-dobanzile-platite-pentru-comarnic-brasov-323199.html
  30. http://www.romania-actualitati.ro/autostrada_comarnic_brasov_la_al_treilea_esec-78047
  31. http://www.bzb.ro/stire/spaniolii-subliciteaza-autostrada-spre-brasov-a91309
  32. http://monitorizari.hotnews.ro/stiri-infrastructura_articole-20503343-care-sunt-constructorii-care-bat-loturile-capat-ale-autostrazii-comarnic-brasov-surpiza-lotul-1.htm
  33. https://www.digi24.ro/stiri/economie/transporturi/incepe-autostrada-comarnic-brasov-cu-10-km-in-campie-803187
  34. "Autostrada Brasov - Cluj - Bors". CNADNR. Archived from the original on 24 December 2013. Retrieved 22 December 2013.
  35. 1 2 "Contractul cu Bechtel pentru autostrada Transilvania a fost reziliat". MondoNews.ro. 30 May 2013.
  36. 1 2 3 4 "Tronsonul autostrazii Sebes-Bors va fi concesionat in totalitate". Wall-Street.ro. 29 October 2013. Retrieved 27 December 2013. Constructia unui tronson de 8,7 kilometri al Autostrazii Transilvania, 3A1 Gilau - Nadaselu (judetul Cluj), singurul pentru care mai sunt contractate lucrari, va incepe in 2014, desi contractul de proiectare si executie a fost semnat in aprilie, motivul amanarii lucrarilor fiind lipsa banilor, potrivit CNADNR.
  37. "Archived copy" (PDF). Archived from the original (PDF) on 2014-07-27. Retrieved 2014-07-16.
  38. "Archived copy" (PDF). Archived from the original (PDF) on 2014-07-27. Retrieved 2014-07-16.
  39. "Archived copy" (PDF). Archived from the original (PDF) on 2014-07-27. Retrieved 2014-07-16.
  40. "Autostrada Bors-Brasov, construita de Bechtel". EVZ.ro. 16 December 2003. Archived from the original on 6 September 2005.
  41. "Autostrada Bechtel, mai scumpa cu 2 miliarde de euro". EVZ.ro. 7 August 2007.
  42. "Infrastructura: Finalizarea autostrazii Transilvania, o enigma si pentru Bechtel". ZF.ro. 14 December 2009.
  43. "Bechtel to continue works on two sectors of motorway in Romania". SeeNews.com. Retrieved 15 August 2011.
  44. "Bechtel built 52 km of Transylvania Motorway for EUR 1.25 billion, but agreed to renegotiate contract". Business Review. 5 August 2011.
  45. "Romania's partnership with Bechtel ends". Nine O`Clock. 4 August 2011.
  46. "Ce aduce 2012 pentru Autostrada Transilvania". Ziua de Cluj. 22 January 2012. Archived from the original on 25 January 2012.
  47. "Panglicile se îndepărtează de autostrăzile în lucru". Capital.ro. 4 June 2012.
  48. "Cea mai mare BĂTAIE DE JOC a banului public!". Capital.ro. 13 August 2012.
  49. "A3, prioritate a guvernului". Transilvania Live. 5 June 2012. Archived from the original on 9 June 2012.
  50. ""Regii asfaltului" au pus ochii pe Autostrada Transailvania". Ziua de Cluj. 22 August 2012.
  51. "După o întârziere de şase luni, Umbrărescu intră pe Autostrada Transilvania" [After a six months delay, Umbrărescu enters on Transylvania Motorway] (in Romanian). Economica.net. 25 April 2013. Retrieved 12 August 2018.
  52. "Comunicat de presă" (PDF). CNADNR. 25 October 2012.
  53. "Primul pret al autostrazii a fost stabilit dupa ureche". EVZ.ro. 26 November 2007.
  54. "CNADNR a reziliat contractul pentru tronsonul Gilău-Nădăşel din autostrada A3". Ziarul Faclia. 29 June 2013.
  55. "Lucrările pe Autostrada Transilvania se mișcă încet, dar sigur". Vocea Transilvaniei. 10 November 2014. Retrieved 7 March 2015.
  56. https://monitorizari.hotnews.ro/stiri-infrastructura_articole-21702164-video-viaductul-lipsa-gilau-care-face-inutilizabil-tronson-autostrada-aproape-terminat-licitatia-pentru-executie-blocata-trei-luni-evaluarea-ofertelor.htm
  57. https://monitorizari.hotnews.ro/stiri-infrastructura_articole-22098961-video-filmare-aeriana-inceput-lucrarile-podul-peste-somes-care-uneasca-autostrada-transilvania-ciotul-gilau-nadaselu-langa-cluj-napoca.htm
  58. "Nouă companii au câştigat licitaţiile pentru Autostrada Câmpia Turzii-Târgu Mureş". Economica.net. 27 January 2015. Retrieved 7 March 2015.
  59. https://monitorizari.hotnews.ro/stiri-infrastructura_articole-20931826-unul-din-loturile-autostrazii-a3-campia-turzii-mures-fost-reziliat-cererea-constructorului-pentru-trecut-12-luni-semnarea-contracutului-nu-dat-ordinul-incepere.htm
  60. https://monitorizari.hotnews.ro/stiri-infrastructura_articole-22113296-lotul-autostrada-a3-targu-mures-ungheni-are-sfarsit-constructor-dupa-sapte-luni-rezilierea-contractului-initial.htm
  61. http://monitorizari.hotnews.ro/stiri-infrastructura_articole-20738359-harta-interactiva-tadiul-lucrarilor-fiecare-autostrada-din-romania-tronsoane-cati-kilometri-putea-deschisi-circulatiei-2016.htm
  62. https://monitorizari.hotnews.ro/stiri-infrastructura_articole-21396459-contractul-pentru-autostrada-a3-bors-suplacu-barcau-aproape-reziliere-directorul-companiei-drumuri-contract-probleme-unde-nu-lucrat-mai-nimic.htm
  63. "Boc a inaugurat Autostrada Transilvania cu un Logan". EVZ.ro. 1 December 2009.
  64. "Emil Boc și Anca Boagiu au inaugurat 12 km din Autostrada Transilvania". EVZ.ro. 13 November 2010.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.