Line 2 (Mumbai Metro)

Line 2 of the Mumbai Metro is an under construction metro line in the city of Mumbai connecting Dahisar in the northwest with Mandale in Mankhurd in the east.

Mumbai Metro Line 2 (Yellow line)
Overview
TypeRapid Transit
SystemMumbai Metro
Status
  • Line 2A (Under construction)[1]
  • Line 2B (Under Construction)
LocaleMumbai Metropolitan Region
TerminiDahisar
Mandale, Mankhurd
Stations39
Daily ridership1.61 million (2021 estimate)[2]
WebsiteLine 2A
Line 2B
Operation
Commenced2016 (2016)
Planned openingDecember 2020 (December 2020)
OwnerMMRDA
CharacterElevated
Depot(s)Charkop (2A)
Mandale (2B)
Technical
Line length42.232 km (26.242 mi)
Number of tracks2
Track gauge1,435 mm (4 ft 8 12 in) standard gauge
Electrification25 Kv AC Overhead catenary

Construction on the first section of the line, called Metro 2A (between Dahisar and D.N. Road), began in November 2016, and is expected to be completed in 2020. This section shall be 18.589 km (11.551 mi) long, and comprise 17 of the 39 stations that form part of this route.

Planning

Public private partnership with RInfra

A 38.24 km long Colaba-Bandra–Charkop line was proposed as Line 2 in the original Mumbai Metro master plan unveiled by the MMRDA in 2004. A 13.37 km long Bandra-Kurla–Mankhurd line and a 7.5 km line from Charkop to Dahisar were proposed as Line 3 and Line 4, respectively, in the same plan.[3] Line 2 was originally planned to run from Colaba to Charkop, with Colaba to Mahalaxmi as underground. However, the underground stretch that was extended in plan up to Bandra (around 20 km) was changed to Charkop-Bandra-Mankhurd (about 35 km), all elevated, primarily due to cost considerations,[4] in the updated Mumbai Metro master plan revised by the MMRDA in 2012.[5] In the updated master plan, the proposed Charkop–Bandra–Mankhurd and Charkop–Dahisar lines were merged into a single Dahisar–Bandra–Mankhurd line, which would have been 32 km and had 27 stations. This was planned to be the second corridor of the Mumbai Metro. Like Line 1, this corridor was also proposed to be constructed on a public private partnership (PPP) model.[6]

Then President Pratibha Patil launched the project in August 2009. The MMRDA appointed Reliance Infrastructure (RInfra), in consortium with SNC Lavolin Inc Canada and Reliance Communication,[7] through an international competitive bidding process to carry out this phase of the project, and the concession agreement was signed with the RInfra-led consortium in January 2010.[8] The project was proposed to be implemented on build–operate–transfer (BOT) basis for a concession period of 35 years with an extension clause of another 10 years.[7] The MMRDA estimated the project would cost 8,250 crore (US$1.2 billion), while Reliance Infrastructure estimated it would cost 11,000 crore.[9] Construction was planned to begin in August 2010 and be completed by mid-2013.[10] However, construction work had yet to begin by December 2012, leading to calls for Line 2 to be cancelled outright.[8]

The line's construction was handicapped by the lack of available land for carsheds at Charkop and Mankhurd; Coastal Regulation Zone (CRZ) laws forbade construction on the land that had been selected by the MMRDA. The Union Ministry of Environment and Forests (MoEF) refused to give clearance for the depots.[11] MMRDA officials plan to solve the problem by shifting the location of the proposed rake depot to Malwani near Malad. The 19 hectares (0.19 km2) plot does not come under the purview of the CRZ laws and therefore will not require environmental clearances.[12] The MMRDA has said that they have not ruled out an underground line, claiming that they had considered a combination of an elevated and underground alignment but had deemed it impossible due to the large land requirement for ramps and slip roads.[13]

On 6 September 2012, the MMRDA sent a letter to Reliance Infrastructure asking them to start work on the metro immediately or face legal action.[14][15] In response to the letter, RInfra blamed the government and MMRDA for the delayed construction work. They said that the government had failed to fulfill its contractual obligation to provide the necessary land, right of way permits and clearances.[16][17][18][19] On 8 February 2013, then RInfra CEO Sumit Banerjee claimed that the project had not advanced because the MMRDA had failed to fulfill its share of the responsibilities.[20][21] The state government had since been considering alternative sites for the depot, which might have led to complete change in the alignment of the line and could have required re-bidding for the project.[22] On 9 August 2013, DNA reported that an MMRDA official had informed them that a 27-acre plot that was to be used as the casting yard for Line 2, was planned to be marked for use as a casting yard for Line 3. The paper called the move "a clear indication" that Line 2 "will not take off in the near future."[23] Chief Minister Prithviraj Chavan told the media on 30 August 2013 that "it is now clear that Mumbai's Metro II project will now not happen."[24]

In January 2014, then MP from Mumbai North Sanjay Nirupam told The Times of India that the existing contract awarded to Reliance Infrastructure would be cancelled and a revised tender would be invited. The decision to do so was taken at a meeting between the city's parliamentarians and Chief Minister Prithviraj Chavan. The terminal of Line 2 was extended from Charkop end to Dahisar, making the new route the Dahisar-Bandra-Mankhurd corridor. According to Nirupam, "It would be easier to shift the depot and casting yard to Dahisar as a land there belongs to the Centre. The present Charkop land has run into environmental hurdles turning the project into a non-starter since 2009 despite contracts being awarded." The Dahisar land belongs to the civil aviation department and can be easily made available for the project as it has not been included in any aviation expansion plans. Reliance had previously informed the State government that lack of environmental clearance to the Charkop depot, absence of permission from the aviation department for the Metro's elevated track in Juhu, huge network of underground and overhead utilities and no higher FSI for station's commercial development made the project financially unviable.[25]

On 13 November 2014, Reliance Infrastructure announced that it had terminated the agreement between the MMTPL and the Maharashtra government. RInfra stated, "Due to non-fulfilment of various critical obligations by Maharashtra government and Mumbai Metropolitan Region Development Authority (MMRDA), the project could not take off. Even after four years, despite the best efforts of the Maharashtra government, various project impediments could not be resolved." The MMRDA issued a statement confirming that the agreement was terminated with mutual consent. No party will bare any cost as a result of the termination and the state government will return a bank guarantee of 160 crore. The MMRDA also clarified that the Line 2 project had not been cancelled and will be constructed by the Mumbai Metro Railway Corp. Ltd (MMRCL) under an engineering, procurement and construction (EPC) model.[26][27]

EPC model

In September 2013, the MMRDA appointed RITES to study the feasibility of constructing the proposed 32-km metro line underground. RITES also studied the feasibility of extending the corridor and merging the 7.5-km Charkop-Dahisar metro, proposed as a separate line, with this project. RITES submitted its final report to the MMRDA in the last week of May 2014, concluding that constructing the metro underground and extending it up to Dahisar was feasible.[28][29][30] The merged Dahisar-Bandra-Mankhurd line would be 40.2 km long and have 37 underground stations. The estimated cost of construction of this line is 28,900 crore, 134% higher than the originally estimated costs of 7,660 crore for the Charkop-Bandra-Mankhurd line and 4,680 crore for the Charkop-Dahisar corridor. RITES proposed the construction of a major car depot at Oshiwara and a minor car depot at Mandalay, Mankhurd on sites that were a mix of publicly and privately held land.[31] The extension of the line to Mankhurd would resolve the land acquisition issues as land was available for the construction of a depot at Mankhurd.[32]

In June 2015, the MMRDA proposed a new line from BKC to Mankhurd.[33] On 15 June 2015, the MMRDA announced that it would implement Line 2 of the metro in three parts - Dahisar East-DN Nagar (Metro 2A), DN Nagar-BKC (Metro 2B), and BKC-Mankhurd (Metro 2C), and also appointed the DMRC to conduct a feasibility study and detailed project report for the line.[34][35] On 1 July 2015, it was announced that MMRDA was allotted a 22-acre plot in Mankhurd adjacent to the Sion Panvel highway for the Metro carshed. The land was under dispute between the MMRDA and the State Home Ministry for the construction of a Jail.[36]

The plan was later modified to build the line in two sections - Dahisar-DN Nagar (Metro 2A) and DN Nagar-Mankhurd (Metro 2B). Metro 2A was approved by the Maharashtra Government on 6 October 2015.[37] In November 2015, the Department of Economic Affairs (DEA) cleared the MMRDA's request to secure a loan from the Asian Development Bank (ADB).[38]

The Maharashtra Cabinet approved the Metro 2B corridor on 27 September 2016. Half of the project cost will be funded by the Centre and the State Government, while the remaining will be financed through loans from the Asian Development Bank and New Development Bank.[39] The Metro 2B corridor will be 23.5 km long and have 22 stations. The project is estimated to cost 10,986 crore,[40][41] including land acquisition cost of Rs 1,274 crore.[32]

Construction

As per the government releases, Metro 2 will be built in two sections - Dahisar-DN Nagar (Metro 2A) and DN Nagar-Mankhurd (Metro 2B). The Maharashtra Government appointed the DMRC as a consultant to execute both sections. The DMRC will have sole responsibility for civil and technical works and O&M on the Metro 2A corridor. For the Metro 2B corridor, the MMRDA will carry out civil works, while the DMRC is tasked with technical work and O&M.[42]

Metro 2A

The corridor will be 18.5 km long and connect Dahisar West to DN Nagar. The corridor will have 16 stations - Dahisar East, Upper Dahisar Station (Anand Nagar), Kandarpada (Rushi Sankul), Mandapeshwar (IC Colony), Eksar, Borivali West (Don Bosco), Pahadi Eksar (Shimpoli, then Shimpawali), Kandivali West (Mahavir Nagar), Dahanukarwadi (Kamraj Nagar), Valnai (Charkop), Malad West, Lower Malad (Kasturi Park), Pahadi Goregaon (Bangur Nagar), Goregaon West, Oshiwara (Adarsh Nagar), Lower Oshiwara (Shastri Nagar) and Andheri West (D.N. Nagar). It will have interchange with Line 1 at DN Nagar and Line 7 at Dahisar. Line 2B will connect DN Nagar to Mankhurd via BKC. Line 2A is estimated to cost around ₹6,410 crore.[32] The DMRC was appointed as the implementing agency for the project. The DMRC floated two tenders for designing and construction of the corridor. The first package includes the design and construction of viaduct and 8 elevated stations - Dahisar East, Upper Dahisar Station (Anand Nagar), Kandarpada (Rushi Sankul), Mandapeshwar (IC Colony), Eksar, Borivali West (Don Bosco), Pahadi Eksar (Shimpoli, then Shimpawali), Kandivali West (Mahavir Nagar), Dahanukarwadi (Kamraj Nagar). The second package includes the remaining viaduct and 8 stations - Valnai (Charkop), Malad West, Lower Malad (Kasturi Park), Pahadi Goregaon (Bangur Nagar), Goregaon West, Oshiwara (Adarsh Nagar), Lower Oshiwara (Shastri Nagar) and Andheri West (D.N. Nagar). JKumar Infra Pvt. Ltd was awarded both packages in June 2016, and carried out civil work, including viaduct and stations. The cost of the packages was estimated as 700 crore each, with JKumar Infra bidding below the reserve price.[43]

Soil testing work along the corridor commenced in July 2016.[44] Construction on the corridor began in November 2016. As of 13 September 2017, 77% of the soil investigation work for pier foundation is completed, 76% of barricading work is completed, 37% piles completed, 19% pile caps completed, 110 piers are cast, 75 pier caps erected, 26 U girders erected and work pile foundation work commenced for all 17 stations.[45] The corridor was scheduled to be commissioned in 2019, but delays in procuring rolling stock will push the deadline to 2020.[46]

In April 2019, the MMRDA issued tenders for the rooftop solar PV power projects at stations on Metro 2A.[47]

Metro 2B

The foundation stone for the Metro 2B was laid by Prime Minister Narendra Modi on 24 December 2016.[48] The MMRDA invited bids for civil work on Metro 2B on 4 January 2017.[49][50][51] Metro 2B was divided into four packages - ESIC Nagar to Khira Nagar, Saraswat Nagar to ILFS, MTNL Metro to Chembur, and Diamond Garden to Mandale.[52] Metro 2B was tendered alongside Metro 4. L&T, Afcons Infrastructure, Tata, NCC and JMC, Reliance Infrastructure-RdE, JKumar Group, ITD Cementation, CHEC-TPL bid for packages on both Metro 2B and Metro 4. Simplex Infrastructures and a consortium of GHEC-RCC-JV-China placed bids only for some packages of Metro 2B. A total of 10 firms and/or consortia submitted bids for the two lines.[53][54]

The MMRDA utilized a drone to carry out survey work for Metro 2B. The drones were fitted with a 360-degree camera that provides up to 3 millimeter accuracy. The aerial survey takes less time than a regular survey, achieves greater accuracy and helps protect against false claims for compensation.[55]

Construction began in April 2018. MMRDA has awarded contract of construction of viaduct and stations for package 1 to simplex. This package includes section between DN nagar to BKC.[56]

Current Status

Metro 2A

Sr. No. Name of Work Description Status as of [57]
24 October 2017 9 January 2018 28 February 2018 10 April 2018 10 July 2018 21 May 2019 24 May 2019 25 May 2019 26 December 2019
1 Soil Investigation Works Soil investigation work for pier foundation completed 84% 94% 95% 98% 99%
2 Barricading Works Barricading work completed 76% 89%
Utility Works Work completed 82% 87% 94% 98% 99%
3 Piling Works Out of 4668 4576
piling work for foundations completed 47% (2190) 61% (2797) 67% (3069) 72% (3277) 78% (3533) 92% 93% 97% 98%
4 Pile Cap Works Out of 980 945
Pile Cap work completed 23% (253) 43% (406) 53% (497) 56% (530) 65% (593) 85% 87% 92% 94%
5 Pier Works Out of 957 908
Piers Cast 181 300 420 476 526 82% 83% 90% 92%
6 Pier Cap Works Out of 827 799
Pier Caps Cast 138 236 309 374 426 88% 91% 94%
Pier Caps Erected 111 199 256 326 376 83% 86% 91%
7 U Girder Works Out of 1430 1435
U-girders cast 190 343 415 495 661 77% 81% 91% 94%
U-girders erected 62 146 265 352 510 69% 73% 88%
8 Station Work Work is in progress at all the 17 stations Dahisar East, Upper Dahisar Station (Anand Nagar), Kandarpada (Rushi Sankul), Mandapeshwar (IC Colony), Eksar, Borivali West (Don Bosco), Pahadi Eksar (Shimpoli, then Shimpawali), Kandivali West (Mahavir Nagar), Dahanukarwadi (Kamraj Nagar), Valnai (Charkop), Malad West, Lower Malad (Kasturi Park), Pahadi Goregaon (Bangur Nagar), Goregaon West, Oshiwara (Adarsh Nagar), Lower Oshiwara (Shastri Nagar) and Andheri West (D.N. Nagar)
64%

Metro 2B

Sr. No. Name of Work Description Status as of [58]
21 May 2019 22 November 2019
1 Soil Investigation Works Soil investigation work for pier foundation completed 55% 59.08%
2 Barricading Works Barricading work completed
Utility Works Work completed 23% 28.86%
3 Piling Works piling work for foundations completed 7% 8.84%
4 Pile Cap Works Pile Cap work completed 3% 4.08%
5 Pier Works Piers Cast 1.2% 1.45%
6 Pier Cap Works Casting beds are under preparation. Casting beds are under preparation.
7 U Girder Works Casting yard works are in progress 0.7% 0.8%
8 Station Work Work is in progress at all the 22 stations Yet to start Soil Investigation and Utility Identification work is in progress. Foundation work yet to start

Stations

There will be a total of 39 stations on the Dahisar - Mandala route. Metro 2A, from Dahisar to DN Nagar, will have 17 stations, and Metro 2B, from DN Nagar to Mankhurd, will have 22 stations.

# Station[59][60] Status Connections
1 Dahisar (East) Under Construction Line 7
2 Upper Dahisar Under Construction None
3 Kandarpada Under Construction None
4 Mandapeshwar Under Construction None
5 Eksar Under Construction None
6 Borivali (West) Under Construction None
7 Pahadi Eksar Under Construction None
8 Kandivali (West) Under Construction None
9 Dahanukarwadi Under Construction None
10 Valnai Under Construction None
11 Malad (West) Under Construction None
12 Lower Malad Under Construction None
13 Pahadi Goregaon Under Construction None
14 Goregaon (West) Under Construction None
15 Oshiwara Under Construction Line 6
16 Lower Oshiwara Under Construction None
17 D N Nagar Under Construction Line 1
18 ESIC Nagar Under Construction None
19 Prem Nagar Under Construction None
20 Indira Nagar Under Construction None
21 Nanavati Hospital Under Construction None
22 Khira Nagar Under Construction None
23 Saraswat Nagar Under Construction None
24 National College Under Construction None
25 Bandra Metro Under Construction None
26 MMRDA Under Construction None
27 ITO, BKC Under Construction[61] Line 3
28 IL&FS, BKC Under Construction[61] None
29 MTNL, BKC Under Construction None
30 S G Barve Marg Under Construction None
31 Kurla Terminus Under Construction Lokmanya Tilak Terminus
32 Kurla (East) Under Construction None
33 Eastern Express Highway
(near Amar Mahal Jn.)
Under Construction Line 4
34 Chembur Under Construction Monorail
35 Diamond Garden Under Construction None
36 Shivaji Chowk Under Construction None
37 BSNL Under Construction None
38 Mankhurd Under Construction None
39 Mandala Under Construction None

Construction & System Contracts

Sr No.ContractContractor
1Detail Design ConsultancyAECOM
2Rolling stockBEML
3Anand Nagar-Kamraj Nagar

(8.1 km Viaduct & 8 Stations)

J Kumar-CRTG JV
4Charkop-DN Nagar

(9.8 km Viaduct & 8 Stations)

J Kumar-CRTG JV
5ESIC Nagar-ILFS

(12.7 km Viaduct & 11 Stations)

Simplex Infrastructure
6MTNL Metro-Chembur

(5.9 km Viaduct & 6 Stations)

RCC-MBZ JV
7Diamond Garden -Mandala

(5.0 km Viaduct & 6 Stations)

Nagarjuna Construction Company Ltd.-

Cost

Metro 2A is estimated to cost 5,566 crore (US$780 million). The State Government will bear 48% of the total project cost. The MMRDA secured a loan worth 52% of the total project cost from the Asian Development Bank (ADB).[38] Metro 2B is estimated to cost 10,986 crore,[40][41] including land acquisition cost of Rs 1,274 crore.[32] Half of the project cost will be funded by the Centre and the State Government, while the remaining will be financed through loans from the Asian Development Bank and the World Bank.

The MMRDA allotted 340 crore (US$48 million) to the DMRC to implement and commission rolling stock, signalling and telecommunication work for the Metro 2A and Metro 7 corridors on 26 November 2016.[62][63][64]

On 2 March 2019, the Union Ministry of Finance stated that it signed a $926 million loan agreement with the ADB to fund construction of Metro 2 and 7. This was the single largest infrastructure loan ever extended by the ADB. The funds will be used to procure 63 six-car trainsets and for signalling and safety systems on both corridors.[65]

References

  1. http://www.thehindu.com/todays-paper/tp-national/tp-mumbai/mmrc-gears-up-to-start-work-on-metro3/article8878600.ece
  2. "Mumbai Metro Line 2 (Dahisar-Charkop-Bandra-Mankhurd Metro Project)". MMRDA. 21 March 2014. Archived from the original on 14 April 2014. Retrieved 27 March 2014.
  3. "Mmrda – Projects – Mumbai Metro Rail Project". Mmrdamumbai.org. Archived from the original on 16 June 2014. Retrieved 12 March 2014.
  4. "Road infrastructure must be planned with priority for pedestrians, non-motorised vehicle traffic - Moneylife". Moneylife.in. Retrieved 28 September 2013.
  5. Bureau, Our (26 August 2014). "Third phase of metro rail inaugurated".
  6. "MMRDA in talks for foreign funding". The Indian Express.
  7. "Reliance Infra wins Rs 11,000-cr Mumbai Metro-II project - Economic Times". The Times of India. Retrieved 3 April 2014.
  8. "Another R-Infra project heads for termination". Business Standard. 18 December 2012. Retrieved 21 December 2012.
  9. "Reliance Infra's Mumbai metro phase II faces cancellation". Business Standard. 17 December 2012. Retrieved 21 December 2012.
  10. Jadhav, Ranjeet (9 January 2012). "MMTPL to CM: Metro II will take more time, money". Mumbai: Mid Day. Retrieved 13 March 2012.
  11. Siddhaye, Ninad (5 December 2009). "CRZ rules may stop Metro II in its tracks". Mumbai: DNA. Retrieved 13 March 2012.
  12. "MMRDA finds land for Metro II rake depot in Malwani". Mumbai Mirror. 22 September 2012. Retrieved 26 September 2012.
  13. "Metro-II may still run underground in Mumbai". Daily News and Analysis. 15 March 2012. Retrieved 28 March 2012.
  14. "Metro II delay: Mumbai Metropolitan Region Development Authority warns of action". The Times of India. 15 September 2012. Retrieved 26 September 2012.
  15. "MMRDA warns RInfra over delay in second Metro line". Hindustan Times. 15 September 2012. Retrieved 26 September 2012.
  16. "Metro’s second line project may get derailed". The Times of India. 17 September 2012. Retrieved 26 September 2012.
  17. "Mumbai Metropolitan Region Development Authority, Reliance Infrastructure on clash course over second Metro rail". The Times of India. 4 October 2012.
  18. "‘No work unless state follows contract’". The Indian Express. 4 October 2012.
  19. "Developer sticks to his guns, won’t start work on Metro-II". Hindustan Times. 4 October 2012. Retrieved 7 July 2013.
  20. "Rs 65cr spent on Metro II, work still to take off". The Times of India. 9 February 2013. Retrieved 12 February 2013.
  21. "Metro 2 stuck in RInfra-MMRDA blame game". DNA India. 9 February 2013. Retrieved 12 February 2013.
  22. "Mumbai Metro Corp calls for consultants for third line". Business Standard. 19 June 2013. Retrieved 7 July 2013.
  23. "Mumbai's second Metro line on the verge of derailment - Mumbai - DNA". Daily News and Analysis. Retrieved 28 September 2013.
  24. Rohit Chandavarkar (31 August 2013). "Mumbai's Metro II project cancelled; Metro I and other Infra projects in deep trouble - Economic Times". The Economic Times. Retrieved 28 September 2013.
  25. "Tenders for Metro-II to be reinvited soon". The Times of India. Retrieved 25 January 2014.
  26. Sanjai, P.R. (13 November 2014). "Reliance Infra pulls out of Mumbai Metro Line 2". Livemint. Retrieved 14 October 2016.
  27. India, Press Trust of (4 February 2014). "Further delay in Colaba-Seepz metro as govt tweaks bid norms". Business Standard India. Retrieved 14 October 2016.
  28. "Underground Metro technically feasible: Study". The Indian Express. Retrieved 3 April 2014.
  29. "Metro-II gets nod for underground line".
  30. "MMRDA in talks for foreign funding". 20 May 2014.
  31. "Dahisar-Bandra-Mankhurd corridor set to be costliest Metro project". 5 June 2014.
  32. "Construction of two metro lines to begin mid-monsoon". Hindustan Times. 23 July 2016. Retrieved 14 October 2016.
  33. "Over 130 km of Metro lines to criss-cross city by 2020". 16 June 2015.
  34. "Metro 2 to be built in three phases, 2 other routes also on cards". 16 June 2015.
  35. "Centre paves way for Rs 8,000-cr loan for 2 metro lines". Hindustan Times. 26 November 2015. Retrieved 14 October 2016.
  36. Naik, Yogesh (1 July 2015). "MMRDA gets 22-acre plot in Mankhurd for Metro II yard". Mumbai Mirror. Mumbai. Retrieved 1 July 2015.
  37. "Maharashtra govt approves 2 new Metro lines for Mumbai, cost revised to Rs 12,618 crore". The Indian Express. 7 October 2015. Retrieved 12 February 2017.
  38. "Centre paves way for Rs 8,000-cr loan for 2 metro lines". Hindustan Times. 26 November 2015. Retrieved 12 February 2017.
  39. "Mumbai Metro Yellow Line - Info, Route Maps, Fares, Tenders & Updates". The Metro Rail Guy. Retrieved 11 May 2020.
  40. "Maharashtra Cabinet Gives Go-Ahead For Two Metro Lines". NDTV.com. Retrieved 14 October 2016.
  41. "Mumbai to get two more Metro Rails". Business Standard India. 27 September 2016. Retrieved 14 October 2016.
  42. "Mumbai Metro to get by with help from Delhi". Hindustan Times. 10 May 2016. Retrieved 14 October 2016.
  43. "Tainted J Kumar Infraporjects bags Dahisar-DN Nagar Metro 2A project". dna. 9 August 2016. Retrieved 14 October 2016.
  44. "Soil testing starts for metro projects". Asian Age/. 2 July 2016. Retrieved 12 February 2017.
  45. "Piling Work Begins for Mumbai Metro's Line-2". The Metro Rail Guy. Retrieved 12 February 2017.
  46. "Nearly 50% of pillars ready, Metro 2A to start in 2020 - Times of India". The Times of India. Retrieved 20 May 2018.
  47. "MMRDA Issues 7.63 MW Rooftop Solar Tender For Mumbai Metro Project". saurenergy.com. Retrieved 4 May 2019.
  48. "MMRDA invites civil work bids for two Metro projects". The Times of India. Retrieved 10 February 2017.
  49. "MMRDA invites bids for 2 metro projects". dna. 5 January 2017. Retrieved 10 February 2017.
  50. "MMRDA invites tenders for design, construction of stations, viaducts for new Metro routes". The Indian Express. 5 January 2017. Retrieved 10 February 2017.
  51. "Racing against 2021 deadline, Maharashtra opens bids for two more Metro lines". Hindustan Times. 5 January 2017. Retrieved 10 February 2017.
  52. "Mumbai commute to get faster, firms queue up to build two more Metro lines". Hindustan Times. 13 May 2017. Retrieved 13 May 2017.
  53. "MMRDA receives interest from domestic, foreign firms for metro". India Today. Retrieved 13 May 2017.
  54. "R Infra, 10 others bid for Metro-2B, Metro-4 corridors". Asian Age. 13 May 2017. Retrieved 13 May 2017.
  55. "MMRDA plans drone survey for other Metro lines". The Indian Express. 7 March 2017. Retrieved 7 March 2017.
  56. "MMRDA wants night noise rules relaxed to build Metro on time". Hindustan Times. 13 February 2017. Retrieved 15 February 2017.
  57. "Mumbai Metropolitan Region Development Authority - Metro Line - 2". mmrda.maharashtra.gov.in. Retrieved 24 December 2017.
  58. "Mumbai Metropolitan Region Development Authority - Metro Line - 2". mmrda.maharashtra.gov.in. Retrieved 21 May 2019.
  59. "Line 2A-Project Features-Stations". MMRDA. Retrieved 7 June 2017.
  60. "Line 2B-Project Features-Stations". MMRDA. Retrieved 7 June 2017.
  61. "RCC-MBZ & Neeraj-Guan Lowest Bidders for Mumbai Metro's Line-2B - The Metro Rail Guy". themetrorailguy.com. Retrieved 20 February 2018.
  62. "Consultant for MTHL finalized". The Times of India. Retrieved 26 November 2016.
  63. "Mumbai Trans-Harbour Link: MMRDA approves appointment of general consultants". The Indian Express. 26 November 2016. Retrieved 26 November 2016.
  64. "General consultant appointed for MTHL project". dna. 25 November 2016. Retrieved 26 November 2016.
  65. "Asian Development Bank To Lend $926 Million For Mumbai Metro Rail Project". NDTV.com. Retrieved 14 March 2019.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.