Arklow Bank Wind Park

Arklow Bank Wind Park is a 25 megawatt offshore wind farm generating electrical power for the Wicklow region in Ireland. It is the first offshore wind farm in Ireland, and the world's first erection of wind turbines rated over 3 MW. It is located on the Arklow Bank, a shallow water sandbank in the Irish Sea, around 10 kilometers (6.2 mi) off the coast of Arklow with an area of 27 by 2.5 kilometres (16.8 by 1.6 mi).[1]

Arklow Bank Wind Park
GE turbines on dock during Arklow Bank construction 2003
CountryIreland
LocationArklow Bank, Irish Sea
Coordinates52.789°N 5.949°W / 52.789; -5.949
StatusOperational
Commission date2004
Owner(s)GE Renewable Energy
Operator(s)GE Renewable Energy
Wind farm
TypeOffshore
Distance from shore10 km (6.2 mi)
Hub height73.5 m (241 ft)
Rotor diameter124 m (407 ft)
Power generation
Units operational7
Make and modelGE Wind Energy: GE 3.6xl
Nameplate capacity25 MW

The project is being co-developed by Airtricity and GE Wind Energy. In 2002, Airtricity obtained an offshore lease for a 520 MW offshore wind farm. The first phase of the project, commissioned in June 2004, consists of seven GE 3.6-megawatt generators. They were installed by the Danish offshore wind farms services provider A2SEA.[2] Power cables were laid by Five Oceans Services (now SIEM Offshore Contractors),[3] and construction of the turbines themselves was based out of Rosslare port. All of the turbines have a height of 73.5 metres (241 ft) and height to top of blade of 124 metres (407 ft). The blade length is 50.5 metres (166 ft) and each turbine has three blades. Each turbine weights 290 tonnes. They use steel monopole foundations driven in by a hydraulic hammer and each turbine has a landing platform for boat access. They are spaced 600 metres (2,000 ft) apart.[4] Generated electricity is fed to ESB Networks distribution grid through the Arklow National Grid Substation.[1]

Phase 2 of the Arklow Project was to be developed in partnership with Acciona Energy of Spain. The development was to consist of a further 193 turbines. However, Phase 2 and the planned connection to Eirgrid transmission system was cancelled in 2007.[5] In January 2018, SSE Ireland confirmed to the Oireachtas Joint Committee On Communications, Climate Action And Environment their continuing commitment and planned investment of over €1B in the project to help meet Ireland's 2020 renewable energy targets. [6] [7] A geotechnical survey was completed in September 2018. [8]

The project is proposed to a larger scheme which includes a further installation at Codling Bank, near Bray Head and would see a total of 1620MW generation capacity, almost twice the offshore turbine capacity in operation worldwide as of 2006. The development has elicited local concern that some 420 turbines would also be visible from coastal Wicklow and Wexford, while applications have been submitted for further wind banks in excess of 1000MW capacity.[9] Local consultation about offshore power generation is minimal,[10] but the local tourism association lists the wind farm as part of the Arklow South Beach.[11] Technological advances since permission was originally sought mean that approximately half the original number of turbines are planned to be deployed in Arklow Bank phase 2, while still achieving the additional power generation capacity of 500MW. [12]

The Arklow Bank Wind Farm capacity remains 25MW as of October 2018.[13]

See also

References

  1. Ireland's Offshore Wind Power Archived June 15, 2012, at the Wayback Machine, University of Delaware
  2. "A2SEA references" (PDF). A2SEA. A2SEA. 2011-06-20. Retrieved 2011-06-20.
  3. "Arklow Bank Offshore Wind Farm". Five Oceans Services/SIEM Offshore Contractors. Archived from the original on 2014-03-12. Retrieved 2014-03-12.
  4. "Datasheet for Arklow Bank". LORC Knowledge. 2011-03-14. Retrieved 2011-06-20.
  5. "Archived copy" (PDF). Archived from the original (PDF) on 2011-09-28. Retrieved 2011-08-17.CS1 maint: archived copy as title (link)
  6. "SSE tells Oireachtas that offshore wind can power the future". SSE. 2018-01-23. Retrieved 2018-10-18.
  7. McLoughlin, Gavin (2018-09-15). "Energy giant to invest €2bn in offshore wind farm". Irish Independent. Retrieved 2018-10-18.
  8. "Arklow Bank Phase 2 Offshore Wind Farm". 4C Offshore. 2018-09-30. Retrieved 2018-10-18.
  9. Background Note: Wicklow Offshore Wind Farms – Inadequate Permitting Process Archived 2014-10-06 at the Wayback Machine, Coastal Concern Alliance
  10. Pylon concerns raised with Labour, Wicklow News
  11. Arklow South Beach & Wind Farm visitarklow.ie
  12. "Arklow Wind Bank". SSE. Archived from the original on 2018-10-18. Retrieved 2018-10-18.
  13. Archived 2018-10-18 at the Wayback Machine Arklow & District Chamber
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.