Tarnița – Lăpuștești Hydroelectric Power Station

Tarnița - Lăpuștești Hydropower Plant is a proposed hydroelectric pumped-storage project on the Someșul Cald River in Cluj County, Romania. If built it would be the largest hydro-electric load balancing system in Romania. During the night, when the demand is low and electricity is cheap because of powerplants which generate electricity continuously, such as the Cernavodă nuclear power plant, it will use electricity to pump water up the hill, while during the day, it will use the hydro energy to generate electricity.

Tarnița – Lăpuștești Hydroelectric Power Station
Location of Tarnița – Lăpuștești Hydroelectric Power Station in Romania
CountryRomania
LocationLăpuștești, Râșca, Cluj County
Coordinates46°42′50″N 23°16′07″E
StatusUnder construction
Construction began15 June 2008[1]
Construction costEstimated €1.3 billion[2][3][4] (US$1.5 billion)
Dam and spillways
ImpoundsSomeșul Cald River
Website

Location

The Tarnița - Lăpuștești power station will be located 35 km from Cluj Napoca,[5] on the left bank of the Someşul Cald River valley in the area of the existing Tarniţa accumulation and the Lăpuşteşti village (Râşca commune).

Power generation

The power station will have four turbines, each capable of producing 250 megawatts, for a total of 1000 megawatts.[6]

Schedule

Construction has not started. The Romanian state is looking for investors. The strategic environmental assessment (SEA) procedure is at the beginning, the environmental impact assessment (EIA) procedure did not start yet, as the project consultants admitted publicly on the 17.11.2010. In 2016 the Romanian government stated that several smaller projects were being considered instead.[7]