Redhill MRT station

Redhill MRT station (EW18) is an above-ground Mass Rapid Transit (MRT) station on the East West Line located in Bukit Merah, Singapore. This is the last above-ground station eastbound until Kallang MRT station.

 EW18 
Redhill
红山
ரெட்ஹில்
Redhill
Rapid transit
View of Redhill MRT station, seen from above
Location920 Tiong Bahru Road
Singapore 158792
Coordinates1°17′23.04″N 103°49′0.30″E
Operated bySMRT Trains (SMRT Corporation)
Line(s)
Platforms2 (1 island platform)
Tracks2
ConnectionsBus, Taxi
Construction
Structure typeElevated
Platform levels1
ParkingYes (external)
Bicycle facilitiesYes
Disabled accessYes
Other information
Station code EW18 
History
Opened12 March 1988 (1988-03-12)
ElectrifiedYes
Previous namesAlexandra
Services
Preceding station   Mass Rapid Transit   Following station
towards Pasir Ris
East West line
towards Joo Koon or Tuas Link
Location

Redhill is the only MRT station in which the two platforms are not parallel.

History


The MRTC has awarded the Contract 202 for the construction of Redhill and Queenstown MRT stations on 7 February 1985 for $50 million, together with the viaduct from Tiong Bahru Road to Queensway, construction starts on March 1985 for the completion in December 1987.[1]

Redhill station opened on 12 March 1988, which is part of the Phase 1B of the MRT line. It travels from Outram Park to Clementi.[2]

On 31 August 2004, a lady in her 40s was hit by a train after she fell on to the tracks. She suffered head injuries and was sent to the Singapore General Hospital. This incident took place just hours after another train hit another lady in her 50s earlier in the day at Bukit Batok MRT station.

On 18 May 2010, eastbound train services between Queenstown and Outram Park MRT stations were disrupted for about 45 minutes when a passenger was hit by a train at 11.35 am. To maintain eastbound service at the unaffected sections, some westbound trains were turned around at Outram Park MRT station. Close to 5,500 passengers were affected by the incident and train services resumed at about 12.20pm.

In view of accidents along the MRT line, platform screen doors were installed and started operations on 31 May 2011.[3]

References

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.