Dasu Dam

The Dasu Dam is a large hydroelectric gravity dam currently under construction on the Indus River near Dasu in Kohistan District, Khyber Pakhtunkhwa Province, Pakistan. It is developed by Pakistan Water and Power Development Authority (Wapda), as a key component of the company's Water Vision 2025.

Dasu Dam
Location of Dasu Dam in Pakistan
CountryPakistan
LocationDasu, Kohistan District, Khyber Pakhtunkhwa Province
Coordinates35°19′02.16″N 73°11′35.78″E
PurposePower, water supply
StatusUnder construction
Construction beganJune 2017
Opening date2025 (est.)
Construction cost$4.278 billion (stage I)
Owner(s)Government of Pakistan
Operator(s)Water and Power Development Authority (WAPDA)
Dam and spillways
Type of damGravity, roller-compacted concrete
ImpoundsIndus River
Height242 m (794 ft)
Length570 m (1,870 ft)
Reservoir
Total capacity1,410,000,000 m3 (1,140,000 acre⋅ft)
Dasu Hydropower Plant
Coordinates35°17′47.03″N 73°12′44.59″E
Commission dateEarly 2025 (stage I)
Hydraulic head171.59 m (563.0 ft)
TurbinesStage I: 6 x 360 MW Francis-type
Stage II: 6 x 360 MW Francis-type
Installed capacity4,320 MW
Annual generation21 TWh

The 242 m (794 ft) tall dam will support a 4,320 MW hydropower station, the largest in Pakistan, to be built in two 2,160 MW stages. The plant is expected to start generating power in late 2024, and stage I is planned to complete by early 2025.[1]

Water from the reservoir will be diverted to the power station located about 3.5 km (2.2 mi) downstream.[2]

Timeline

Dasu dam proposal was approved in 2001, as part of Government of Pakistan’s Vision 2025 program. Feasibility study was completed in 2009.[3]

The first stage was approved by the Executive Committee of the National Economic Council on 29 March 2014. It will cost an estimated $4.278 billion.[4] Prime Minister Nawaz Sharif attended the dam's groundbreaking ceremony on 25 June 2014.[5]

Contracts for preparatory works of the project were awarded in the first half of 2015, and early construction works actually started in June 2017.[3]

The main civil works, undertaken by China Gezhouba Group Company Limited, started in February 2018. Work on the water diversion tunnel was inaugurated December 2018.[6]

In November 2019, Wapda signed a first Rs52.5 billion contract with a chinese joint-venture, regarding electro-mechanical works. This contract includes design, supply and installation of the first stage's six 600 MW turbines, along with their generators, and transformers.[7]

As of March 2020, aside from the main civil works on diversion tunnels and powerhouse access, construction of the right bank access road, the relocation of Karakoram Highway, and the 132 kV transmission line was also under way.[1]

Funding

The project cost was revised from an initial Rs486.093 billion to Rs510.980 billion, mainly because of escalation of land cost.[8]

Funding is being provided by the World Bank ($700 million), the Industrial and Commercial Bank of China ($1.5 billion), Deutsche Bank ($1 billion) and Aga Khan Development Network ($500 Million).

On 1st April 2020, World Bank approved an additional $700 million in financing, with the funds to be used for the transmission line that will complete the first 2,160 MW phase of the project on the Indus River.[9]

Resettlement and Shatial Museum

In December 2015, Pakistan Water and Power Development Authority (Wapda) signed a contract worth Rs571.95 million with China Railway First Group for construction at resettlement sites and building the Shatial museum – two schemes that are part of the Dasu hydroelectric power project.

The contract includes construction at three sites for the resettlement of displaced people belonging to Choochang village and developing an open-air museum at the archeological site of Shatial to conserve pre-historic rock carvings. Work on these schemes is expected to be completed in one and a half years.

References

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.