Araneta City Cyberpark

The Araneta City Cyberpark is a 8 hectares (20 acres) office development [1] located in The Araneta City in Cubao, Quezon City. Under a new master plan, the development consists of green offices, retail and commercial spaces, and an outdoor park, with 2 towers completed, and one tower under construction, with 179,863 m2 (1,936,029.22 sq ft) of office space completed as of February 2020.

Araneta City Cyberpark
General information
StatusUnder Development
TypeOffice
LocationGen.Aguinaldo Ave. cor Gen. Mc Arthur Ave., Araneta City, Quezon City, Metro Manila, Philippines
Construction started2007 (Telus,APAC,EGS House)
2014 (Cyberpark Tower 1)
2016 (Cyberpark Tower 2)
Completed2008 (Telus,APAC,EGS House)
2016 (Cyberpark Tower 1)
2018 (Cyberpark Tower 2)
Opening2016 (Cyberpark Tower 1)
2018 (Cyberpark Tower 2)
Cost₱20 billion
OwnerACI Inc.
ManagementACI Inc.
Height
Roof122 m (400 ft) (Cyberpark Tower 1 including helipad)
125 m (410 ft) (Cyberpark Tower 2 including helipad)
Technical details
Floor count30 (Cyberpark Tower 1)
31 (Cyberpark Tower 2 & Tower 3)
3 Underground
Floor area550,000 m2 (5,920,150.73 sq ft) (upon completion)
Lifts/elevators10
Design and construction
ArchitectASYA Design
DeveloperACI Inc.
Main contractorMegawide Construction Corporation
Website
www.aranetacenter.net/cyberpark/index.php
www.aranetagroup.com/cyberpark/cyberpark-masterplan.php

The ACI Inc. is the owner and developer of the project and part of Araneta City Master Plan.[2]

History

The Araneta City Cyberpark is part of the Araneta City master plan unveiled in 2000, situated along Gen. Aguinaldo and Gen. Mc Arthur Avenues, primarily for BPO/IT office development. The first phase of the Cyberpark, which was completed on 2008, is composed of 7 low-rise buildings, housed by Telus, APAC, AGS, Agentworx, and Expert Global Solutions.[3]

As demand for office spaces grew and expanded over the years, a newer and updated master plan was finalised, consisting of 5 PEZA certified and LEED-approved towers, with 2 levels of retail (initially 5), surrounding an outdoor park,[4] and connected to malls such as SM Cubao, Ali Mall, the Gateway Mall 3, the Gateway Mall 2, and major transport hubs such as the LRT 2, the MRT 3 and transport terminals, attracting Business process outsourcing and corporate services companies.

Facilities

Telus House

The Telus House is one of the first low-rise, 4-storey buildings in the original Cyberpark plan completed in 2008, and currently houses Telus. The building has 15,000 m2 (161,458.66 sq ft) of total office space.

The building will soon be demolished in order to give way for the construction of the Gateway Mall 3, a 100,000 m2 (1,100,000 sq ft) expansion project of the Gateway Mall, and Cyberpark Tower 4. The future development will also feature additional retail and commercial spaces and a green, outdoor park.

Cyberpark Tower 1

Cyberpark Tower 1 on General Aguinaldo Avenue

The first tower in the project,[5] [6] and standing 30 storeys high, construction started on 2014, which is completed in 2016. The Cyberpark Tower 1 has 86,689 m2 (933,112.63 sq ft) of office space [7], with 3 basement parking levels, 2 levels of retail, and houses companies Like 24-7 Intouch, Stellar, Sterling, Genesys, Accenture, and The Vibal Group, as well as The Medical City Clinic Cubao Branch. The Tower will is also connected to nearby SM Cubao via Elevated Bridge.

The tower features double glazed windows for energy efficiency, a rainwater collection system, and is also equipped with Solar panels located at the roof deck of the building. [8] The tower will soon to be directly connected to the Gateway Mall 3 along with Cyberpark Tower 4.

Cyberpark Tower 2

The second tower of the project, [9] [10] standing 31 storeys high on the former Jeepney Terminal, The Cyberpark Tower 2 has 93,174 m2 (1,002,916.59 sq ft) of office space, featuring double-glazed energy-efficient windows, smart elevators, vertical trellises, balconies with planters, and a rainwater recovery system,[2] construction started on 2016, and was finished in 2018.[9] [11] The Tower houses companies like Alorica, occupying the first 7 floors of the Tower, with plans to occupy more floors, as well as Pizza hut, and Dairy Queen (with the main office still located at the Aurora Tower), and Ibex. [12] [13]

Cyberpark Tower 3

The third tower of the project, Cyberpark Tower 3 is now under construction, soon to rise on the former Alorica Building now demolished. The tower will be similarly designed to Cyberpark Tower 2, standing 31 storeys high, having 93,174 m2 (1,002,916.59 sq ft) of office spaces, and features double-glazed energy-efficient windows, smart elevators, vertical trellises, balconies with planters, and a rainwater recovery system. Groundbreaking started in the 2nd quarter of 2019 and is slated to be completed on 2021. [14] [15] [16] [17] [18] [19]

Cyberpark Tower 4

The fourth tower of the project, Cyberpark Tower 4 is a planned 30-storey office building planned to be built on the Telus House, and it is planned to be directly connected to the Gateway Mall 3.[19]

Cyberpark Tower 5

The final office building planned in the Cyberpark, the Cyberpark Tower 5 is a planned 40-storey office building planned to be built on the Jeepney Terminal located along Cyberpark Tower 2.[19]

References

  1. https://businessmirror.com.ph/araneta-center-cyberpark-the-newest-premier-business-district-in-the-metro/
  2. http://www.aranetagroup.com. "The Araneta Group". www.aranetagroup.com. Retrieved 2018-02-19.
  3. "- Manhattan Garden City". yourpropertyconsultant.weebly.com/. Retrieved 28 February 2018.
  4. "Overview". aranetacenter.net/cyberpark/index.php. Retrieved 28 February 2018.
  5. "Cyberpark Tower 1". megawide.com.ph/. Retrieved 28 February 2018.
  6. https://www.aranetacenter.net/btowers/home/13
  7. https://www.aranetacenter.net/btowers/home/13
  8. https://www.aranetacenter.net/news/article/142
  9. "Araneta breaks ground on CyberPark Tower 2 for BPO locators". bworldonline.com/. Retrieved 28 February 2018.
  10. https://www.aranetacenter.net/btowers/home/14
  11. https://businessmirror.com.ph/araneta-group-tops-off-2nd-office-tower-in-cyberpark/
  12. https://www.bilyonaryo.com.ph/2019/06/07/bpo-giant-ibex-doubles-ph-network-to-6-offices-adds-3000-jobs/
  13. https://business.mb.com.ph/2019/02/23/araneta-center-poised-to-become-ncrs-next-big-business-district/
  14. https://www.manilatimes.net/araneta-center-targets-3rd-tower-development/388552/
  15. https://www.philstar.com/business/2018/03/26/1800251/araneta-group-rethinks-planned-office-building-amid-business-process-outsourcing-slowdown
  16. https://www.aranetacenter.net/news/article/111
  17. https://www.aranetacenter.net/news/article/142
  18. https://www.gmanetwork.com/news/money/companies/702267/araneta-group-unveils-p20-b-masterplan-for-cyberpark-complex-in-cubao/story/
  19. "The Araneta Center Cyberpark pushes for green initiatives". BusinessMirror. 6 August 2019. Retrieved 5 October 2019.

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.