Rayalaseema Thermal Power Station
Rayalaseema Thermal Power Station | |
---|---|
| |
Country | India |
Location | Kadapa, Kadapa, Andhra Pradesh |
Coordinates | 14°42′N 78°28′E / 14.70°N 78.46°ECoordinates: 14°42′N 78°28′E / 14.70°N 78.46°E |
Status | Operational |
Commission date |
Unit 1: March 31, 1994 Unit 2: February 25, 1995 Unit 3: January 25, 2007 Unit 4: November 20, 2007 Unit 5: March 14 , 2018 |
Operator(s) | APGENCO |
Thermal power station | |
Primary fuel | Coal |
Power generation | |
Units operational | 5 X 210 MW and 1 × 600 MW |
Nameplate capacity | 1650 MW |
Rayalaseema Thermal Power Station is located at Kadapa in Andhra Pradesh. The power plant is one of the coal based power plants of APGENCO.[1]
Capacity
The Thermal Power Station has a capacity of 1650 MW; 5 units of 210 MW each and 1 units of 600 MW.
Phase | Installed Capacity (MW) | Date of Commissioning | Status |
---|---|---|---|
I | 2X210 | 1994 | Commissioned |
II | 2X210 | 2007 | Commissioned |
III | 1X210 | 2010 | Commissioned |
IV | 1X600 | 2018 | Commissioned |
Power Plant
Rayalaseema Thermal Power Plant was developed under 3 stages namely stage I,II and III. The station is performing well in the recent years by achieving high plant load factor. It stood first in country during 98-99, 2002–03, 2003–04 and second during 99-2000, 2001-02.[2] The station has received Meritorious productivity awards for six consecutive years and Incentive award for seven consecutive years.[3]. BHEL commissioned stage IV unit 1x600MW in March 2018 leading to total installed capacity of RTPP to 1650MW.[4]
References
- ↑ http://www2.adb.org/Documents/PPARs/IND/22344-IND-PPAR.pdf
- ↑ "Rayalaseema Thermal Power Plant". Andhra Pradesh Power Generation Corporation Ltd. Retrieved 19 August 2010.
- ↑ http://www2.adb.org/Documents/PPARs/IND/22344-IND-PPAR.pdf
- ↑ https://energy.economictimes.indiatimes.com/news/power/bhel-commissions-600-megawatt-thermal-power-plant-in-andhra-pradesh/63298985