Machai Hydropower Plant

Machai Hydropower Plant
Country Pakistan
Location Machai Kalai, Mardan District, Khyber Pakhtunkhwa
Purpose Power
Status Operational
Construction began 2013
Opening date October 2017
Owner(s) Government of Khyber Pakhtunkhwa
Dam and spillways
Type of dam Gravity dam
Impounds Machai Canal
Operator(s) WAPDA
Commission date October 2017
Type Run-of-the-river
Turbines 4
Installed capacity 2.6 MW

The Machai Hydropower Plant is a run-of-the-river hydroelectric power plant with a generating capacity of 2.6 MW.[1] Construction of the damn crossing the Machai Canal began in 2013 and was completed in March 2015 at the cost of PKR 683.50 million.[2]

References

  1. "KP Govt inaugurates 2.6 MW Machai Hydropower Plant in Mardan". Peshawar Today. 13 October 2017. Retrieved 26 February 2018.
  2. "Senior Minister Sikandar Sherpao for early completion of Machai Hydro power project". Information and Public Relations Department, Government of KPK. Retrieved 26 February 2018.