Condor Cliff Dam

The Condor Cliff Dam, formerly known as Néstor Kirchner Dam, is a concrete-face rock-fill dam being built on the Santa Cruz River about 180 km (110 mi) west of Puerto Santa Cruz in Santa Cruz Province, Argentina. It was renamed after the former president Néstor Kirchner, born in Santa Cruz. A consortium led by China's Gezhouba Group was awarded the contract to build the Néstor Kirchner Dam and Jorge Cepernic Dam downstream in August 2013. The consortium will also fund the construction. Both dams are expected to cost nearly US$4.8 billion.[1] It will be built by the firm Electroingeniería, led by Osvaldo Acosta and Gerardo Ferreyra.[2] The primary purpose of the dam is hydroelectric power generation and its power station will have an installed capacity of 1,140 megawatts (1,530,000 hp).[3]

Néstor Kirchner Dam
Location of Néstor Kirchner Dam in Argentina
CountryArgentina
LocationPuerto Santa Cruz, Santa Cruz Province
Coordinates50°12′41.67″S 70°46′30.29″W
PurposePower
StatusUnder construction
Construction beganJuly 2015
Dam and spillways
Type of damEmbankment, concrete-face rock-fill
ImpoundsSanta Cruz River
Height75.5 m (248 ft)
Length2,780 m (9,120 ft)
Dam volume14,100,000 m3 (18,400,000 cu yd)
Reservoir
Total capacity6,260×10^6 m3 (5,080,000 acre⋅ft)
Surface area275 km2 (106 sq mi)
Hydraulic head64.47 m (211.5 ft)
Turbines6 x 190 MW (250,000 hp) Francis-type
Installed capacity1,140 MW (1,530,000 hp)
Annual generation3,380 GWh (12,200 TJ) (estimated)

In July 2015 machines arrived in Santa Cruz for the construction of the dams.[4]